THE POTTER'S HAND
EAPEN CHANDY
SY NO. 78/1, Khatha No 30,Block II,Kyalasanahalli Village , K R Puram Hobli,Bengaluru
Approved
12th Oct 2018
Completed
1st Mar 2019
Registration No.
PRM/KA/RERA/1251/446/PR/181012/002084
Acknowledgement No.
ACK/KA/RERA/1251/446/PR/180720/002469
Project Type
Residential/Group Housing
Approving Authority
BBMP - Bruhat Bengaluru Mahanagara Palike
District
Bengaluru Urban
Taluka
Bengaluru East
State
Karnataka
Project Details
| Project Name | THE POTTER'S HAND |
| Project Description | Apartment of 4 Floors |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| Project Start Date | 15-11-2014 |
| Proposed Project Completion Date | 01-03-2019 |
| Total Area Of Land (Sq Mtr) | 4223 |
| Total Coverd Area (Sq Mtr) | 2111 |
| Total Open Area (Sq Mtr) | 2112 |
| Estimated Cost of Construction (INR) | 240000000 |
| Cost of Land (INR) | 80000000 |
| Total Project Cost (INR) | 355000000 |
| Project Address | SY NO. 78/1, Khatha No 30,Block II,Kyalasanahalli Village , K R Puram Hobli,Bengaluru |
| District | Bengaluru Urban |
| Taluk | Bengaluru East |
| Approving Authority | BBMP - Bruhat Bengaluru Mahanagara Palike |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Extent of development carried till date | 85 % |
| Extent of development pending | 15 % |
| Total amount of money collected from allottee | 212994281 |
| Total amount of money used for development of project | 225972024 |
| Total amount of balance maney lying with promoter | 0 |
| Is Any Subsequent Modification in Plan | No |
| Is Delay in the Project | No |
| No of Month Delay | 0 |
| Road System | Local Authority |
| Water Supply | Local Authority |
| Sewege and Drainage System | Local Authority |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Local Authority |
| Fire Fighting facility | Local Authority |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Local Authority |
| Bank Name | STATE BANK OF INDIA |
| Branch | COX TOWN |
| ifscCode | SBIN0070428 |
| Account No.(70% Account) | 67310908558 |
| State | Karnataka |
Promoter Details
| Firm Type | Individual |
| Name | EAPEN CHANDY |
| Father's Name | Late Mr. Mathai Chandy |
| PAN Number | AEG******* |
| Address | S-2, Abide With Me, 1/A, 11 th Cross,,Kariannapalya,Lingarajapuram, |
| State/UT | Karnataka |
| PIN Code | 560084 |
Project Development Schedule
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 02-02-2015 | 27-02-2015 |
| 2 | Foundation footing work | Yes | 25-02-2015 | 15-04-2016 |
| 3 | Retaining wall (All types) | Yes | 02-03-2015 | 30-05-2016 |
| 4 | Plinth level Beam | Yes | 22-03-2015 | 30-05-2016 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 16-04-2015 | 29-06-2016 |
Amenities & Utilities Availability
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | No |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | Yes |
| 9 | Energy management | No |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | No |
Post Registration Details
| FAR Sanctioned | 2.25 |
| Number of Towers | 1 |
| 0 | 11 |
| 1 | 12 |
| 2 | 12 |
| 3 | 12 |
| 4 | 12 |
| Total No of Units | 59 |
Completion Details
| Project Start Date | 15-11-2014 |
| Project End Date | 01-03-2019 |
| If any extension of time has been granted | NO |
| Cost of land | 80000000 |
| Cost of construction | 240000000 |
| Total project cost | 355000000 |
| Total amount collected from buyers | 239550000 |
| Whether any loan has been raised | YES |
| Total amount spent for completion of the project | 240000000 |
| Balance amount with the promoter | 450000 |
| Total number of Flats/Apartments of the Project | 59 |
| Total number of Flats/Apartments sold | 59 |
| Total number of Flats/Apartments Unsold | 0 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 13-08-2019 |
Appeals & Complaints
| Appeals / FNH | NO APPEALS / FNH |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in