SIGNATURE DWELLINGS PRIVATE LIMITED
Anekal
Approved
28th Dec 2023
Completed
31st Dec 2025
Registration No.
PRM/KA/RERA/1251/308/PR/281223/006516
Acknowledgement No.
ACK/KA/RERA/1251/308/PR/191123/007608
Project Type
Residential/Group Housing
District
Bengaluru Urban
Taluka
Anekal
State
Karnataka
| Number of Survey No./CMC No./CTS No./PID No. | 2 |
| Is there any Litigations on Land/Property/Khatha? | NO |
| Type of Firm | Company |
| Promoter Name | SIGNATURE DWELLINGS PRIVATE LIMITED |
| Main Objectives | DEVELOPMENT OF RESIDENTIAL APARTMENT BUILDING. |
| Registration Number | U70200KL2012PTC030293 |
| PAN | ADRPN3617N |
| GSTIN | 29AARCS0900K1Z1 |
| Promoter Address | Registered office at Kousthubham, No.29/208-B, Lane No.28, Janatha Road, Vytilla, Kochi-682019 Kerala,Branch office at No. 21 & 22, 3rd Floor, 1st Main Road, 1st Block, Koramangala ,Bengaluru South ,Bengaluru Urban-560034 |
| District | Bengaluru Urban |
| Taluk | Bengaluru South |
| PIN Code | 560034 |
| Name of Authorized Signatory | PRASANTH NARAYANAN |
| Name of CEO/MD | PRASANTH NARAYANAN |
| Designation | Managing Director |
| Director Identification (DIN) Number | 03548411 |
| Number of Directors | 2 |
| Is there any RERA Registrations in other State / UT ? | NO |
| Is there any Projects Launched In The Past 5 Years in Karnataka ? | YES |
| Project Name | SIGNATURE CLASSIC |
| Project Description | Residential Building |
| Type of Project | Residential |
| Current Status | Completed |
| Expected Completion Date | 31-12-2025 |
| Is there any case pending ? | NO |
| Is Payment Pertaining to Project Land Pending ? | NO |
| Project Address | Sy No 71, Sompura Village, Sarjapura Hobli, Anekal Taluk. |
| State/UT | Karnataka |
| Pin Code | 562106 |
| Present Address | 29/208B, Lane No 28, Janatha Road, Vytilla, Kochi , Ernakulam , Ernakulam , Kerala - 682019 |
| Permanent Address | 29/208B, Lane No 28, Janatha Road, Vytilla, Kochi , Ernakulam , Ernakulam , Kerala - 682019 |
| Official Address | No. 21 & 22, 3rd Floor, 1st Main Road, 1st Block, Koramangala , Bengaluru Urban , Karnataka - 560034 |
| Sl No. | |
| Sl No._1 | |
| Sl No._2 | |
| Sl No._3 |
| Type of Inventory | 3 BHK Flats |
| No of Inventory | 112 |
| Carpet Area (Sq Mtr) | 8273 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 01-11-2023 | 31-03-2024 |
| 2 | Foundation footing work | Yes | 01-12-2023 | 30-06-2024 |
| 3 | Upto Plinth Level | Yes | 01-12-2023 | 30-08-2024 |
| 4 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 01-12-2023 | 30-08-2024 |
| 5 | Retaining wall (All types) | No |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Sewage and Drainage System | Yes |
| 3 | Water conservation/rain water harvesting/recharge of ground water | Yes |
| 4 | Energy management | No |
| 5 | Fire protection and fire safety requirements | No |
| 6 | Solid waste management and disposal | No |
| 7 | Emergency Evacuation services | No |
| FAR Sanctioned | 1.74 |
| Number of Towers | 1 |
| 0 | 39 |
| 1 | 39 |
| 2 | 39 |
| 3 | 39 |
| Total No of Units | 156 |
| Project Start Date | 01-11-2023 |
| Project End Date | 31-12-2025 |
| If any extension of time has been granted | NO |
| Cost of land | 119650000 |
| Cost of construction | 354687000 |
| Total project cost | 474337000 |
| Total amount collected from buyers | 432905219 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 432905219 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 108 |
| Total number of Flats/Apartments sold | 108 |
| Total number of Flats/Apartments Unsold | 0 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 21-03-2025 |
| Complaints on Project | No Complaints Found. |