Project Details

Number of Survey No./CMC No./CTS No./PID No.2
Is there any Litigations on Land/Property/Khatha?NO

Promoter Details

Type of FirmProprietorship
Promoter NameSOMASHEKHAR K M
Main ObjectivesPLOTTED DEVELOPMENT OF 31 PLOTS
Trade NameSOMASHEKHAR K M
Registration Number000
PANASQPK6078C
GSTIN00000
Promoter Address#15, SARJAPURA MAIN ROAD, NEAR BSNL OFFICE, ,DODDAKANNEHALLI ,Bengaluru East ,Bengaluru Urban-560035
DistrictBengaluru Urban
TalukBengaluru East
PIN Code560035
Name of Authorized SignatorySOMASHEKHAR K M
Is there any RERA Registrations in other State / UT ?NO
Is there any Projects Launched In The Past 5 Years in Karnataka ?NO
Present Address#15, SARJAPURA MAIN ROAD, NEAR BSNL OFFICE, DODDAKANNEHALLI , Bengaluru Urban , Karnataka - 560035
Permanent Address#15, SARJAPURA MAIN ROAD, NEAR BSNL OFFICE, DODDAKANNEHALLI , Bengaluru Urban , Karnataka - 560035
Official Address#15, SARJAPURA MAIN ROAD, NEAR BSNL OFFICE, DODDAKANNEHALLI , Bengaluru Urban , Karnataka - 560035
Sl No.

Modification Plan Details

Type of Inventory9.14M X 15.24
No of Inventory14
Carpet Area (Sq Mtr)1950 Sq Mtr
Area of exclusive balcony/verandah (Sq Mtr)0 Sq Mtr
Area of exclusive open terrace if any (Sq Mtr)0 Sq Mtr

Residential Plot Details

Sl No.Plot No.Plot TypePlot SizePlot AreaPhaseStageNorth DimensionSouth DimensionEast DimensionWest DimensionNorth Schedule DimensionSouth Schedule DimensionEast Schedule DimensionWest Schedule Dimension
11Vacant Plot32.37*20.49661.18543291COMPLETED33.331.4420.3520.64Remaining Portion of Sy.No. 90/2Site No 2RoadRoad
22Vacant Plot30.74*15.27468.41322931COMPLETED31.4430.0415.2415.3Site No 1Site No 3 & Site No 21RoadRoad
33Vacant Plot14.37*9.16131.36380531COMPLETED14.813.959.149.18Site No 2Site No 4Site No 21Road
44Vacant Plot13.53*9.16123.65291711COMPLETED13.9513.119.149.18Site No 3Site No 5Site No 20Road
55Vacant Plot12.69*9.16116.12783351COMPLETED13.1112.279.149.18Site No 4Site No 6Site No 19Road
66Vacant Plot11.91*9.155108.9743591COMPLETED12.2711.569.149.17Site No 5Site No 7Site No 18Road
77Vacant Plot11.27*9.15103.12151621COMPLETED11.5610.989.149.16Site No 6Site No 8Site No 17Road
88Vacant Plot10.69*9.1597.826086961COMPLETED10.9810.419.149.16Site No 7Site No 9Site No 16Road
99Vacant Plot10.12*9.1592.530657751COMPLETED10.419.849.149.16Site No 8Site No 10Site No 15Road
1010Vacant Plot226.6*24.7226.6815311COMPLETED25.0824.519.149.16Site No 9 & Site No 15Site No 11RoadRoad
1111Vacant Plot221.5*24.2221.57190641COMPLETED24.5123.949.149.16Site No 10Site No 12RoadRoad
1212Vacant Plot216.4*23.6216.46228171COMPLETED23.9423.369.149.16Site No 11Site No 13 & Site No 14RoadRoad
1313Vacant Plot9.305*13.23111.48272021COMPLETED11.317.310.7113.23Site No 12RoadSite No 14Sy. No. 89
1414Vacant Plot12.21*10.68115.19881091COMPLETED12.0512.378.1610.68Site No 12RoadRoadSite No 13
1515Vacant Plot15.24*9.14139.35340021COMPLETED15.2415.249.149.14Site No 16Site No 10RoadSite No 9
1616Vacant Plot15.24*9.14139.35340021COMPLETED15.2415.249.149.14Site No 17Site No 15RoadSite No 8
1717Vacant Plot15.24*9.14139.35340021COMPLETED15.2415.249.149.14Site No 18Site No 16RoadSite No 7
1818Vacant Plot15.24*9.14139.35340021COMPLETED15.2415.249.149.14Site No 19Site No 17RoadSite No 6
1919Vacant Plot15.24*9.14139.35340021COMPLETED15.2415.249.149.14Site No 20Site No 18RoadSite No 5
2020Vacant Plot15.24*9.14139.35340021COMPLETED15.2415.249.149.14Site No 21Site No 19RoadSite No 4
2121Vacant Plot15.24*9.14139.35340021COMPLETED15.2415.249.149.14Site No 2Site No 20RoadSite No 3
2222Vacant Plot15.24*9.14139.35340021COMPLETED15.2415.249.149.14Remaining Portion of Sy.No. 90/2Site No 23Sy. No. 90/3Road
2323Vacant Plot15.24*9.14139.35340021COMPLETED15.2415.249.149.14Site No 22Site No 24Sy. No. 90/3Road
2424Vacant Plot15.24*9.14139.35340021COMPLETED15.2415.249.149.14Site No 23Site No 25Sy. No. 90/3Road
2525Vacant Plot15.24*9.14139.35340021COMPLETED15.2415.249.149.14Site No 24Site No 26Sy. No. 90/3Road
2626Vacant Plot15.24*9.14139.35340021COMPLETED15.2415.249.149.14Site No 25Site No 27Sy. No. 90/3Road
2727Vacant Plot15.24*9.14139.35340021COMPLETED15.2415.249.149.14Site No 26Site No 28Sy. No. 90/3Road
2828Vacant Plot15.24*9.14139.35340021COMPLETED15.2415.249.149.14Site No 27Site No 29Sy. No. 90/3Road
2929Vacant Plot15.23*13.11199.27536231COMPLETED15.2415.2313.1113.11Site No 28RoadSite No 30Road
3030Vacant Plot9.53*16.25154.77517651COMPLETED9.529.5416.2316.27Sy. No. 90/3RoadSite No 31Site No 29
3131Vacant Plot9.61*15.98153.66034931COMPLETED9.689.5415.9815.98Sy. No. 90/3RoadSy. No. 90/3Site No 30

Project Development Schedule

Sl NoProject WorkIs Applicable ?Estimated From DateEstimated To Date
1Ground Clearance/Formation Of PlotsYes31-12-201915-03-2022
2Formation Of Road, FootpathYes16-07-202204-06-2023
3Construction Of Water Supply InfrastuctureNo
4Construction Of Sewage System InfrastuctureYes12-05-202312-08-2023
5Power Supply Work(Transformer & Substation)Yes07-07-202330-08-2023
6Construction Of Storm Water DrainageNo
7Solid Waste Management and DisposalNo
8Tree Plantation And LandScape WorkYes13-09-202322-10-2024
9Street LightingYes15-08-202304-11-2023
10Sewage Treatment Plant (STP)Yes19-10-202330-12-2023
11Other Miscellaneous WorkYes01-03-202331-12-2025

Amenities & Utilities Availability

SlNo.WorkIs Applicable ?
1ElectricityYes
2Smart home automationNo
3CCTV surveillanceNo
4Club HouseNo
5Community HallNo
6Outdoor Sports facilityNo
7Indoor sports facilityNo
8Swimming PoolsNo
9GymNo
10ParksYes
11Power BackupNo
12Piped GasNo
13Water and SanitationYes
14Air conditioningNo

Post Registration Details

Total number of Plots31
No. of Public and Semi Pubic Sites2
Area of Public and Semi Pubic Sites(in Sq.m)28
No. of Parks and Open Spaces2
Area of Parks and Open Spaces(in Sq.m)1444
Area of Road/Transportation(in Sq.m)2909

Completion Details

Project Start Date31-12-2019
Project End Date31-12-2025
If any extension of time has been grantedNO
Cost of land428839380
Cost of construction11663762
Total cost440503142
Total amount collected From buyers0
Whether any loan has been raisedNO
Total amount spent on Project for completion of the project16663762
Total No of sites of Project31
Total No of sites sold0
Total No of sites unsold31
Whether there is any changes in inventory detailsNO

Appeals & Complaints

Complaints on PromoterNo Complaints Found.
Complaints on ProjectNo Complaints Found.

Top Properties in Bangalore

Pexo Icon

Ask Pulse Ai anything about real estate

Unlock the Latest in Real Estate

News, Infographics, Blogs & More! Delivered to your inbox.

Proptech Pulse Logo

Data that drives action.
Insight that inspires action.
Technology that empowers action.“

Made with Love

Statue

© PropTech Pulse 2026, All rights reserved.

Terms of Use and Privacy Policy