GK ENGINEERS & CONTRACTORS
#780/A, 35TH MAIN,, JPNAGAR 1ST PHASE,
Approved
20th Feb 2019
Completed
27th Nov 2021
Registration No.
PRM/KA/RERA/1251/310/PR/190220/002439
Acknowledgement No.
ACK/KA/RERA/1251/310/PR/190201/003005
Project Type
Residential/Group Housing
Approving Authority
BBMP - Bruhat Bengaluru Mahanagara Palike
District
Bengaluru Urban
Taluka
Bengaluru South
State
Karnataka
| Project Name | SHREE SAI ANUGRAHA APARTMENTS |
| Project Description | STILT PLUS THREE UPPER FLOORS. WITH 10NOS OF 3BHK FLATS. |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| Project Start Date | 01-12-2018 |
| Proposed Project Completion Date | 27-11-2021 |
| Total Area Of Land (Sq Mtr) | 611 |
| Total Coverd Area (Sq Mtr) | 395 |
| Total Open Area (Sq Mtr) | 216 |
| Estimated Cost of Construction (INR) | 35000000 |
| Cost of Land (INR) | 90000000 |
| Total Project Cost (INR) | 125000000 |
| Project Address | #780/A, 35TH MAIN,, JPNAGAR 1ST PHASE, |
| District | Bengaluru Urban |
| Taluk | Bengaluru South |
| Approving Authority | BBMP - Bruhat Bengaluru Mahanagara Palike |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Local Authority |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Local Authority |
| Bank Name | KOTAK MAHINDRA BANK |
| Branch | JP NAGAR |
| ifscCode | KKBK0008043 |
| Account No.(70% Account) | 6612947313 |
| State | Karnataka |
| Promoter Type | Partnership Firm |
| Name | T.S BADREESH |
| PAN Number | AALFG7822P |
| Address | SRINIVASA KRUPA,1STCROSS,.GANDHINGAR,TUMKUR |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560002 |
| Company Registration No. | NA |
| Type | Board Member |
| Pin Code | 572101 |
| Extension Applied On | 14-02-2020 |
| Extension Approved On | 08-09-2020 |
| Extension Registration Number | EX/PRM/KA/RERA/1251/310/PR/200908/002439 |
| Proposed Project End Date at the time of registration | 28-02-2020 |
| Project End Date provided under Section 6 | 27-02-2021 |
| whether 2/3rd concern from the allottees has taken? | NO |
| Whether any compensation is provided for the Buyer? | NO |
| Document Name | Old bank statement |
| 1 | Financial crunch |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 28-02-2018 | 28-04-2018 |
| 2 | Foundation footing work | Yes | 15-03-2018 | 15-05-2018 |
| 3 | Retaining wall (All types) | No | ||
| 4 | Plinth level Beam | Yes | 16-05-2018 | 16-07-2018 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 17-07-2018 | 17-08-2018 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | No |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | No |
| 5 | Street Lighting | No |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | No |
| 7 | Solid waste management and disposal | No |
| 8 | Water conservation | Yes |
| 9 | Energy management | No |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | No |
| Agent Registration No 1 | Non |
| FAR Sanctioned | 3.0 |
| Number of Towers | 1 |
| 0 | 1 |
| 1 | 3 |
| 2 | 3 |
| 3 | 3 |
| Total No of Units | 10 |
| Project Start Date | 01-12-2018 |
| Project End Date | 27-11-2021 |
| If any extension of time has been granted | YES |
| Extended From Date | 28-02-2020 |
| Extended End Date | 27-02-2021 |
| Cost of land | 90000000 |
| Cost of construction | 35000000 |
| Total project cost | 125000000 |
| Total amount collected from buyers | 39500000 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 131960085 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 10 |
| Total number of Flats/Apartments sold | 3 |
| Total number of Flats/Apartments Unsold | 7 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 13-08-2021 |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |


Ask Pulse Ai anything about real estate
News, Infographics, Blogs & More! Delivered to your inbox.