SV HOUSING
Sy. 101/2 & 101/3, Kammasandra, Attibele
Approved
17th Jan 2020
Completed
9th Apr 2022
Registration No.
PRM/KA/RERA/1251/308/PR/200117/003159
Acknowledgement No.
ACK/KA/RERA/1251/308/PR/191022/003644
Project Type
Residential/Group Housing
Approving Authority
Local Planing Authority
District
Bengaluru Urban
Taluka
Anekal
State
Karnataka
| Project Name | SV GRANDUR |
| Project Description | Residential Appartment 284 FLATS ( 2BHK & 3 BHK), BASEMENT + GROUND FLOOR + 12 FLOORS |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| Project Start Date | 02-04-2019 |
| Proposed Project Completion Date | 09-04-2022 |
| Total Area Of Land (Sq Mtr) | 13557 |
| Total Coverd Area (Sq Mtr) | 2433 |
| Total Open Area (Sq Mtr) | 11124 |
| Estimated Cost of Construction (INR) | 630000000 |
| Cost of Land (INR) | 147391730 |
| Total Project Cost (INR) | 777391730 |
| Project Address | Sy. 101/2 & 101/3, Kammasandra, Attibele |
| District | Bengaluru Urban |
| Taluk | Anekal |
| Approving Authority | Local Planing Authority |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 35 |
| Area of Parking for Sale (Sq Mtr) | 481 |
| Type of Inventory | 2 Bhk & 3 Bhk |
| No of Inventory | 284 |
| Carpet Area (Sq Mtr) | 27681SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 973SqMtr |
| Road System | Self Development |
| Water Supply | Local Authority |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Self Development |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Self Development |
| Bank Name | Industrial Development Bank of India |
| Branch | MARATHAHALLI |
| ifscCode | IBKL0001004 |
| Account No.(70% Account) | 1004102000011936 |
| State | Karnataka |
| Name | SVM CONSTRUCTION |
| Address | #89, 3rd Floor, VM Cosma,Karthik Nagar, Marathahalli |
| Pin Code | 560037 |
| Year Of Establishment | 2012 |
| Number of Project Completed | 500+ |
| Reg. Of COA No. | BCC/BL-3.6/E:3957:2014-15 |
| Local Authority Licence Number | BCC/BL-3-6/E-4030:2014-15 |
| Number Of Project Completed | 21 |
| Promoter Type | Partnership Firm |
| Name | S VENKATESH |
| PAN Number | ACMFS5438G |
| Address | #89, 3rd Floor, VM Cosma , Karthik Nagar, Marathahalli |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560037 |
| Company Registration No. | SJN F 1093 2013 14 |
| Type of Inventory | 2 Bhk & 3 Bhk |
| No of Inventory | 284 |
| Carpet Area (Sq Mtr) | 27681 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 973 Sq Mtr |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 02-04-2019 | 15-04-2019 |
| 2 | Foundation footing work | Yes | 16-04-2019 | 01-06-2019 |
| 3 | Retaining wall (All types) | Yes | 26-04-2019 | 10-06-2019 |
| 4 | Plinth level Beam | Yes | 15-06-2019 | 30-06-2019 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 10-07-2019 | 15-08-2019 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | Yes |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | Yes |
| 11 | Education/Health/Other public amenities | Yes |
| FAR Sanctioned | 2.49 |
| Number of Towers | 4 |
| 0 | 0 |
| 1 | 5 |
| 2 | 6 |
| 3 | 6 |
| 4 | 6 |
| 5 | 6 |
| 6 | 6 |
| 7 | 6 |
| 8 | 6 |
| 9 | 6 |
| 10 | 6 |
| 11 | 6 |
| 12 | 6 |
| Total No of Units | 284 |
| Project Start Date | 02-04-2019 |
| Project End Date | 09-04-2022 |
| If any extension of time has been granted | NO |
| Cost of land | 147391730 |
| Cost of construction | 630000000 |
| Total project cost | 777391730 |
| Total amount collected from buyers | 658889533 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 732366041 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 284 |
| Total number of Flats/Apartments sold | 119 |
| Total number of Flats/Apartments Unsold | 165 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 02-03-2022 |
| Appeals / FNH | NO APPEALS / FNH |