SIGNATURE GRANDE
Bengaluru East
Approved
4th Nov 2022
Completed
31st Dec 2024
Registration No.
PRM/KA/RERA/1251/446/PR/041122/005392
Acknowledgement No.
ACK/KA/RERA/1251/446/PR/270422/005886
Project Type
Plotted Development
District
Bengaluru Urban
Taluka
Bengaluru East
State
Karnataka
| Number of Survey No./CMC No./CTS No./PID No. | 1 |
| Is there any Litigations on Land/Property/Khatha? | NO |
| Type of Firm | Partnership Firm |
| Promoter Name | SIGNATURE GRANDE |
| Main Objectives | Residential Layout Development. |
| Registration Number | SJN-F34-2021-22 |
| PAN | ALRPP5373P |
| Promoter Address | No.85, Signature Dreams,Huskur Village Bidarahalli Hobli ,Bengaluru East ,Bengaluru Urban-560049 |
| District | Bengaluru Urban |
| Taluk | Bengaluru East |
| PIN Code | 560049 |
| Name of Authorized Signatory | Challa Prashanth Reddy |
| Number of Partners | 3 |
| Is there any RERA Registrations in other State / UT ? | NO |
| Is there any Projects Launched In The Past 5 Years in Karnataka ? | NO |
| Present Address | Flat No. A-801, Tower-1, Godrej Woodsman Estate Hebbal , Bengaluru Urban , Karnataka - 560024 |
| Permanent Address | Flat No. A-801, Tower-1, Godrej Woodsman Estate Hebbal , Bengaluru Urban , Karnataka - 560024 |
| Official Address | No.85, Signature Dreams, Huskur Village Bidarahalli Hobli , Bengaluru Urban , Karnataka - 560049 |
| Sl No. | |
| Sl No._1 |
| Type of Inventory | Odd Sites |
| No of Inventory | 18 |
| Carpet Area (Sq Mtr) | 2169 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Sl No. | Plot No. | Plot Type | Plot Size | Plot Area | Phase | Stage | North Dimension | South Dimension | East Dimension | West Dimension | North Schedule Dimension | South Schedule Dimension | East Schedule Dimension | West Schedule Dimension |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 1 | residential | ODD | 139.01 | PHASE-1 | WORK UNDER PROGRESS | 11.04 | 11.04 | 12.5 | 12.55 | Land in Sy.no.65 | Road | Re-sy.no.64 | Road |
| 2 | 2 | residential | ODD | 115.81 | PHASE-1 | WORK UNDER PROGRESS | 9.22 | 9.22 | 12.55 | 12.57 | Land in Sy.no.65 | Road | Road | Site no.3 |
| 3 | 3 | residential | ODD | 115.02 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 12.57 | 12.6 | Land in Sy.no.65 | Road | Site no.2 | Site no.4 |
| 4 | 4 | residential | ODD | 115.22 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 12.6 | 12.62 | Land in Sy.no.65 | Road | Site no.3 | Site no.5 |
| 5 | 5 | residential | ODD | 115.43 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 12.62 | 12.64 | Land in Sy.no.65 | Road | Site no.4 | Site no.6 |
| 6 | 6 | residential | ODD | 115.63 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 12.64 | 12.66 | Land in Sy.no.65 | Road | Site no.5 | Site no.7 |
| 7 | 7 | residential | ODD | 115.83 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 12.66 | 12.68 | Land in Sy.no.65 | Road | Site no.6 | Site no.8 |
| 8 | 8 | residential | ODD | 116.04 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 12.68 | 12.71 | Land in Sy.no.65 | Road | Site no.7 | Site no.9 |
| 9 | 9 | residential | ODD | 116.24 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 12.71 | 12.73 | Land in Sy.no.65 | Road | Site no.8 | Site no.10 |
| 10 | 10 | residential | ODD | 116.45 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 12.73 | 12.75 | Land in Sy.no.65 | Road | Site no.9 | Site no.11 |
| 11 | 11 | residential | ODD | 116.65 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 12.75 | 12.77 | Land in Sy.no.65 | Road | Site no.10 | Site no.12 |
| 12 | 12 | residential | ODD | 116.85 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 12.77 | 12.8 | Land in Sy.no.65 | Road | Site no.11 | Site no.13 |
| 13 | 13 | residential | ODD | 117.06 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 12.8 | 12.82 | Land in Sy.no.65 | Road | Site no.12 | Site no.14 |
| 14 | 14 | residential | ODD | 117.26 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 12.82 | 12.89 | Land in Sy.no.65 | Road | Site no.13 | Site no.15 |
| 15 | 15 | residential | ODD | 117.46 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 12.89 | 12.89 | Land in Sy.no.65 | Road | Site no.14 | Site no.16 |
| 16 | 16 | residential | ODD | 117.66 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 12.89 | 12.89 | Land in Sy.no.65 | Road | Site no.15 | Road |
| 17 | 17 | residential | ODD | 167.83 | PHASE-1 | WORK UNDER PROGRESS | 10.98 | 10.98 | 15.24 | 15.24 | Road | Land in Sy.no.63 | Re-sy.no.64 | Site no.18 |
| 18 | 18 | residential | 9.14 X 15.24 | 139.29 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 15.24 | 15.24 | Road | Land in Sy.no.63 | Site no.17 | Site no.19 |
| 19 | 19 | residential | 9.14 X 15.24 | 139.29 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 15.24 | 15.24 | Road | Land in Sy.no.63 | Site no.18 | Site no.20 |
| 20 | 20 | residential | 9.14 X 15.24 | 139.29 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 15.24 | 15.24 | Road | Land in Sy.no.63 | Site no.19 | Site no.21 |
| 21 | 21 | residential | 9.14 X 15.24 | 139.29 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 15.24 | 15.24 | Road | Land in Sy.no.63 | Site no.20 | Site no.22 |
| 22 | 22 | residential | 9.14 X 15.24 | 139.29 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 15.24 | 15.24 | Road | Land in Sy.no.63 | Site no.21 | Site no.23 |
| 23 | 23 | residential | 9.14 X 15.24 | 139.29 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 15.24 | 15.24 | Road | Land in Sy.no.63 | Site no.22 | Site no.24 |
| 24 | 24 | residential | 9.14 X 15.24 | 139.29 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 15.24 | 15.24 | Road | Land in Sy.no.63 | Site no.23 | Site no.25 |
| 25 | 25 | residential | 9.14 X 15.24 | 139.29 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 15.24 | 15.24 | Road | Land in Sy.no.63 | Site no.24 | Site no.26 |
| 26 | 26 | residential | 9.14 X 15.24 | 139.29 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 15.24 | 15.24 | Road | Land in Sy.no.63 | Site no.25 | Site no.27 |
| 27 | 27 | residential | 9.14 X 15.24 | 139.29 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 15.24 | 15.24 | Road | Land in Sy.no.63 | Site no.26 | Site no.28 |
| 28 | 28 | residential | 9.14 X 15.24 | 139.29 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 15.24 | 15.24 | Road | Land in Sy.no.63 | Site no.27 | Site no.29 |
| 29 | 29 | residential | 9.14 X 15.24 | 139.29 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 15.24 | 15.24 | Road | Land in Sy.no.63 | Site no.28 | Site no.30 |
| 30 | 30 | residential | 9.14 X 15.24 | 139.29 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 15.24 | 15.24 | Road | Land in Sy.no.63 | Site no.29 | Site no.31 |
| 31 | 31 | residential | 9.14 X 15.24 | 139.29 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 15.24 | 15.24 | Road | Land in Sy.no.63 | Site no.30 | Site no.32 |
| 32 | 32 | residential | 9.14 X 15.24 | 139.29 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 15.24 | 15.24 | Road | Land in Sy.no.63 | Site no.31 | Site no.33 |
| 33 | 33 | residential | 9.14 X 15.24 | 139.29 | PHASE-1 | WORK UNDER PROGRESS | 9.14 | 9.14 | 15.24 | 15.24 | Road | Land in Sy.no.63 | Site no.32 | Road |
| 34 | 34 | residential | Odd | 117 | PHASE-1 | WORK UNDER PROGRESS | 13 | 13 | 9 | 9 | 3M Path way & Park | Land in Sy.no.63 | Road | 3M Path way & Park |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Ground Clearance/Formation Of Plots | Yes | 13-12-2021 | 30-01-2022 |
| 2 | Formation Of Road, Footpath | Yes | 13-12-2021 | 30-12-2022 |
| 3 | Construction Of Water Supply Infrastucture | Yes | 01-01-2022 | 30-12-2022 |
| 4 | Construction Of Sewage System Infrastucture | Yes | 01-01-2022 | 30-12-2022 |
| 5 | Power Supply Work(Transformer & Substation) | Yes | 01-02-2023 | 30-12-2024 |
| 6 | Construction Of Storm Water Drainage | No | ||
| 7 | Solid Waste Management and Disposal | Yes | 01-01-2022 | 01-12-2023 |
| 8 | Tree Plantation And LandScape Work | Yes | 01-01-2022 | 01-12-2023 |
| 9 | Street Lighting | Yes | 01-01-2022 | 01-12-2023 |
| 10 | Sewage Treatment Plant (STP) | Yes | 01-01-2022 | 01-12-2023 |
| 11 | Other Miscellaneous Work | No |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Electricity | Yes |
| 2 | Smart home automation | No |
| 3 | CCTV surveillance | No |
| 4 | Club House | No |
| 5 | Community Hall | No |
| 6 | Outdoor Sports facility | No |
| 7 | Indoor sports facility | No |
| 8 | Swimming Pools | No |
| 9 | Gym | No |
| 10 | Parks | Yes |
| 11 | Power Backup | No |
| 12 | Piped Gas | No |
| 13 | Water and Sanitation | Yes |
| 14 | Air conditioning | No |
| Total number of Plots | 34 |
| No. of Public and Semi Pubic Sites | 1 |
| Area of Public and Semi Pubic Sites(in Sq.m) | 406 |
| No. of Parks and Open Spaces | 1 |
| Area of Parks and Open Spaces(in Sq.m) | 811 |
| Area of Road/Transportation(in Sq.m) | 2478 |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |