SAI METRO CITY 7TH PHASE
SAI RENIIT PROJECTS PRIVATE LTD
SY NO 26/6, 33/2,34/2,39/2, 88, 89,90/1 & 95/1 OF CHIKKANAHALLI KAMANAHALLI VILLAGE, SARJAPURA HOBLI, ANEKAL TALUK BANGALORE URBAN DISTRICT, BANGALORE
Approved
7th Sept 2021
Completed
31st Dec 2021
Registration No.
PRM/KA/RERA/1251/308/PR/210907/004295
Acknowledgement No.
ACK/KA/RERA/1251/308/PR/201214/004446
Project Type
Plotted Development
Approving Authority
Local Planing Authority
District
Bengaluru Urban
Taluka
Anekal
State
Karnataka
Project Details
| Project Name | SAI METRO CITY 7TH PHASE |
| Project Description | RESIDENTIAL VACANT SITES CONSISTING OF AMENITIE VIZ ROADS, PARK, STP, OVERHEAD TANK, SUMP, CHILDREN PLAY AREA, WATER, ELECTRICITY & SANITARY, STREET LIGHT, AND SECURITY PROVIDED |
| Project Type | Plotted Development |
| Project Status | Completed |
| Project Start Date | 01-09-2020 |
| Proposed Project Completion Date | 31-12-2021 |
| Total Area Of Land (Sq Mtr) | 26810 |
| Total Coverd Area (Sq Mtr) | 14654 |
| Total Open Area (Sq Mtr) | 12156 |
| Estimated Cost of Construction (INR) | 53387925 |
| Cost of Land (INR) | 88498655 |
| Total Project Cost (INR) | 141886580 |
| Project Address | SY NO 26/6, 33/2,34/2,39/2, 88, 89,90/1 & 95/1 OF CHIKKANAHALLI KAMANAHALLI VILLAGE, SARJAPURA HOBLI, ANEKAL TALUK BANGALORE URBAN DISTRICT, BANGALORE |
| District | Bengaluru Urban |
| Taluk | Anekal |
| Approving Authority | Local Planing Authority |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Extent of development carried till date | 95 % |
| Extent of development pending | 5 % |
| Total amount of money collected from allottee | 0 |
| Total amount of money used for development of project | 50718528 |
| Total amount of balance maney lying with promoter | 0 |
| Is Any Subsequent Modification in Plan | No |
| Is Delay in the Project | No |
| No of Month Delay | 0 |
| Type of Inventory | 22 SITES 12.19 X 9.14 & 76 ODD SITES |
| No of Inventory | 98 |
| Carpet Area (Sq Mtr) | 14654SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0SqMtr |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Self Development |
| Solid Waste Management And Disposal | Local Authority |
| Fire Fighting facility | Local Authority |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Local Authority |
| PROJECT CONSISTS OF RESIDENTIAL | Self Development |
| Bank Name | Axis Bank |
| Branch | HSR K T BRANCH |
| ifscCode | UTIB0004823 |
| Account No.(70% Account) | 921020032293483 |
| State | Karnataka |
| Name | MR. SUBRAMANIAM (SHREE VENKTESHWARA CONSTRUCTIONS)ESHWARA |
| Address | NEAR SARJAPRUA SUBREIGISTRAR OFFICE OFFICE,60TH CROSS, RENUKANAGAR |
| Pin Code | 562125 |
| Year Of Establishment | 2010 |
| Number of Project Completed | 10 |
| Reg. Of COA No. | BCC/BL-36/S-1299-10-11 |
| Local Authority Licence Number | BCC/BL-36/S-1299-10-11 |
| Number Of Project Completed | 02 |
Promoter Details
| Promoter Type | Company |
| Name | K MUNIKRISHNAPPA |
| PAN Number | AAE******* |
| Address | CHIKKANAHALLI- KAMMANHALLI & KUGUR VILLAGE SARJAPURA HOBLI ANEKAL TALUK |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560102 |
| Company Registration No. | U70100KA2013PTC072016 |
| Project Name | SAI METRO CITY 6THPHASE |
| Project Description | VACANT RESIDENTIAL AROUND 72 SITES CONSISTING OF ROAD, PARK, STP, CHILDRENS PLAY AREA, ELECTRICITY & WATER CONNECTION, OVERHEAD TANK STREET LIGHT WITH ALROUND SECURITY PROVIDED THEREIN |
| Current Status | Ongoing |
| Type of Land | Plotted Development |
| Expected Completion Date | 31-12-2022 |
| Pin Code | 562125 |
| Sl No. |
Modification Plan Details
| Type of Inventory | 22 SITES 12.19 X 9.14 & 76 ODD SITES |
| No of Inventory | 98 |
| Carpet Area (Sq Mtr) | 14654 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
Residential Plot Details
| Sl No. | Plot No. | Plot Type | Plot Size | Plot Area | Phase | Stage | North Dimension | South Dimension | East Dimension | West Dimension | North Schedule Dimension | South Schedule Dimension | East Schedule Dimension | West Schedule Dimension |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 1 | Residential | odd | 1323 | VII Phase | completed | 14.16 | 14.76 | 8.49 | 8.62 | Approved Layout | Site No.2 | 24m road | pvt property of sy.no.39/1 |
| 2 | 2 | Residential | odd | 1459 | VII Phase | completed | 14.76 | 15.19 | 9.14 | 9.16 | Site No.1 | Site No.3 | 24m road | pvt property of sy.no.39/1 |
| 3 | 3 | Residential | odd | 1505 | VII Phase | completed | 15.19 | 15.52 | 9.14 | 9.15 | Site No.2 | 9.14m road | 24m road | pvt property of sy.no.39/1 |
| 4 | 4 | Residential | odd | 1596 | VII Phase | completed | 15.98 | 16.44 | 9.14 | 9.16 | 9.14m road | Site No.5 | 24m road | pvt property of sy.no.39/1 |
| 5 | 5 | Residential | odd | 1641 | VII Phase | completed | 16.44 | 16.9 | 9.14 | 9.16 | Site No.4 | Approved Layout | 24m road | pvt property of sy.no.39/1 |
| 6 | 6 | Residential | odd | 1226 | VII Phase | completed | 12.46 | 12.46 | 9.06 | 9.14 | Site No.7 | Approved Layout | Site No.8 | 24m road |
| 7 | 7 | Residential | odd | 1226 | VII Phase | completed | 12.46 | 12.46 | 9.14 | 9.14 | 9.14m road | Site No.6 | Site No.8 | 24m road |
| 8 | 8 | Residential | odd | 1680 | VII Phase | completed | 9 | 8.07 | 18.33 | 18.2 | 9.14m road | Approved Layout | pvt property of sy.no.39/2 | Site No.6 and 7 |
| 9 | 9 | Residential | odd | 1610 | VII Phase | completed | 8.8 | 7.56 | 18.34 | 18.29 | Site No.12 | 9.14m road | pvt property of sy.no.39/2 | Site No.10 and 11 |
| 10 | 10 | Residential | odd | 1414 | VII Phase | completed | 14.36 | 14.36 | 9.14 | 9.14 | Site No.11 | 9.14m road | Site No.9 | 24m road |
| 11 | 11 | Residential | odd | 1414 | VII Phase | completed | 14.36 | 14.36 | 9.14 | 9.14 | Site No.12 | Site No.10 | Site No.9 | 24m road |
| 12 | 12 | Residential | odd | 3080 | VII Phase | completed | 26.32 | 23.16 | 11.99 | 9.11 | Approved Layout | Site No.9 and 11 | pvt property of sy.no.39/2 | 24m road |
| 13 | 13 | Residential | odd | 7799 | VII Phase | completed | 20.2 | 20.65 | 41.77 | 33.76 | pvt property of sy.no.96 | 18m road | pvt property of sy.no.95/3 | pvt property of sy.no.95/2 |
| 14 | 14 | Residential | odd | 1939 | VII Phase | completed | 13.04 | 17 | 11.28 | 13.06 | 18 m road | Site No.15 | 30m intermediate road | pvt property of sy.no.82 |
| 15 | 15 | Residential | odd | 1818 | VII Phase | completed | 17 | 19.94 | 9.14 | 9.61 | Site No.14 | Site No.16 | 30m intermediate road | pvt property of sy.no.82 |
| 16 | 16 | Residential | odd | 2108 | VII Phase | completed | 19.94 | 22.89 | 9.14 | 9.61 | Site No.15 | Site No.17 | 30m intermediate road | pvt property of sy.no.82 |
| 17 | 17 | Residential | odd | 2357 | VII Phase | completed | 22.89 | 24.35 | 9.26 | 9.61 | Site No.16 | Site No.18 | 30m intermediate road | pvt property of sy.no.82 |
| 18 | 18 | Residential | odd | 3707 | VII Phase | completed | 24.35 | 23.87 | 19.59 | 9.61 | Site No.17 | pvt property of sy.no.87 | 9.14m road | pvt property of sy.no.82 |
| 19 | 19 | Residential | odd | 2237 | VII Phase | completed | 14.84 | 10.11 | 16.87 | 16.41 | 9.14m road | pvt property of sy.no.89 | Site No.20 and pvt property of sy.no.90/2 | 30m road |
| 20 | 20 | Residential | 9.14m x 12.19 m | 1200 | VII Phase | completed | 9.14 | 9.14 | 12.19 | 12.19 | 9.14m road | pvt property of sy.no.90/2 | Site No.21 | Site No.19 |
| 21 | 21 | Residential | 9.14m x 12.19 m | 1200 | VII Phase | completed | 9.14 | 9.14 | 12.19 | 12.19 | 9.14m road | pvt property of sy.no.90/2 | Site No.22 | Site No.20 |
| 22 | 22 | Residential | 9.14m x 12.19 m | 1200 | VII Phase | completed | 9.14 | 9.14 | 12.19 | 12.19 | 9.14m road | pvt property of sy.no.90/2 | Site No.23 | Site No.21 |
| 23 | 23 | Residential | 9.14m x 12.19 m | 1200 | VII Phase | completed | 9.14 | 9.14 | 12.19 | 12.19 | 9.14m road | pvt property of sy.no.90/2 | Site No.24 | Site No.22 |
| 24 | 24 | Residential | 9.14m x 12.19 m | 1200 | VII Phase | completed | 9.14 | 9.14 | 12.19 | 12.19 | 9.14m road | pvt property of sy.no.90/2 | Site No.25 | Site No.23 |
| 25 | 25 | Residential | 9.14m x 12.19 m | 1200 | VII Phase | completed | 9.14 | 9.14 | 12.19 | 12.19 | 9.14m road | pvt property of sy.no.90/2 | Site No.26 | Site No.24 |
| 26 | 26 | Residential | 9.14m x 12.19 m | 1200 | VII Phase | completed | 9.14 | 9.14 | 12.19 | 12.19 | 9.14m road | pvt property of sy.no.90/2 | Site No.27 | Site No.25 |
| 27 | 27 | Residential | 9.14m x 12.19 m | 1200 | VII Phase | completed | 9.14 | 9.14 | 12.19 | 12.19 | 9.14m road | pvt property of sy.no.90/2 | Site No.28 | Site No.26 |
| 28 | 28 | Residential | 9.14m x 12.19 m | 1200 | VII Phase | completed | 9.14 | 9.14 | 12.19 | 12.19 | 9.14m road | pvt property of sy.no.90/2 | Site No.29 | Site No.27 |
| 29 | 29 | Residential | 9.14m x 12.19 m | 1200 | VII Phase | completed | 9.14 | 9.14 | 12.19 | 12.19 | 9.14m road | pvt property of sy.no.90/2 | Site No.30 | Site No.28 |
| 30 | 30 | Residential | odd | 1005 | VII Phase | completed | 6.03 | 9.28 | 12.62 | 12.19 | 9.14m road | pvt property of sy.no.90/2 | 3m pathway | Site No.29 |
| 31 | 31 | Residential | odd | 1101 | VII Phase | completed | 5.55 | 9.16 | 14.7 | 13.48 | 18m road | 9.14m road | Road | Site No.32 |
| 32 | 32 | Residential | odd | 1313 | VII Phase | completed | 9.15 | 9.14 | 13.48 | 13.28 | 18m road | 9.14m road | Site No.31 | Site No.33 |
| 33 | 33 | Residential | odd | 1287 | VII Phase | completed | 9.15 | 9.14 | 13.28 | 13.02 | 18m road | 9.14m road | Site No.32 | Site No.34 |
| 34 | 34 | Residential | odd | 1261 | VII Phase | completed | 9.15 | 9.14 | 13.02 | 12.76 | 18m road | 9.14m road | Site No.33 | Site No.35 |
| 35 | 35 | Residential | odd | 1236 | VII Phase | completed | 9.15 | 9.14 | 12.76 | 12.5 | 18m road | 9.14m road | Site No.34 | Site No.36 |
| 36 | 36 | Residential | odd | 1210 | VII Phase | completed | 9.15 | 9.14 | 12.5 | 12.24 | 18m road | 9.14m road | Site No.35 | Site No.37 |
| 37 | 37 | Residential | odd | 1185 | VII Phase | completed | 9.15 | 9.14 | 12.24 | 11.98 | 18m road | 9.14m road | Site No.36 | Site No.38 |
| 38 | 38 | Residential | odd | 1192 | VII Phase | completed | 9.15 | 9.14 | 11.98 | 12.21 | 18m road | 9.14m road | Site No.37 | Site No.39 |
| 39 | 39 | Residential | odd | 1238 | VII Phase | completed | 9.16 | 9.14 | 12.21 | 12.68 | 18m road | 9.14m road | Site No.38 | Site No.40 |
| 40 | 40 | Residential | odd | 1284 | VII Phase | completed | 9.16 | 9.14 | 12.68 | 13.14 | 18m road | 9.14m road | Site No.39 | Site No.41 |
| 41 | 41 | Residential | odd | 2338 | VII Phase | completed | 17.69 | 14.37 | 13.14 | 14.48 | 18m road | 9.14m road | Site No.40 | 30m intermediate road |
| 42 | 42 | Residential | odd | 2249 | VII Phase | completed | 12.19 | 12.28 | 16.49 | 17.69 | Site No.43 | 24m road | 9.14m road | 3m pathway |
| 43 | 43 | Residential | 9.14m x 12.19 m | 1200 | VII Phase | completed | 12.19 | 12.19 | 9.14 | 9.14 | Site No.44 | Site No.42 | 9.14m road | 3m pathway |
| 44 | 44 | Residential | 9.14m x 12.19 m | 1200 | VII Phase | completed | 12.19 | 12.19 | 9.14 | 9.14 | Site No.45 | Site No.43 | 9.14m road | 3m pathway |
| 45 | 45 | Residential | 9.14m x 12.19 m | 1200 | VII Phase | completed | 12.19 | 12.19 | 9.14 | 9.14 | Site No.46 | Site No.44 | 9.14m road | 3m pathway |
| 46 | 46 | Residential | 9.14m x 12.19 m | 1200 | VII Phase | completed | 12.19 | 12.19 | 9.14 | 9.14 | Site No.47 | Site No.45 | 9.14m road | 3m pathway |
| 47 | 47 | Residential | odd | 1255 | VII Phase | completed | 12.25 | 12.19 | 9.93 | 9.14 | 9.14m road | Site No.46 | 9.14m road | 3m pathway |
| 48 | 48 | Residential | odd | 1930 | VII Phase | completed | 19.7 | 20.2 | 8.84 | 9.34 | Site No.49 | 9.14m road | 9.14m road | Approved Layout |
| 49 | 49 | Residential | odd | 1915 | VII Phase | completed | 19.21 | 19.7 | 9.14 | 9.16 | Site No.50 | Site No.48 | 9.14m road | Approved Layout |
| 50 | 50 | Residential | odd | 1867 | VII Phase | completed | 18.72 | 19.21 | 9.14 | 9.16 | Site No.51 | Site No.49 | 9.14m road | Approved Layout |
| 51 | 51 | Residential | odd | 1519 | VII Phase | completed | 18.32 | 18.72 | 7.62 | 7.63 | Site No.52 | Site No.50 | 9.14m road | Approved Layout |
| 52 | 52 | Residential | odd | 1451 | VII Phase | completed | 17.92 | 18.32 | 6.99 | 7.9 | Approved Layout | Site No.51 | 9.14m road | Approved Layout |
| 53 | 53 | Residential | odd | 1242 | VII Phase | completed | 10.1 | 9.48 | 11.29 | 12.34 | Approved Layout | 9.14m road | Approved Layout | 9.14m road |
| 54 | 54 | Residential | odd | 1045 | VII Phase | completed | 8.95 | 8.29 | 11.53 | 11.04 | 9.14m road | Site No.55 | Approved Layout | 9.14m road |
| 55 | 55 | Residential | odd | 1115 | VII Phase | completed | 12.19 | 12.19 | 8.6 | 8.55 | Site No.54 and approved layout | 9.14m road | Site No.56 | 9.14m road |
| 56 | 56 | Residential | odd | 1166 | VII Phase | completed | 12.22 | 12.25 | 9.17 | 8.6 | Approved Layout | 9.14m road | Site No.57 | Site No.55 |
| 57 | 57 | Residential | odd | 924 | VII Phase | completed | 9.16 | 9.11 | 9.6 | 9.17 | Approved Layout | 9.14m road | Site No.58 | Site No.56 |
| 58 | 58 | Residential | odd | 1069 | VII Phase | completed | 9.81 | 10.21 | 10.06 | 9.6 | Approved Layout | 9.14m road | 12.19m road | Site No.57 |
| 59 | 59 | Residential | odd | 1431 | VII Phase | completed | 12.19 | 12.21 | 11.19 | 10.62 | Approved Layout | 9.14m road | Site No.60 | 12.19m road |
| 60 | 60 | Residential | odd | 1661 | VII Phase | completed | 13.27 | 13.58 | 11.82 | 11.19 | Approved Layout | 9.14m road | 9.14m road | Site No.59 |
| 61 | 61 | Residential | odd | 1644 | VII Phase | completed | 12.2 | 12.22 | 12.81 | 12.24 | Approved Layout | 9.14m road | Site No.62 | 9.14m road |
| 62 | 62 | Residential | odd | 2099 | VII Phase | completed | 14.83 | 14.86 | 13.5 | 12.81 | Approved Layout | 9.14m road | 9.14m road | Site No.61 |
| 63 | 63 | Residential | odd | 2038 | VII Phase | completed | 12.64 | 12.22 | 18.13 | 13.92 | Approved Layout | 9.14m road | Site No.64 and 65 | 9.14m road |
| 64 | 64 | Residential | odd | 2435 | VII Phase | completed | 19.16 | 17.92 | 16.74 | 8.57 | Approved Layout | Site No.65 | 9.14m road | Site No.61 |
| 65 | 65 | Residential | odd | 1840 | VII Phase | completed | 17.92 | 17.92 | 9.56 | 9.56 | Site No.64 | 9.14m road | 9.14m road | Site No.63 |
| 66 | 66 | Residential | odd | 1661 | VII Phase | completed | 0 | 9.85 | 32.66 | 30.55 | Approved Layout | 9.14m road | Approved Layout | 9.14m road |
| 67 | 67 | Residential | odd | 1907 | VII Phase | completed | 12.12 | 16.81 | 13.13 | 12.25 | 9.14m road | Site No.68 | Approved Layout | 9.14m road |
| 68 | 68 | Residential | odd | 2249 | VII Phase | completed | 16.81 | 21.03 | 11.84 | 11.1 | Site No.67 | Approved Layout | Approved Layout | 9.14m road |
| 69 | 69 | Residential | odd | 1806 | VII Phase | completed | 12.19 | 12.19 | 13.76 | 13.76 | 9.14m road | Site No.70 | 9.14m road | Site No.72 |
| 70 | 70 | Residential | odd | 1252 | VII Phase | completed | 12.19 | 12.19 | 9.54 | 9.56 | Site No.69 | Approved Layout | 9.14m road | Site No.71 |
| 71 | 71 | Residential | odd | 1252 | VII Phase | completed | 12.2 | 12.2 | 9.56 | 9.54 | Site No.72 | Approved Layout | Site No.70 | 9.14m road |
| 72 | 72 | Residential | odd | 1807 | VII Phase | completed | 12.2 | 12.2 | 13.76 | 13.76 | 9.14m road | Site No.71 | Site No.69 | 9.14m road |
| 73 | 73 | Residential | odd | 1806 | VII Phase | completed | 12.19 | 12.19 | 13.76 | 13.76 | 9.14m road | Site No.74 | 9.14m road | Site No.76 |
| 74 | 74 | Residential | odd | 1252 | VII Phase | completed | 12.19 | 12.19 | 9.54 | 9.56 | Site No.73 | Approved Layout | 9.14m road | Site No.75 |
| 75 | 75 | Residential | odd | 1252 | VII Phase | completed | 12.2 | 12.2 | 9.56 | 9.54 | Site No.76 | Approved Layout | Site No.74 | 9.14m road |
| 76 | 76 | Residential | odd | 1807 | VII Phase | completed | 12.2 | 12.2 | 13.76 | 13.76 | 9.14m road | Site No.75 | Site No.73 | 9.14m road |
| 77 | 77 | Residential | odd | 1806 | VII Phase | completed | 12.19 | 12.19 | 13.76 | 13.76 | 9.14m road | Site No.78 | 9.14m road | Site No.80 |
| 78 | 78 | Residential | odd | 1252 | VII Phase | completed | 12.19 | 12.19 | 9.54 | 9.56 | Site No.77 | Approved Layout | 9.14m road | Site No.79 |
| 79 | 79 | Residential | odd | 1252 | VII Phase | completed | 12.2 | 12.2 | 9.56 | 9.54 | Site No.80 | Approved Layout | Site No.78 | 9.14m road |
| 80 | 80 | Residential | odd | 1807 | VII Phase | completed | 12.2 | 12.2 | 13.76 | 13.76 | 9.14m road | Site No.79 | Site No.77 | 9.14m road |
| 81 | 81 | Residential | odd | 2258 | VII Phase | completed | 15.24 | 15.24 | 13.76 | 13.76 | 9.14m road | Site No.82 | 9.14m road | Site No.84 |
| 82 | 82 | Residential | odd | 1564 | VII Phase | completed | 15.24 | 15.24 | 9.54 | 9.56 | Site No.81 | Approved Layout | 9.14m road | Site No.83 |
| 83 | 83 | Residential | odd | 1548 | VII Phase | completed | 14.79 | 15.4 | 9.56 | 9.55 | Site No.84 | Approved Layout | Site No.82 | 9.14m road |
| 84 | 84 | Residential | odd | 2121 | VII Phase | completed | 13.86 | 14.79 | 13.76 | 13.79 | 9.14m road | Site No.83 | Site No.81 | 9.14m road |
| 85 | 85 | Residential | odd | 1533 | VII Phase | completed | 12.22 | 12.19 | 12.07 | 11.29 | 9.14m road | Site No.86 | 9.14m road | Site No.96 |
| 86 | 86 | Residential | 9.14m x 12.19 m | 1200 | VII Phase | completed | 12.19 | 12.19 | 9.14 | 9.14 | Site No.85 | Site No.87 | 9.14m road | Site No.95 |
| 87 | 87 | Residential | 9.14m x 12.19 m | 1200 | VII Phase | completed | 12.19 | 12.19 | 9.14 | 9.14 | Site No.86 | Site No.88 | 9.14m road | Site No.94 |
| 88 | 88 | Residential | 9.14m x 12.19 m | 1200 | VII Phase | completed | 12.19 | 12.19 | 9.14 | 9.14 | Site No.87 | Site No.89 | 9.14m road | Site No.93 |
| 89 | 89 | Residential | 9.14m x 12.19 m | 1200 | VII Phase | completed | 12.19 | 12.19 | 9.14 | 9.14 | Site No.88 | Site No.90 | 9.14m road | Site No.92 |
| 90 | 90 | Residential | odd | 1808 | VII Phase | completed | 12.19 | 12.25 | 13.18 | 14.38 | Site No.89 | 24m road | 9.14m road | Site No.91 |
| 91 | 91 | Residential | odd | 1966 | VII Phase | completed | 12.19 | 12.25 | 14.38 | 15.58 | Site No.92 | 24m road | Site No.90 | 9.14m road |
| 92 | 92 | Residential | 9.14m x 12.19 m | 1200 | VII Phase | completed | 12.19 | 12.19 | 9.14 | 9.14 | Site No.93 | Site No.91 | Site No.89 | 9.14m road |
| 93 | 93 | Residential | 9.14m x 12.19 m | 1200 | VII Phase | completed | 12.19 | 12.19 | 9.14 | 9.14 | Site No.94 | Site No.92 | Site No.88 | 9.14m road |
| 94 | 94 | Residential | 9.14m x 12.19 m | 1200 | VII Phase | completed | 12.19 | 12.19 | 9.14 | 9.14 | Site No.95 | Site No.93 | Site No.87 | 9.14m road |
| 95 | 95 | Residential | 9.14m x 12.19 m | 1200 | VII Phase | completed | 12.19 | 12.19 | 9.14 | 9.14 | Site No.96 | Site No.94 | Site No.86 | 9.14m road |
| 96 | 96 | Residential | odd | 1431 | VII Phase | completed | 12.22 | 12.19 | 11.29 | 10.13 | 9.14m road | Site No.95 | Site No.85 | 9.14m road |
| 97 | 97 | Residential | odd | 2000 | VII Phase | completed | 13.93 | 14.4 | 12.65 | 15.4 | 9m road | Approved Layout | Site No.98 | 9.14m road |
| 98 | 98 | Residential | odd | 2277 | VII Phase | completed | 12.35 | 9.2 | 17.2 | 24.45 | 9m road | 12m road | Approved Layout | Site No.97 and approved layout |
Project Development Schedule
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Ground Clearance/Formation Of Plots | Yes | 01-09-2020 | 04-10-2020 |
| 2 | Formation Of Road, Footpath | Yes | 30-01-2021 | 03-05-2021 |
| 3 | Construction Of WaterSupply Infrastucture | Yes | 28-10-2020 | 05-11-2020 |
| 4 | Construction Of Sewage System Infrastucture | Yes | 05-10-2020 | 27-10-2020 |
| 5 | Power Supply Work(Tansformer And Substation) | Yes | 30-12-2020 | 03-04-2021 |
| 6 | Construction Of Storm Water Drainage | Yes | 06-11-2020 | 28-03-2021 |
| 7 | Solid Waste Management and Disposal | Yes | 30-03-2021 | 25-05-2021 |
| 8 | Tree Plantation And LandScape Work | Yes | 12-04-2021 | 20-04-2021 |
| 9 | Street Lighting | Yes | 20-03-2021 | 30-03-2021 |
| 10 | Other Miscellaneous Work | Yes | 28-06-2021 | 03-08-2021 |
Amenities & Utilities Availability
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Electricity | Yes |
| 2 | Smart home automation | No |
| 3 | CCTV surveillance | Yes |
| 4 | Club House | No |
| 5 | Community Hall | No |
| 6 | Outdoor Sports facility | No |
| 7 | Indoor sports facility | No |
| 8 | Swimming Pools | No |
| 9 | Gym | No |
| 10 | Parks | No |
| 11 | Power Backup | No |
| 12 | Gas | No |
| 13 | Water and Sanitation | Yes |
| 14 | Air conditioning and incarnation | No |
Post Registration Details
| WebSite Link 1 | www.saireniit.co.in |
| Agent Registration No 1 | N.A. |
| Total number of Plots | 98 |
| No. of Public and Semi Pubic Sites | 0 |
| Area of Public and Semi Pubic Sites(in Sq.m) | 0 |
| No. of Parks and Open Spaces | 0 |
| Area of Parks and Open Spaces(in Sq.m) | 0 |
| Area of Road/Transportation(in Sq.m) | 12155 |
Completion Details
| Project Start Date | 01-09-2020 |
| Project End Date | 31-12-2021 |
| If any extension of time has been granted | NO |
| Cost of land | 88498655 |
| Cost of construction | 53387925 |
| Total cost | 141886580 |
| Total amount collected From buyers | 228077652 |
| Whether any loan has been raised | YES |
| Total amount spent on Project for completion of the project | 141886580 |
| Total No of sites of Project | 98 |
| Total No of sites sold | 66 |
| Total No of sites unsold | 32 |
| Whether there is any changes in inventory details | NO |
Appeals & Complaints
| Complaints on Project | No Complaints Found. |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in