Suadela Constructions Private Limited
Begur Village, Next to Hulimavu Lake, Akshay Nagar, Begur Hobli, Bangalore South Taluk/ Tehsil, Bangalore District 560068
Approved
5th Mar 2019
Completed
31st Mar 2023
Registration No.
PRM/KA/RERA/1251/310/PR/190305/002472
Acknowledgement No.
ACK/KA/RERA/1251/310/PR/181217/002903
Project Type
Residential/Group Housing
Approving Authority
BBMP - Bruhat Bengaluru Mahanagara Palike
District
Bengaluru Urban
Taluka
Bengaluru South
State
Karnataka
| Project Name | Torino |
| Project Description | 1 Basement + Ground floor + 12 Floor |
| Project Type | Residential/Group Housing |
| Project Status | New Project Launch |
| Project Start Date | 20-09-2018 |
| Proposed Project Completion Date | 31-03-2023 |
| Total Area Of Land (Sq Mtr) | 1781 |
| Total Coverd Area (Sq Mtr) | 496 |
| Total Open Area (Sq Mtr) | 1285 |
| Estimated Cost of Construction (INR) | 240400138 |
| Cost of Land (INR) | 58310340 |
| Total Project Cost (INR) | 336818686 |
| Project Address | Begur Village, Next to Hulimavu Lake, Akshay Nagar, Begur Hobli, Bangalore South Taluk/ Tehsil, Bangalore District 560068 |
| District | Mumbai Suburban |
| Taluk | Bengaluru South |
| Approving Authority | BBMP - Bruhat Bengaluru Mahanagara Palike |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 96 |
| Area of Parking for Sale (Sq Mtr) | 1320 |
| Road System | Self Development |
| Water Supply | Local Authority |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Self Development |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Self Development |
| Bank Name | ICICI Bank |
| Branch | Powai |
| ifscCode | ICIC0000020 |
| Account No.(70% Account) | 777705205070 |
| State | Maharashtra |
| Promoter Type | Company |
| Name | Debdoot Das |
| PAN Number | AALCS0443D |
| Address | 514 Dalamal Tower, FJP Marg , Nariman Point, Mumbai |
| District | Mumbai City |
| State/UT | Maharashtra |
| PIN Code | 400021 |
| Company Registration No. | U45200MH2007PTC172213 |
| Extension Applied On | 01-09-2022 |
| Extension Approved On | 30-09-2022 |
| Extension Registration Number | EX/PRM/KA/RERA/1251/310/PR/220930/002472 |
| Proposed Project End Date at the time of registration | 30-09-2022 |
| Project End Date provided under Section 6 | 31-03-2023 |
| whether 2/3rd concern from the allottees has taken? | NO |
| Whether any compensation is provided for the Buyer? | NO |
| Document Name | Exhibit 7 |
| 1 | Force Majeure |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 10-09-2018 | 20-11-2018 |
| 2 | Foundation footing work | Yes | 25-09-2018 | 30-11-2018 |
| 3 | Retaining wall (All types) | Yes | 05-03-2019 | 20-09-2019 |
| 4 | Plinth level Beam | Yes | 28-01-2019 | 25-02-2019 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 15-01-2020 | 28-02-2020 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | Yes |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | Yes |
| FAR Sanctioned | 5173.62 |
| Number of Towers | 1 |
| 0 | 0 |
| 1 | 8 |
| 2 | 8 |
| 3 | 8 |
| 4 | 8 |
| 5 | 8 |
| 6 | 8 |
| 7 | 8 |
| 8 | 8 |
| 9 | 8 |
| 10 | 8 |
| 11 | 8 |
| 12 | 8 |
| Total No of Units | 96 |
| Project Start Date | 20-09-2018 |
| Project End Date | 31-03-2023 |
| If any extension of time has been granted | YES |
| Extended From Date | 30-09-2022 |
| Extended End Date | 31-03-2023 |
| Cost of land | 58310340 |
| Cost of construction | 240400138 |
| Total project cost | 336818686 |
| Total amount collected from buyers | 280700000 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 249700000 |
| Balance amount with the promoter | 31000000 |
| Total number of Flats/Apartments of the Project | 96 |
| Total number of Flats/Apartments sold | 96 |
| Total number of Flats/Apartments Unsold | 0 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 21-03-2023 |
| Appeals / FNH | NO APPEALS / FNH |