Ruchira Projects Pvt Ltd
Sy no,12/2, Bandapura Village, Bidaralli Hobli
Approved
5th Jun 2018
Completed
24th Jan 2023
Registration No.
PRM/KA/RERA/1251/446/PR/180605/001876
Acknowledgement No.
ACK/KA/RERA/1251/446/PR/180501/002209
Project Type
Residential/Group Housing
Approving Authority
BDA - Bangalore Development Authority
District
Bengaluru Urban
Taluka
Bengaluru East
State
Karnataka
| Project Name | Ruchira Iris |
| Project Description | Ruchira Iris is the high rise BDA project from Ruchira Projects Pvt Ltd located in Bandapura near Safal Market in Whitefield - Hoskote Main Road. Ruchira Iris is B+G+11 floors, which has total 2 blocks and 207, 2 and 3 BHK flats. |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| Project Start Date | 25-04-2018 |
| Proposed Project Completion Date | 24-01-2023 |
| Total Area Of Land (Sq Mtr) | 12949 |
| Total Coverd Area (Sq Mtr) | 11093 |
| Total Open Area (Sq Mtr) | 7812 |
| Estimated Cost of Construction (INR) | 550000000 |
| Cost of Land (INR) | 0 |
| Total Project Cost (INR) | 550000000 |
| Project Address | Sy no,12/2, Bandapura Village, Bidaralli Hobli |
| District | Bengaluru Urban |
| Taluk | Bengaluru East |
| Approving Authority | BDA - Bangalore Development Authority |
| No of Garage for Sale | 238 |
| Area of Garage for Sale (Sq Mtr) | 9135 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Road System | Local Authority |
| Water Supply | Local Authority |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Self Development |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Self Development |
| Bank Name | Axis Bank |
| Branch | Whitefield Road |
| ifscCode | UTIB0002177 |
| Account No.(70% Account) | 917020070122582 |
| State | Karnataka |
| Name | Badami Projects & Contracts india pvt ltd |
| Address | #30 BTM 1st Stage 2 Main Maruti Layout,Bannergatta Road |
| Pin Code | 560029 |
| Year Of Establishment | 2001 |
| Number of Project Completed | 60 |
| Reg. Of COA No. | CA/2009/45804 |
| Local Authority Licence Number | BCC/BL-3.6/E-3454/2010-11 |
| Number Of Project Completed | 12 |
| Promoter Type | Company |
| Name | Ramanjulu Goniguntla |
| PAN Number | AAGCR9701A |
| Address | Sy. No. 279/1B1 & 279/1A, Katha Serial No. 857/810 Kadugodi Village, Bidarahalli Hobli Bangalore Bangalore KA 560067 |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560066 |
| Company Registration No. | 75175 |
| Project Name | Ruchira Lilium |
| Project Description | Ruchira Lilium, Kadukodi, Bangalore RERA number - PR/KN/170802/000996 |
| Current Status | Ongoing |
| Type of Land | Residential |
| Expected Completion Date | 30-06-2018 |
| Pin Code | 560067 |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 08-08-2018 | 16-10-2018 |
| 2 | Foundation footing work | Yes | 16-10-2018 | 31-12-2018 |
| 3 | Retaining wall (All types) | Yes | 16-10-2018 | 15-12-2018 |
| 4 | Plinth level Beam | Yes | 01-01-2019 | 15-01-2019 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 15-12-2018 | 17-01-2019 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | Yes |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | Yes |
| 11 | Education/Health/Other public amenities |
| WebSite Link 1 | www.ruchiraprojects.com |
| Agent Registration No 1 | Diligent Enterprises |
| FAR Sanctioned | 2.25 |
| Number of Towers | 2 |
| 0 | 0 |
| 1 | 9 |
| 2 | 9 |
| 3 | 9 |
| 4 | 9 |
| 5 | 9 |
| 6 | 9 |
| 7 | 9 |
| 8 | 9 |
| 9 | 9 |
| 10 | 9 |
| 11 | 9 |
| 12 | 9 |
| Total No of Units | 207 |
| Project Start Date | 25-04-2018 |
| Project End Date | 24-01-2023 |
| If any extension of time has been granted | NO |
| Cost of land | 0 |
| Cost of construction | 550000000 |
| Total project cost | 550000000 |
| Total amount collected from buyers | 760806946 |
| Whether any loan has been raised | YES |
| Total amount spent for completion of the project | 580358326 |
| Balance amount with the promoter | 334376 |
| Total number of Flats/Apartments of the Project | 207 |
| Total number of Flats/Apartments sold | 125 |
| Total number of Flats/Apartments Unsold | 7 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 09-03-2022 |
| Appeals / FNH | NO APPEALS / FNH |