Ithaca Estates Private Limited
Kurudusonnehaalli & Kodigehalli, K.R Puram
Approved
15th Sept 2017
Pending
31st Dec 2030
Registration No.
PRM/KA/RERA/1251/446/PR/170915/000308
Acknowledgement No.
PR/KN/170731/000308
Project Type
Residential/Group Housing
Approving Authority
BDA - Bangalore Development Authority
District
Bengaluru Urban
Taluka
Bengaluru East
State
Karnataka
| Project Name | Skylark Ithaca |
| Project Description | Apartment Project |
| Project Type | Residential/Group Housing |
| Project Status | Ongoing |
| Project Start Date | 25-08-2014 |
| Proposed Project Completion Date | 31-12-2020 |
| Further Extension Date | 31-12-2030 |
| Total Area Of Land (Sq Mtr) | 79621 |
| Total Coverd Area (Sq Mtr) | 12051 |
| Total Open Area (Sq Mtr) | 67570 |
| Estimated Cost of Construction (INR) | 7515913303 |
| Cost of Land (INR) | 127327786 |
| Total Project Cost (INR) | 7643241089 |
| Project Address | Kurudusonnehaalli & Kodigehalli, K.R Puram |
| District | Bengaluru Urban |
| Taluk | Bengaluru East |
| Approving Authority | BDA - Bangalore Development Authority |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 1679 |
| Area of Parking for Sale (Sq Mtr) | 23086 |
| Extent of development carried till date | 44 % |
| Extent of development pending | 44 % |
| Total amount of money collected from allottee | 3836377361 |
| Total amount of money used for development of project | 3590815067 |
| Total amount of balance maney lying with promoter | 0 |
| Is Any Subsequent Modification in Plan | Yes |
| Is Delay in the Project | No |
| No of Month Delay | 0 |
| Type of Inventory | Apartment |
| No of Inventory | 1498 |
| Carpet Area (Sq Mtr) | 105637SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 112SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0SqMtr |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Self Development |
| Solid Waste Management And Disposal | Self Development |
| Bank Name | ICICI Bank |
| Branch | Commissariat Road |
| ifscCode | ICIC0000002 |
| Account No.(70% Account) | 000205024745 |
| State | Karnataka |
| Promoter Type | Company |
| Name | Mr. Saleem Sheriff OR Mr. OMar Sheriff |
| PAN Number | AADCI1447B |
| Address | Skylark Chambers , Ulsoor Road |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560042 |
| Company Registration No. | U45205KA2013PTC067632 |
| Type of Inventory | Apartment |
| No of Inventory | 1498 |
| Carpet Area (Sq Mtr) | 105637 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 112 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Extension Applied On | 04-08-2025 |
| Proposed Project End Date at the time of registration | 31-12-2019 |
| Project End Date provided under Section 6 | 31-12-2020 |
| whether 2/3rd concern from the allottees has taken? | YES |
| Whether any compensation is provided for the Buyer? | NO |
| Document Name | TDD Interim Report - Skylark Ithaca |
| 1 | Force Majeure |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 25-04-2014 | 26-01-2015 |
| 2 | Foundation footing work | Yes | 07-10-0014 | 20-03-2015 |
| 3 | Retaining wall (All types) | Yes | 06-11-2014 | 30-05-2019 |
| 4 | Plinth level Beam | No | ||
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 06-12-2014 | 30-05-2019 |
| 6 | * Earth work and other leveling preparation work (Mandatory) Phase 2 | Yes | 09-03-2015 | 06-02-2017 |
| 7 | Foundation footing work Phase 2 | Yes | 16-08-2015 | 28-02-2017 |
| 8 | Retaining wall (All types) Phase 2 | Yes | 13-09-2015 | 30-08-2019 |
| 9 | Plinth level Beam Phase 2 | No | ||
| 10 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) Phase 2 | Yes | 14-10-2015 | 30-03-2020 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | No |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | Yes |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | Yes |
| 12 | *Water Supply (Mandatory) Phase II (Tower 12 to Tower 19) | Yes |
| 13 | Internal Roads & Footpaths Phase II (Tower 12 to Tower 19) | Yes |
| 14 | Sewage and Drainage System Phase II (Tower 12 to Tower 19) | Yes |
| 15 | Parks & Tree planting Phase II (Tower 12 to Tower 19) | Yes |
| 16 | Street Lighting Phase II (Tower 12 to Tower 19) | Yes |
| 17 | Provision for community buildings and for treatment and disposal of sewage and sullage water Phase II (Tower 12 to Tower 19) | Yes |
| 18 | Solid waste management and disposal Phase II (Tower 12 to Tower 19) | Yes |
| 19 | Water conservation Phase II (Tower 12 to Tower 19) | Yes |
| 20 | Energy management Phase II (Tower 12 to Tower 19) | Yes |
| 21 | Fire protection and fire safety requirements Phase II (Tower 12 to Tower 19) | Yes |
| WebSite Link 1 | https://www.skylarkmansions.com/properties/ithaca.php |
| Agent Registration No 1 | Propladder Realty Pvt Ltd |
| Agent Registration No 2 | Assettrust Services |
| Agent Registration No 3 | Elegance Enterprises |
| Agent Registration No 4 | Pin Click |
| FAR Sanctioned | 2.499 |
| Number of Towers | 19 |
| 0 | 3 |
| 1 | 4 |
| 2 | 4 |
| 3 | 4 |
| 4 | 4 |
| 5 | 4 |
| 6 | 4 |
| 7 | 4 |
| 8 | 4 |
| 9 | 4 |
| 10 | 4 |
| 11 | 4 |
| 12 | 4 |
| 13 | 4 |
| 14 | 6 |
| 15 | 6 |
| 16 | 6 |
| 17 | 6 |
| 18 | 6 |
| 19 | 2 |
| Total No of Units | 1761 |
| Appeals / FNH | NO APPEALS / FNH |