SNN Builders Pvt Ltd
NO.326/309/252, Bommanahalli Village, Begur Hobli, Bangalore South Taluk, Hongasandra,Ward No.189, BANGALORE.
Approved
18th Sept 2017
Completed
30th Sept 2025
Registration No.
PRM/KA/RERA/1251/310/PR/170918/000681
Acknowledgement No.
PR/KN/170731/000681
Project Type
Residential/Group Housing
Approving Authority
BBMP - Bruhat Bengaluru Mahanagara Palike
District
Bengaluru Urban
Taluka
Bengaluru South
State
Karnataka
| Project Name | SNN Raj Grandeur |
| Project Description | SNN Raj Grandeur, No.326/309/252,Bommanahalli,Begur,Hongasandra,Ward No.189, Bangalore 560 068. The Land area is 4 Acres 20 Guntas (18,210.49 Sq. Mtrs) with G+13 Floors structure, 2 Basements for Car Park, 2 and 3 BHK Apartments. This Project is a Joint Venture Project between SNN Builders and Essae Suhagraja Pvt Ltd.The construction of the project is being carried out by SNN Builders and Essae Suhagraja Pvt Ltd is the owner of the land. Phase 1 consisting of Blocks EFG will be completed by February 2018 Including Grace Period. |
| Project Type | Residential/Group Housing |
| Project Status | Ongoing |
| Project Start Date | 11-03-2014 |
| Proposed Project Completion Date | 30-09-2023 |
| Further Extension Date | 30-09-2025 |
| Total Area Of Land (Sq Mtr) | 18210 |
| Total Coverd Area (Sq Mtr) | 4146 |
| Total Open Area (Sq Mtr) | 14064 |
| Estimated Cost of Construction (INR) | 1590000000 |
| Cost of Land (INR) | 436375375 |
| Total Project Cost (INR) | 2606613591 |
| Project Address | NO.326/309/252, Bommanahalli Village, Begur Hobli, Bangalore South Taluk, Hongasandra,Ward No.189, BANGALORE. |
| District | Bengaluru Urban |
| Taluk | Bengaluru South |
| Approving Authority | BBMP - Bruhat Bengaluru Mahanagara Palike |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 15 |
| Area of Parking for Sale (Sq Mtr) | 206 |
| Extent of development carried till date | 78 % |
| Extent of development pending | 22 % |
| Total amount of money collected from allottee | 705000000 |
| Total amount of money used for development of project | 895000000 |
| Total amount of balance maney lying with promoter | 0 |
| Is Any Subsequent Modification in Plan | No |
| Is Delay in the Project | No |
| No of Month Delay | 0 |
| Type of Inventory | 3 BHK |
| No of Inventory | 256 |
| Carpet Area (Sq Mtr) | 38349SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0SqMtr |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Self Development |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Self Development |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Self Development |
| Bank Name | SYNDICATE BANK |
| Branch | Seshadripuram Branch |
| ifscCode | SYNB0000407 |
| Account No.(70% Account) | 04071010007819 |
| State | Karnataka |
| Promoter Type | Company |
| Name | Shivashankar Bhat P |
| PAN Number | AANCS6172K |
| Address | No. 3604, 50/1, 50/2, 52/1, 58, 59/1 & 61/1A, Bilekahalli, Bannerghatta Road, Bangalore |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560011 |
| Company Registration No. | U45202KA2009PTCO51411 |
| Project Name | SNN Raj Lakeview - Phase 2 |
| Project Description | SNN Raj Lakeview Ph. 2, BTM 2nd Stage, Bangalore 560076. This Project is abutting SNN Raj Lakeview Phase-1 and the Madiwala Lake. It is spread on 3 Acres 31 Guntas consisting of 184 Units of 3 and 4 BHK Apartments and one Basement Parking. The Apartment size varies from 1575 to 6600 Sqft Apartments. OC obtained and handed over to owners with a proper Association in place. The Project has been awarded as “The Best Luxury Project “in Bangalore by Axis Bank & Silicon India Real Estate Awards. The Project Amenities of both SNN Raj Lakeview Phase 1 and Phase 2 are 1) Bowling Alley 2) Heated Pool 3) Outdoor Swimming Pool 4) Badminton Court – 2 No 5) Squash Court 6) Spa / Health Club 7) Swimming Pool 8) Indoor Games – Billiards , Table Tennis, Carom, Chess 9) Party Hall 10) Yoga / Meditation Room 11) Gym 12) Console Gaming Zone 13) Music & Dance Room 14) Tennis Court 15) Basketball Court 16) Mini Soccer Ground 17) Children Play Area 18) Amphitheater |
| Current Status | Completed |
| Type of Land | Residential |
| Pin Code | 560076 |
| Modification Applied On | 23-02-2023 |
| Modification Approved On | 29-04-2023 |
| Type of Inventory | 3 BHK |
| No of Inventory | 256 |
| Carpet Area (Sq Mtr) | 38349 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Details of Modification of plan sanction / layout brief description | Government over ruled TDR Policy which are release or build over urban the Sanction FAR area and subsequently we are applied TDR for modified plan. |
| Modified plan applied date | 29/12/2015 |
| Modified plan approved date | 15/10/2019 |
| Extend of the work carried out till date of registered project ( % ) | 99.0 |
| Extend of the work pending of registered project ( % ) | 1.0 |
| Total amount collected in respect of registered project ( INR ) | 2385845634 |
| Total amount spent for the project ( INR ) | 2551781251 |
| Total balance amount lying with the promoter ( INR ) | 0 |
| NOC | Air Port Authority |
| Extension Applied On | 14-12-2022 |
| Extension Approved On | 12-01-2023 |
| Extension Registration Number | EX/PRM/KA/RERA/1251/310/PR/230112/000681 |
| Proposed Project End Date at the time of registration | 30-09-2022 |
| Project End Date provided under Section 6 | 30-09-2023 |
| whether 2/3rd concern from the allottees has taken? | NO |
| Whether any compensation is provided for the Buyer? | NO |
| Document Name | Request Letter to Town Planning to Issue OC |
| 1 | Awaiting OC |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 23-01-2014 | 12-12-2014 |
| 2 | Foundation footing work | Yes | 10-04-2014 | 25-03-2015 |
| 3 | Retaining wall (All types) | Yes | 10-05-2014 | 10-04-2015 |
| 4 | Plinth level Beam | Yes | 10-06-2014 | 03-07-2015 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 03-08-2015 | 29-08-2015 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | No |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | Yes |
| 9 | Energy management | No |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | Yes |
| FAR Sanctioned | 2.8 |
| Number of Towers | 7 |
| 0 | 3 |
| 1 | 3 |
| 2 | 3 |
| 3 | 3 |
| 4 | 4 |
| 5 | 4 |
| 6 | 4 |
| 7 | 4 |
| 8 | 4 |
| 9 | 4 |
| 10 | 4 |
| 11 | 4 |
| 12 | 4 |
| 13 | 4 |
| Total No of Units | 372 |
| Project Start Date | 11-03-2014 |
| Project End Date | 30-09-2023 |
| If any extension of time has been granted | YES |
| Extended From Date | 30-09-2022 |
| Extended End Date | 30-09-2023 |
| Cost of land | 436375375 |
| Cost of construction | 1590000000 |
| Total project cost | 2606613591 |
| Total amount collected from buyers | 2412172994 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 2559487637 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 372 |
| Total number of Flats/Apartments sold | 372 |
| Total number of Flats/Apartments Unsold | 0 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | NO |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Project | No Complaints Found. |