M/s. Venkateshwara Builders
Katha No.128, Sy.No.2/1, Municipal No.128, , Kumbenaagrahara Village. Bidarahalli Hobli
Approved
31st Jan 2019
Completed
30th Sept 2022
Registration No.
PRM/KA/RERA/1251/446/PR/190131/002323
Acknowledgement No.
ACK/KA/RERA/1251/446/PR/181207/002881
Project Type
Residential/Group Housing
Approving Authority
BBMP - Bruhat Bengaluru Mahanagara Palike
District
Bengaluru Urban
Taluka
Bengaluru East
State
Karnataka
| Project Name | SV ELEGANT |
| Project Description | Residential Apartment |
| Project Type | Residential/Group Housing |
| Project Status | New Project Launch |
| Project Start Date | 07-12-2018 |
| Proposed Project Completion Date | 30-09-2022 |
| Total Area Of Land (Sq Mtr) | 3757 |
| Total Coverd Area (Sq Mtr) | 1776 |
| Total Open Area (Sq Mtr) | 1981 |
| Estimated Cost of Construction (INR) | 180000000 |
| Cost of Land (INR) | 140000000 |
| Total Project Cost (INR) | 320000000 |
| Project Address | Katha No.128, Sy.No.2/1, Municipal No.128, , Kumbenaagrahara Village. Bidarahalli Hobli |
| District | Bengaluru Urban |
| Taluk | Bengaluru East |
| Approving Authority | BBMP - Bruhat Bengaluru Mahanagara Palike |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Self Development |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Local Authority |
| Drinking Water Facility | Self Development |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Self Development |
| Bank Name | Bank of Maharashtra |
| Branch | Seegehalli |
| ifscCode | MAHB0001682 |
| Account No.(70% Account) | 60319856486 |
| State | Karnataka |
| Promoter Type | Partnership Firm |
| Name | Mr.Vijayakumar.D |
| PAN Number | AAKFV1359B |
| Address | No.25, Shiva Shakthi Krupa, Munireddy Layout , Horamavu, |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560043 |
| Company Registration No. | Not Applicable |
| Modification Applied On | 08-10-2020 |
| Type of Inventory | Residential |
| No of Inventory | 108 |
| Carpet Area (Sq Mtr) | 9609 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 11152 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Details of Modification of plan sanction / layout brief description | Project JDA as been entered in respect of SY. No. 2/1, further the JDA is entered in respect of SY.No. 2/7 with the land owners, Hence a modified Plan was obtained for developing the Project in the Amalgamated SY.No. 2/1 & 2/7, having Khata No. 439 |
| Modified plan applied date | 26/12/2019 |
| Modified plan approved date | 11/02/2020 |
| Extend of the work carried out till date of registered project ( % ) | 5.83 |
| Extend of the work pending of registered project ( % ) | 94.17 |
| Total amount collected in respect of registered project ( INR ) | 0 |
| Total amount spent for the project ( INR ) | 19501093 |
| Total balance amount lying with the promoter ( INR ) | 0 |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 07-12-2018 | 04-08-2021 |
| 2 | Foundation footing work | Yes | 07-12-2018 | 04-08-2021 |
| 3 | Retaining wall (All types) | No | ||
| 4 | Plinth level Beam | Yes | 07-12-2018 | 04-08-2021 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | No |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | No |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | No |
| 5 | Street Lighting | No |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | No |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | Yes |
| 9 | Energy management | No |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | No |
| 12 | ELECTRICITY SUPPLY TRANSFORMER AND SUBSTATION | Yes |
| FAR Sanctioned | 2.25 |
| Number of Towers | 1 |
| 0 | 27 |
| 1 | 27 |
| 2 | 27 |
| 3 | 27 |
| Total No of Units | 108 |
| Project Start Date | 07-12-2018 |
| Project End Date | 30-09-2022 |
| If any extension of time has been granted | NO |
| Cost of land | 140000000 |
| Cost of construction | 180000000 |
| Total project cost | 320000000 |
| Total amount collected from buyers | 0 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 290000000 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 108 |
| Total number of Flats/Apartments sold | 0 |
| Total number of Flats/Apartments Unsold | 108 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | YES |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 03-08-2021 |
| Appeals / FNH | NO APPEALS / FNH |