Sobha Limited
Survey nos 21/4, 22/1, 22/2 & 22/4 Thalagattapura village, survey no’s 37/1, 37/2,37/3 & 37/4 Mallasandra village, Uttarahalli Hobli
Approved
7th May 2018
Completed
30th Jan 2023
Registration No.
PRM/KA/RERA/1251/310/PR/180507/001622
Acknowledgement No.
PR/KN/171230/002338
Project Type
Residential/Group Housing
Approving Authority
BDA - Bangalore Development Authority
District
Bengaluru Urban
Taluka
Bengaluru South
State
Karnataka
| Project Name | Sobha Arena - Pebble Court (Block 1) |
| Project Description | The composite development of Sobha Arena consists of 4 blocks. The Blocks, along with its amenities to be constructed in Phases. The registration sought under this application is for Block 4 namely, Sobha Arena - Pebble Court, consisting 136 Apartments in the integrated development at the above premises under the name and title of Sobha Arena. The Common amenities and facilities as per in the larger composite development will be shared for the entire development. (Areas, Car park shown below are proportionate to this Phase). |
| Project Type | Residential/Group Housing |
| Project Status | New Project Launch |
| Project Start Date | 17-01-2018 |
| Proposed Project Completion Date | 30-01-2023 |
| Total Area Of Land (Sq Mtr) | 9795 |
| Total Coverd Area (Sq Mtr) | 1449 |
| Total Open Area (Sq Mtr) | 8346 |
| Estimated Cost of Construction (INR) | 1354780768 |
| Cost of Land (INR) | 575873785 |
| Total Project Cost (INR) | 1930654553 |
| Project Address | Survey nos 21/4, 22/1, 22/2 & 22/4 Thalagattapura village, survey no’s 37/1, 37/2,37/3 & 37/4 Mallasandra village, Uttarahalli Hobli |
| District | Bengaluru Urban |
| Taluk | Bengaluru South |
| Approving Authority | BDA - Bangalore Development Authority |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Type of Inventory | Flats |
| No of Inventory | 136 |
| Carpet Area (Sq Mtr) | 17156SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 641SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0SqMtr |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Self Development |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Self Development |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Self Development |
| BESCOM & BWSSB works | Local Authority |
| Bank Name | INDUSIND BANK |
| Branch | M G Road |
| ifscCode | INDB0000008 |
| Account No.(70% Account) | 251002574109 |
| State | Karnataka |
| Name | Sobha Limited |
| Address | Sarjapur-Marthahalli Outer Ring Road,Bellandur |
| Pin Code | 560103 |
| Year Of Establishment | 1995 |
| Number of Project Completed | 5 |
| Reg. Of COA No. | CA/93/15641 |
| Local Authority Licence Number | M-54001 |
| Number Of Project Completed | 118 |
| Promoter Type | Company |
| Name | Lt. Gen. Mathew Mammen |
| PAN Number | AABCS7723E |
| Address | Sarjapur-Marathahalli ORR , Bellandur Post |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560103 |
| Company Registration No. | L45201KA1995PLC018475 |
| Type of Inventory | Flats |
| No of Inventory | 136 |
| Carpet Area (Sq Mtr) | 17156 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 641 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Extension Applied On | 19-11-2022 |
| Proposed Project End Date at the time of registration | 30-01-2023 |
| Project End Date provided under Section 6 | 30-01-2024 |
| whether 2/3rd concern from the allottees has taken? | NO |
| Whether any compensation is provided for the Buyer? | NO |
| 1 | Awaiting OC |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 15-03-2018 | 30-08-2019 |
| 2 | Foundation footing work | Yes | 05-04-2018 | 26-02-2020 |
| 3 | Retaining wall (All types) | Yes | 16-10-2018 | 25-07-2020 |
| 4 | Plinth level Beam | No | ||
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 09-06-2018 | 21-04-2020 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | No |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | No |
| 9 | Energy management | No |
| 10 | Fire protection and fire safety requirements | Yes |
| 11 | Education/Health/Other public amenities | No |
| WebSite Link 1 | https://www.sobha.com/project/current/bangalore/sobha-arena/index.php |
| Agent Registration No 1 | AG/KN/170831/000934 |
| Agent Registration No 2 | AG/KN/170908/001098 |
| Agent Registration No 3 | AG/KN/170831/000805 |
| Agent Registration No 4 | AG/KN/170731/000139 |
| FAR Sanctioned | 2.223 |
| Number of Towers | 2 |
| 0 | 2 |
| 1 | 2 |
| 2 | 4 |
| 3 | 4 |
| 4 | 4 |
| 5 | 4 |
| 6 | 4 |
| 7 | 4 |
| 8 | 4 |
| 9 | 4 |
| 10 | 4 |
| 11 | 4 |
| 12 | 4 |
| 13 | 4 |
| 14 | 4 |
| 15 | 4 |
| 16 | 4 |
| 17 | 4 |
| Total No of Units | 136 |
| Project Start Date | 17-01-2018 |
| Project End Date | 30-01-2023 |
| If any extension of time has been granted | NO |
| Cost of land | 575873785 |
| Cost of construction | 1354780768 |
| Total project cost | 1930654553 |
| Total amount collected from buyers | 1860532241 |
| Whether any loan has been raised | YES |
| Total amount spent for completion of the project | 1930654553 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 136 |
| Total number of Flats/Apartments sold | 135 |
| Total number of Flats/Apartments Unsold | 1 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | NO |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 30-01-2023 |
| Appeals / FNH | NO APPEALS / FNH |