SHREE DEVELOPERS
Sri Rama Badavane Phase-II, Sy No:29/10, 30, 35/1 of Kavalahosahalli and Sy.No:99 of Haldenahalli Village, Kasaba Hobli, Anekal Taluk, Bengaluru Urban District 562106
Approved
23rd Mar 2020
Completed
30th Sept 2022
Registration No.
PRM/KA/RERA/1251/308/PR/200323/003381
Acknowledgement No.
ACK/KA/RERA/1251/308/PR/200213/003901
Project Type
Plotted Development
Approving Authority
Local Planing Authority
District
Bengaluru Urban
Taluka
Anekal
State
Karnataka
| Project Name | SRI RAMA BADAVANE PHASE-II |
| Project Description | Residential Layout comprises of 70 plots with different dimensions |
| Project Type | Plotted Development |
| Project Status | New Project Launch |
| Project Start Date | 01-12-2019 |
| Proposed Project Completion Date | 30-09-2022 |
| Total Area Of Land (Sq Mtr) | 20132 |
| Total Coverd Area (Sq Mtr) | 9568 |
| Total Open Area (Sq Mtr) | 10564 |
| Estimated Cost of Construction (INR) | 25000000 |
| Cost of Land (INR) | 32500000 |
| Total Project Cost (INR) | 57500000 |
| Project Address | Sri Rama Badavane Phase-II, Sy No:29/10, 30, 35/1 of Kavalahosahalli and Sy.No:99 of Haldenahalli Village, Kasaba Hobli, Anekal Taluk, Bengaluru Urban District 562106 |
| District | Bengaluru Urban |
| Taluk | Anekal |
| Approving Authority | Local Planing Authority |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Local Authority |
| Fire Fighting facility | Local Authority |
| Drinking Water Facility | Self Development |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Local Authority |
| Bank Name | HDFC |
| Branch | ANEKAL BRANCH |
| ifscCode | HDFC0001049 |
| Account No.(70% Account) | 50200047328071 |
| State | Karnataka |
| Name | ROHIT KUMAR REDDY L |
| Address | #16, Pillareddy Layout, Chandapura ,Anekal Taluk, Bengaluru-560099 |
| Pin Code | 560099 |
| Year Of Establishment | 2015 |
| Number of Project Completed | 152 |
| Reg. Of COA No. | CA/98/23892 |
| Local Authority Licence Number | M-59398/7 |
| Number Of Project Completed | 5 |
| Promoter Type | Partnership Firm |
| Name | V.KRISHNAPPA |
| PAN Number | AECFS1090J |
| Address | #44 & 45, 3rd cross.SRIRAMA BADAVANE, CHANDAPURA MAIN ROAD, ANEKAL |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 562106 |
| Company Registration No. | BSD F449 2019 20 |
| Type | Others |
| Pin Code | 562106 |
| Sl No. |
| Sl No. | Plot No. | Plot Type | Plot Size | Plot Area | Phase | Stage | North Dimension | South Dimension | East Dimension | West Dimension | North Schedule Dimension | South Schedule Dimension | East Schedule Dimension | West Schedule Dimension |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 1 | RESIDENTIAL | ODD | 131.73 | PHASE II | COMPLETED | 10.75 | 11.54 | 12.16 | 12.16 | 9.14M ROAD | PRIVATE PROP | SITE NO 2 | PRIVATE PROP |
| 2 | 2 | RESIDENTIAL | odd | 108.48 | PHASE II | COMPLETED | 12.19 | 12.19 | 9.14 | 9.14 | 9.14M road | Private Prop | Site No 3 | Site No 2 |
| 3 | 3 | RESIDENTIAL | odd | 114.37 | PHASE II | COMPLETED | 12.83 | 12.83 | 9.14 | 9.14 | 9.14M Road | Private Prop | Site No 4 | Site No 2 |
| 4 | 4 | RESIDENTIAL | ODD | 120.24 | PHASE II | COMPLETED | 13.47 | 13.47 | 9.14 | 9.14 | 9.14M ROAD | PRIVATE PROP | SITE NO 5 PRIVATE PROP SITE NO 15&PRIVATE PROP | SITE NO 3 SITE NO 5 SITE NO 7&12 |
| 5 | 5 | RESIDENTIAL | ODD | 132.82 | Phase II | Completed | 14.29 | 14.29 | 8.36 | 10.9 | 9.14M Road | Private Prop | Private Prop | Site No 5 |
| 6 | 6 | RESIDENTIAL | ODD | 154.38 | Phase II | Completed | 14.26 | 14.5 | 9.52 | 12.13 | Site No 14 | 9.14M Road | Site No 15 and Private Prop | Site No 7 & 12 |
| 7 | 7 | RESIDENTIAL | 30X40 | 111.48 | PHASE II | COMPLETED | 9.14 | 9.14 | 12.19 | 12.19 | SITE NO 12 | 9.14M ROAD | SITE NO 6 9.14M | 9.14M ROAD |
| 8 | 8 | RESIDENTIAL | ODD | 111.48 | PHASE II | COMPLETED | 9.14 | 9.14 | 12.19 | 12.19 | Site No 11 | 9.14M Road | Road | Site No 9 |
| 9 | 9 | RESIDENTIAL | ODD | 90.95 | PHASE II | COMPLETED | 9.16 | 9.14 | 9.67 | 10.22 | Site No 10 | 9.14M road | Site No 8 | PRIVATE PROP |
| 10 | 10 | RESIDENTIAL | ODD | 96.02 | PHASE II | COMPLETED | 9.16 | 9.16 | 10.78 | 10.78 | 9.14M ROAD | SITE NO 9 | SITE NO 11 | PRIVATE PROP |
| 11 | 11 | RESIDENTIAL | 30X40 | 111.48 | PHASE II | COMPLETED | 9.14 | 9.14 | 12.19 | 12.19 | 9.14M ROAD | SITE NO 8 | 9.14M ROAD | SITE NO 10 |
| 12 | 12 | RESIDENTIAL | 30X40 | 111.48 | PHASE II | COMPLETED | 9.14 | 9.14 | 12.19 | 12.19 | SITE NO 13 | SITE NO 7 | SITE NO 6&14 | 9.14M ROAD |
| 13 | 13 | RESIDENTIAL | ODD | 157.85 | PHASE II | COMPLETED | 13 | 13 | 12.19 | 12.19 | 9.14M ROAD | SITE NO 12 | SITE NO 14 | 9.14M ROAD |
| 14 | 14 | RESIDENTIAL | ODD | 230.33 | PHASE II | COMPLETED | 16.92 | 17.07 | 12.13 | 15.19 | 9.14M ROAD | SITE NO 6 | SITE NO 15 | SITE NO 12&13 |
| 15 | 15 | RESIDENTIAL | ODD | 191.79 | PHASE II | COMPLETED | 20.54 | 20.9 | 9.2 | 15.4 | 9.14M ROAD | PRIVATE PROP | PRIVATE PROP | SITE NO 14 |
| 16 | 16 | RESIDENTIAL | ODD | 176.4 | PHASE II | COMPLETED | 14.5 | 14.5 | 12.19 | 12.2 | PRIVATE PROP | 9.14M ROAD | 9.14M ROAD | SITE NO 17 |
| 17 | 17 | RESIDENTIAL | ODD | 169.57 | PHASE II | COMPLETED | 14.41 | 14.44 | 11.33 | 12.2 | PRIVATE PROP | 9.14M ROAD | SITE NO 16 | PRIVATE PROP |
| 18 | 18 | RESIDENTIAL | ODD | 119.47 | PHASE II | COMPLETED | 12.22 | 12.19 | 9.43 | 10.17 | 9.14M ROAD | PRIVATE PROP | SITE NO 19 | PRIVATE PROP |
| 19 | 19 | RESIDENTIAL | 30X40 | 111.48 | PHASE II | COMPLETED | 12.19 | 12.19 | 9.14 | 9.14 | 9.14M ROAD | PRIVATE PROP | SITE NO 20 | SITE NO 18 |
| 20 | 20 | RESIDENTIAL | 30X40 | 111.48 | PHASE II | COMPLETED | 12.19 | 12.19 | 9.14 | 9.14 | 9.14M ROAD | PRIVATE PROP | 9.14M ROAD | SITE NO 19 |
| 21 | 21 | RESIDENTIAL | ODD | 90.77 | PHASE II | COMPLETED | 6.45 | 10.13 | 10.72 | 11 | PRIVATE PROP | 9.14M ROAD | SITE NO 22 | PRIVATE PROP |
| 22 | 22 | RESIDENTIAL | ODD | 106.5 | PHASE II | COMPLETED | 13.17 | 13.17 | 9.14 | 9.63 | PRIVATE PROP | 9.14M ROAD | SITE NO 23 | SITE NO 21 |
| 23 | 23 | RESIDENTIAL | ODD | 134.29 | PHASE II | COMPLETED | 16.21 | 16.21 | 9.14 | 9.65 | PRIVATE PROP | 9.14M ROAD | 9.14M ROAD | SITE NO 22 |
| 24 | 24 | RESIDENTIAL | ODD | 114.31 | PHASE II | COMPLETED | 12.78 | 12.19 | 7.46 | 11.29 | C.A | 9.14M ROAD | SITE NO 25 | PRIVATE PROP |
| 25 | 25 | RESIDENTIAL | 30X40 | 111.48 | PHASE II | COMPLETED | 12.19 | 12.19 | 9.14 | 9.14 | C.A | 9.14M ROAD | SITE NO 26 | SITE NO 24 |
| 26 | 26 | RESIDENTIAL | 30X40 | 111.48 | PHASE II | COMPLETED | 12.19 | 12.19 | 9.14 | 9.14 | C.A | 9.14M ROAD | SITE NO 27 | SITE NO 25 |
| 27 | 27 | RESIDENTIAL | 30X40 | 111.48 | PHASE II | COMPLETED | 12.16 | 12.19 | 9.14 | 9.14 | C.A | 9.14M ROAD | SITE NO 28 | SITE NO 26 |
| 28 | 28 | RESIDENTIAL | 30X40 | 111.48 | PHASE II | COMPLETED | 12.19 | 12.19 | 9.14 | 9.14 | C.A | 9.14M ROAD | SITE NO 29 | SITE NO 27 |
| 29 | 29 | RESIDENTIAL | ODD | 123.78 | PHASE II | COMPLETED | 12.19 | 14.8 | 14.35 | 5.96 | C.A | 9.14M ROAD | 9.14M ROAD | SITE NO 28 |
| 30 | 30 | RESIDENTIAL | 30X40 | 111.48 | PHASE II | COMPLETED | 12.19 | 12.19 | 9.14 | 9.14 | 9.14M ROAD | SITE NO 42 | 9.14M ROAD | SITE NO 31 |
| 31 | 31 | RESIDENTIAL | 30X40 | 111.48 | PHASE II | COMPLETED | 12.19 | 12.19 | 9.14 | 9.14 | 9.14M ROAD | SITE NO 41 | SITE NO 30 | SITE NO 32 |
| 32 | 32 | RESIDENTIAL | 30X40 | 111.48 | PHASE II | COMPLETED | 12.19 | 12.19 | 9.14 | 9.14 | 9.14M ROAD | SITE NO 40 | SITE NO 31 | SITE NO 33 |
| 33 | 33 | RESIDENTIAL | 30X40 | 111.48 | PHASE II | COMPLETED | 12.19 | 12.19 | 9.14 | 9.14 | 9.14M ROAD | SITE NO 39 | SITE NO 32 | SITE NO 34 |
| 34 | 34 | RESIDENTIAL | 30X40 | 111.48 | PHASE II | COMPLETED | 12.19 | 12.19 | 9.14 | 9.14 | 9.14M ROAD | SITE NO 38 | SITE NO 33 | SITE NO 35 |
| 35 | 35 | RESIDENTIAL | 30X40 | 111.48 | PHASE II | COMPLETED | 12.19 | 12.19 | 9.14 | 9.14 | 9.14M ROAD | SITE NO 38&37 | SITE NO 34 | SITE NO 36 |
| 36 | 36 | RESIDENTIAL | ODD | 108.56 | PHASE II | COMPLETED | 6.75 | 12.19 | 10.55 | 12.77 | 9.14M ROAD | SITE NO 37 | SITE NO 35 | 9.14M ROAD |
| 37 | 37 | RESIDENTIAL | ODD | 149.83 | PHASE II | COMPLETED | 10.47 | 9.48 | 14.32 | 15.85 | SITE NO 35&36 | PRIVATE PROP | SITE NO 38 | 9.14M ROAD |
| 38 | 38 | RESIDENTIAL | ODD | 157 | PHASE II | COMPLETED | 9.48 | 12.19 | 12.04 | 12.98 | SITE NO 34&35 | 9.14M ROAD | SITE NO 39 | SITE NO 37&PRIVATE PROP |
| 39 | 39 | RESIDENTIAL | 30X40 | 111.48 | PHASE II | COMPLETED | 12.19 | 12.19 | 9.14 | 9.14 | SITE NO 33 | 9.14M ROAD | SITE NO 40 | SITE NO 38 |
| 40 | 40 | RESIDENTIAL | 30X40 | 111.48 | PHASE II | COMPLETED | 12.19 | 12.19 | 9.14 | 9.14 | SITE NO 32 | 9.14M ROAD | SITE NO 41 | SITE NO 39 |
| 41 | 41 | RESIDENTIAL | 30X40 | 111.48 | PHASE II | COMPLETED | 12.19 | 12.19 | 9.14 | 9.14 | SITE NO 31 | 9.14M ROAD | SITE NO 42 | SITE NO 40 |
| 42 | 42 | RESIDENTIAL | 30X40 | 111.48 | PHASE II | COMPLETED | 12.19 | 12.19 | 9.14 | 9.14 | SITE NO 30 | 9.14M ROAD | 9.14M ROAD | SITE NO 41 |
| 43 | 43 | RESIDENTIAL | ODD | 101.51 | PHASE II | COMPLETED | 12.19 | 13.3 | 9.14 | 5.58 | 9.14M ROAD | SITE NO 44 | SITE NO 45&PRIVATE PROP | 9.14M ROAD |
| 44 | 44 | RESIDENTIAL | 30X40 | 111.48 | PHASE II | COMPLETED | 12.19 | 12.19 | 9.14 | 9.14 | SITE NO 43 | 9.14M ROAD | SITE NO 45 | 9.14M ROAD |
| 45 | 45 | RESIDENTIAL | ODD | 179.81 | PHASE II | COMPLETED | 19.17 | 20.16 | 9.14 | 9.2 | PRIVATE PROP | 9.14M ROAD | SITE NO 46&48 | SITE NO 44&43 |
| 46 | 46 | RESIDENTIAL | 30X40 | 111.48 | PHASE II | COMPLETED | 12.19 | 12.19 | 9.14 | 9.14 | SITE NO 48 | 9.14M ROAD | SITE NO 47 | SITE NO 45 |
| 47 | 47 | RESIDENTIAL | ODD | 153.39 | PHASE II | COMPLETED | 12.19 | 14.35 | 16.16 | 8.59 | SITE NO 48 | 9.14M ROAD | 12M ROAD | SITE NO 46 |
| 48 | 48 | RESIDENTIAL | ODD | 119.93 | PHASE II | COMPLETED | 7.96 | 12.07 | 17.74 | 9.77 | PRIVATE PROP | SITE NO 46&47 | 12M ROAD | SITE NO 45 |
| 49 | 49 | RESIDENTIAL | ODD | 223.61 | PHASE II | COMPLETED | 18.92 | 16.74 | 9.34 | 18.15 | PRIVATE PROP | 12M ROAD | SITE NO 50 | 12M ROAD |
| 50 | 50 | RESIDENTIAL | ODD | 153.7 | PHASE II | COMPLETED | 16.74 | 16.74 | 9.14 | 9.14 | PRIVATE PROP | 12M ROAD | SITE NO 51 | SITE NO 49 |
| 51 | 51 | RESIDENTIAL | ODD | 153.7 | PHASE II | COMPLETED | 16.74 | 16.74 | 9.14 | 9.14 | PRIVATE PROP | 12M ROAD | SITE NO 52 | SITE NO 50 |
| 52 | 52 | RESIDENTIAL | ODD | 153.7 | PHASE II | COMPLETED | 16.74 | 16.74 | 9.14 | 9.14 | PRIVATE PROP | 12M ROAD | SITE NO 53 | SITE NO 51 |
| 53 | 53 | RESIDENTIAL | ODD | 153.7 | PHASE II | COMPLETED | 16.74 | 16.74 | 9.14 | 9.14 | PRIVATE PROP | 12M ROAD | SITE NO 54 | SITE NO 52 |
| 54 | 54 | RESIDENTIAL | ODD | 189.18 | PHASE II | COMPLETED | 16.74 | 17.17 | 9.39 | 13.22 | PRIVATE PROP | 12M ROAD | PRIVATE PROP | SITE NO 53 |
| 55 | 55 | RESIDENTIAL | ODD | 263.74 | PHASE II | COMPLETED | 18.85 | 20.57 | 11.26 | 15.78 | 12M ROAD | PRIVATE PROP | PRIVATE PROP | SITE NO 56 |
| 56 | 56 | RESIDENTIAL | ODD | 167.81 | PHASE II | COMPLETED | 17.86 | 17.86 | 9.2 | 9.14 | 12M ROAD | PRIVATE PROP | SITE NO 55 | SITE NO 57 |
| 57 | 57 | RESIDENTIAL | ODD | 158.78 | PHASE II | COMPLETED | 16.87 | 16.87 | 9.2 | 9.14 | 12M ROAD | PRIVATE PROP | SITE NO 56 | SITE NO 58&59 |
| 58 | 58 | RESIDENTIAL | ODD | 169.96 | PHASE II | COMPLETED | 20.07 | 12 | 13.68 | 14.99 | 12M ROAD | SITE NO 59 | SITE NO 57 | 12M ROAD |
| 59 | 59 | RESIDENTIAL | ODD | 123.21 | PHASE II | COMPLETED | 9.15 | 9.32 | 12.8 | 13.68 | SITE NO 58 | PATH WAY | SITE NO 57&PRIVATE PROP | 12M ROAD |
| 60 | 60 | RESIDENTIAL | ODD | 183.79 | PHASE II | COMPLETED | 15.24 | 15.41 | 12.81 | 10.51 | 9.14M ROAD | PATH WAY | 12M ROAD | SITE NO 61 |
| 61 | 61 | RESIDENTIAL | 30X50 | 139.4 | PHASE II | COMPLETED | 15.24 | 15.24 | 9.14 | 9.14 | 9.14M ROAD | PATH WAY | SITE NO 60 | SITE NO 62 |
| 62 | 62 | RESIDENTIAL | 30X50 | 139.4 | PHASE II | COMPLETED | 15.24 | 15.24 | 9.14 | 9.14 | 9.14M ROAD | PATH WAY | SITE NO 61 | SITE NO 63 |
| 63 | 63 | RESIDENTIAL | 30X50 | 139.4 | PHASE II | COMPLETED | 15.24 | 15.24 | 9.14 | 9.14 | 9.14M ROAD | PATH WAY | SITE NO 62 | SITE NO 64 |
| 64 | 64 | RESIDENTIAL | 30X50 | 139.4 | PHASE II | COMPLETED | 15.24 | 15.24 | 9.14 | 9.14 | 9.14M ROAD | PATH WAY | SITE NO 63 | SITE NO 65 |
| 65 | 65 | RESIDENTIAL | 30X50 | 139.4 | PHASE II | COMPLETED | 15.24 | 15.24 | 9.14 | 9.14 | 9.14M ROAD | PATH WAY | SITE NO 64 | SITE NO 66 |
| 66 | 66 | RESIDENTIAL | 30X50 | 139.4 | PHASE II | COMPLETED | 15.24 | 15.24 | 9.14 | 9.14 | 9.14M ROAD | PATH WAY | SITE NO 65 | SITE NO 67 |
| 67 | 67 | RESIDENTIAL | 30X50 | 139.4 | PHASE II | COMPLETED | 15.24 | 15.24 | 9.14 | 9.14 | 9.14M ROAD | PATH WAY | SITE NO 66 | SITE NO 68 |
| 68 | 68 | RESIDENTIAL | 30X50 | 139.4 | PHASE II | COMPLETED | 15.24 | 15.24 | 9.14 | 9.14 | 9.14M ROAD | PATH WAY | SITE NO 67 | SITE NO 69 |
| 69 | 69 | RESIDENTIAL | ODD | 234.06 | PHASE II | COMPLETED | 16.13 | 15.24 | 12.71 | 18.01 | 9.14M ROAD | PATH WAY | SITE NO 68 | PRIVATE PROP |
| 70 | 0 | RESIDENTIAL | ODD | 0 | PHASE II | COMPLETED | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Ground Clearance/Formation Of Plots | Yes | 01-12-2019 | 31-12-2020 |
| 2 | Formation Of Road, Footpath | Yes | 01-12-2019 | 31-12-2020 |
| 3 | Construction Of WaterSupply Infrastucture | Yes | 01-12-2019 | 31-12-2020 |
| 4 | Construction Of Sewage System Infrastucture | Yes | 01-12-2019 | 31-12-2020 |
| 5 | Power Supply Work(Tansformer And Substation) | Yes | 01-12-2019 | 31-12-2020 |
| 6 | Construction Of Storm Water Drainage | Yes | 01-12-2019 | 31-12-2020 |
| 7 | Solid Waste Management and Disposal | No | ||
| 8 | Tree Plantation And LandScape Work | Yes | 01-12-2019 | 31-12-2020 |
| 9 | Street Lighting | Yes | 01-12-2019 | 31-12-2020 |
| 10 | Other Miscellaneous Work | No |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Electricity | Yes |
| 2 | Smart home automation | No |
| 3 | CCTV surveillance | No |
| 4 | Club House | No |
| 5 | Community Hall | No |
| 6 | Outdoor Sports facility | No |
| 7 | Indoor sports facility | No |
| 8 | Swimming Pools | No |
| 9 | Gym | No |
| 10 | Parks | No |
| 11 | Power Backup | No |
| 12 | Gas | No |
| 13 | Water and Sanitation | No |
| 14 | Air conditioning and incarnation | No |
| Total number of Plots | 70 |
| No. of Public and Semi Pubic Sites | 1 |
| Area of Public and Semi Pubic Sites(in Sq.m) | 1008 |
| No. of Parks and Open Spaces | 1 |
| Area of Parks and Open Spaces(in Sq.m) | 2276 |
| Area of Road/Transportation(in Sq.m) | 7279 |
| Project Start Date | 01-12-2019 |
| Project End Date | 30-09-2022 |
| If any extension of time has been granted | NO |
| Cost of land | 32500000 |
| Cost of construction | 25000000 |
| Total cost | 57500000 |
| Total amount collected From buyers | 0 |
| Whether any loan has been raised | NO |
| Total amount spent on Project for completion of the project | 14334105 |
| Total No of sites of Project | 69 |
| Total No of sites sold | 0 |
| Total No of sites unsold | 69 |
| Whether there is any changes in inventory details | NO |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |