Royaume Builders and Promoters Private Limited
Sy. No. 18/1, Khata No. 9, Kyalasanahalli,
Approved
27th Jun 2018
Completed
30th Sept 2023
Registration No.
PRM/KA/RERA/1251/446/PR/180627/001922
Acknowledgement No.
ACK/KA/RERA/1251/446/PR/180412/002167
Project Type
Residential/Group Housing
Approving Authority
BDA - Bangalore Development Authority
District
Bengaluru Urban
Taluka
Bengaluru East
State
Karnataka
| Project Name | Skylark Dasos |
| Project Description | Apartment Project at Kyalasanahalli, Hennur Main Road |
| Project Type | Residential/Group Housing |
| Project Status | New Project Launch |
| Project Start Date | 01-03-2018 |
| Proposed Project Completion Date | 30-09-2023 |
| Total Area Of Land (Sq Mtr) | 26000 |
| Total Coverd Area (Sq Mtr) | 3519 |
| Total Open Area (Sq Mtr) | 22480 |
| Estimated Cost of Construction (INR) | 2267453645 |
| Cost of Land (INR) | 614375000 |
| Total Project Cost (INR) | 2881828645 |
| Project Address | Sy. No. 18/1, Khata No. 9, Kyalasanahalli, |
| District | Bengaluru Urban |
| Taluk | Bengaluru East |
| Approving Authority | BDA - Bangalore Development Authority |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 29 |
| Area of Parking for Sale (Sq Mtr) | 398 |
| Type of Inventory | Apartment |
| No of Inventory | 472 |
| Carpet Area (Sq Mtr) | 36914SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 1783SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0SqMtr |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Self Development |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Self Development |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Self Development |
| Bank Name | HDFC |
| Branch | Richmond |
| ifscCode | HDFC0000523 |
| Account No.(70% Account) | 57500000101040 |
| State | Karnataka |
| Promoter Type | Company |
| Name | MR. SALEEM SHERIFF AND /OR MR. OMAR SHERIFF |
| PAN Number | AAHCR3282R |
| Address | SKYLARK CHAMBERS , ULSOOR ROAD |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560042 |
| Company Registration No. | U45202KA2015PTC080389 |
| Type of Inventory | Apartment |
| No of Inventory | 472 |
| Carpet Area (Sq Mtr) | 36914 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 1783 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 11-11-2019 | 31-12-2019 |
| 2 | Foundation footing work | Yes | 20-12-2019 | 25-01-2020 |
| 3 | Retaining wall (All types) | Yes | 10-01-2020 | 15-03-2020 |
| 4 | Plinth level Beam | No | ||
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 20-12-2019 | 31-03-2020 |
| 6 | * Earth work and other leveling preparation work (Mandatory) Tower 2 | Yes | 05-02-2018 | 10-02-2019 |
| 7 | Foundation footing work Tower 2 | Yes | 15-12-2018 | 15-02-2019 |
| 8 | Retaining wall (All types) | Yes | 10-01-2019 | 20-02-2019 |
| 9 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 15-12-2018 | 30-04-2019 |
| 10 | * Earth work and other leveling preparation work (Mandatory) Tower 3A | Yes | 10-11-2017 | 01-12-2018 |
| 11 | Foundation footing work Tower 3A | Yes | 01-07-2018 | 31-12-2018 |
| 12 | Retaining wall (All types) Tower 3A | Yes | 25-10-2018 | 22-01-2019 |
| 13 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) Tower 3 A | Yes | 01-07-2018 | 30-06-2019 |
| 14 | * Earth work and other leveling preparation work (Mandatory) Tower 3 B | Yes | 28-11-2017 | 02-02-2019 |
| 15 | Foundation footing work Tower 3B | Yes | 20-12-2018 | 10-02-2019 |
| 16 | Retaining wall (All types) Tower 3B | Yes | 20-12-2018 | 10-02-2019 |
| 17 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) Tower 3B | Yes | 20-12-2018 | 20-04-2019 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | Yes |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | Yes |
| 11 | Education/Health/Other public amenities |
| WebSite Link 1 | https://www.skylarkmansions.com/properties/dasos.php |
| Agent Registration No 1 | ASSETTRUST SERVICES |
| Agent Registration No 2 | PROPLADDER REALTY PVT LTD |
| Agent Registration No 3 | Yes Property Ventures Private Limited |
| Agent Registration No 4 | Liveup Solutions Pvt Ltd |
| FAR Sanctioned | 2.249 |
| Number of Towers | 4 |
| 0 | 8 |
| 1 | 9 |
| 2 | 9 |
| 3 | 9 |
| 4 | 9 |
| 5 | 9 |
| 6 | 9 |
| 7 | 9 |
| 8 | 9 |
| 9 | 9 |
| 10 | 9 |
| 11 | 9 |
| 12 | 9 |
| 13 | 9 |
| 14 | 9 |
| 15 | 9 |
| 16 | 9 |
| 17 | 9 |
| Total No of Units | 472 |
| Appeals / FNH | NO APPEALS / FNH |