UNNATHI VAIBHAVI
M/S Bhoo Developers Represented by Mr A M Ganeshan Mr K Perumal Mr Akshay Mrs B Shubha
SURVEY NO 99 KHATHA NO 96 HORAMAVU AGARA VILLAGE , K R PURAM HOBLI WARD NO 25
Approved
11th Jul 2019
Completed
2nd Mar 2023
Registration No.
PRM/KA/RERA/1251/446/PR/190711/002666
Acknowledgement No.
ACK/KA/RERA/1251/446/PR/190411/003216
Project Type
Residential/Group Housing
Approving Authority
BBMP - Bruhat Bengaluru Mahanagara Palike
District
Bengaluru Urban
Taluka
Bengaluru East
State
Karnataka
Project Details
| Project Name | UNNATHI VAIBHAVI |
| Project Description | RESIDENTIAL APARTMENT WITH 176 FLATS AND ALL AMENITIES. |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| Project Start Date | 02-01-2019 |
| Proposed Project Completion Date | 02-03-2023 |
| Total Area Of Land (Sq Mtr) | 8689 |
| Total Coverd Area (Sq Mtr) | 19515 |
| Total Open Area (Sq Mtr) | 172 |
| Estimated Cost of Construction (INR) | 400000000 |
| Cost of Land (INR) | 350000000 |
| Total Project Cost (INR) | 750000000 |
| Project Address | SURVEY NO 99 KHATHA NO 96 HORAMAVU AGARA VILLAGE , K R PURAM HOBLI WARD NO 25 |
| District | Bengaluru Urban |
| Taluk | Bengaluru East |
| Approving Authority | BBMP - Bruhat Bengaluru Mahanagara Palike |
| No of Garage for Sale | 176 |
| Area of Garage for Sale (Sq Mtr) | 2420 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Road System | Local Authority |
| Water Supply | Local Authority |
| Sewege and Drainage System | Local Authority |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Local Authority |
| Fire Fighting facility | Local Authority |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Local Authority |
| Bank Name | ICICI Bank |
| Branch | KAMANHALLI |
| ifscCode | ICIC0000298 |
| Account No.(70% Account) | 029805004843 |
| State | Karnataka |
| Name | Y BHASKAR |
| Address | #329 17TH C CROSS 10TH MAIN,INDIRANAGAR 2ND STAGE |
| Pin Code | 560038 |
| Year Of Establishment | 2005 |
| Number of Project Completed | 110 |
| Reg. Of COA No. | BCC/BL-3.6/E-4350/2018-19 |
| Local Authority Licence Number | BCC/BL-3.6/SE-0315/2019-20 |
Promoter Details
| Promoter Type | Partnership Firm |
| Name | K PERUMAL |
| PAN Number | AAT******* |
| Address | 257 Govindappa Cross R S Palya.Kammanahalli Main Road |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560037 |
| Company Registration No. | SJN F642 2018 19 |
| Type | Others |
| Pin Code | 560033 |
Project Development Schedule
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 02-01-2019 | 15-03-2019 |
| 2 | Foundation footing work | Yes | 15-01-2019 | 15-04-2019 |
| 3 | Retaining wall (All types) | Yes | 25-01-2019 | 15-05-2019 |
| 4 | Plinth level Beam | Yes | 15-02-2019 | 15-06-2019 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | No |
Amenities & Utilities Availability
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | Yes |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | Yes |
| 11 | Education/Health/Other public amenities | Yes |
Post Registration Details
| FAR Sanctioned | 2.0 |
| Number of Towers | 1 |
| 0 | 44 |
| 1 | 44 |
| 2 | 44 |
| 3 | 44 |
| Total No of Units | 176 |
Completion Details
| Project Start Date | 02-01-2019 |
| Project End Date | 02-03-2023 |
| If any extension of time has been granted | NO |
| Cost of land | 350000000 |
| Cost of construction | 400000000 |
| Total project cost | 750000000 |
| Total amount collected from buyers | 530464532 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 498794030 |
| Balance amount with the promoter | 31670502 |
| Total number of Flats/Apartments of the Project | 176 |
| Total number of Flats/Apartments sold | 88 |
| Total number of Flats/Apartments Unsold | 0 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 10-12-2021 |
Appeals & Complaints
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in