V.S.R VENTURES
Katha No.9, Sy No.28/1, Horamavu Village, K.R.Puram Hobli
Approved
23rd Mar 2020
Completed
30th Sept 2025
Registration No.
PRM/KA/RERA/1251/446/PR/200323/003370
Acknowledgement No.
ACK/KA/RERA/1251/446/PR/200229/003934
Project Type
Residential/Group Housing
Approving Authority
BBMP - Bruhat Bengaluru Mahanagara Palike
District
Bengaluru Urban
Taluka
Bengaluru East
State
Karnataka
| Project Name | V.S.R TRANQUIL |
| Project Description | Residential High Rise Apartments. |
| Project Type | Residential/Group Housing |
| Project Status | New Project Launch |
| Project Start Date | 28-02-2020 |
| Proposed Project Completion Date | 30-09-2025 |
| Total Area Of Land (Sq Mtr) | 7255 |
| Total Coverd Area (Sq Mtr) | 2123 |
| Total Open Area (Sq Mtr) | 1504 |
| Estimated Cost of Construction (INR) | 685825450 |
| Cost of Land (INR) | 527076000 |
| Total Project Cost (INR) | 1212901450 |
| Project Address | Katha No.9, Sy No.28/1, Horamavu Village, K.R.Puram Hobli |
| District | Bengaluru Urban |
| Taluk | Bengaluru East |
| Approving Authority | BBMP - Bruhat Bengaluru Mahanagara Palike |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Type of Inventory | Residential Flats |
| No of Inventory | 183 |
| Carpet Area (Sq Mtr) | 14478SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 1249SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 642SqMtr |
| Road System | Local Authority |
| Water Supply | Local Authority |
| Sewege and Drainage System | Local Authority |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Self Development |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Self Development |
| Inner Play Area | Self Development |
| Bank Name | Punjab National Bank |
| Branch | Indiranagar Branch |
| ifscCode | PUNB0126800 |
| Account No.(70% Account) | 1268002100017446 |
| State | Karnataka |
| Name | V.S.R VENTURES |
| Address | Katha No.9, Sy No.28/1, Horamavu Village,K.R.Puram Hobli, |
| Pin Code | 560043 |
| Year Of Establishment | 2013 |
| Number of Project Completed | - |
| Reg. Of COA No. | - |
| Local Authority Licence Number | - |
| Number Of Project Completed | - |
| Promoter Type | Partnership Firm |
| Name | M.Dhananjaya Reddy |
| PAN Number | AAKFV6151D |
| Address | No.87, 3rd Cross, Bhuvaneshwari Nagar.C.V.Raman Nagar Post |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560043 |
| Company Registration No. | NA |
| Type | Board Member |
| Pin Code | 560093 |
| Type of Inventory | Residential Flats |
| No of Inventory | 183 |
| Carpet Area (Sq Mtr) | 14478 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 1249 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 642 Sq Mtr |
| Extension Applied On | 19-09-2024 |
| Extension Approved On | 16-12-2024 |
| Extension Registration Number | EX/PRM/KA/RERA/1251/446/PR/241216/003370 |
| Proposed Project End Date at the time of registration | 30-09-2024 |
| Project End Date provided under Section 6 | 30-09-2025 |
| whether 2/3rd concern from the allottees has taken? | NO |
| Whether any compensation is provided for the Buyer? | NO |
| Document Name | Form - B |
| 1 | Shortage of Labour |
| Document Name_1 |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 01-10-2019 | 30-11-2020 |
| 2 | Foundation footing work | Yes | 01-12-2019 | 31-12-2020 |
| 3 | Retaining wall (All types) | Yes | 01-11-2019 | 31-12-2020 |
| 4 | Plinth level Beam | Yes | 01-11-2019 | 31-12-2020 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 06-05-2020 | 16-01-2021 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | No |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | No |
| 5 | Street Lighting | No |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | No |
| 7 | Solid waste management and disposal | No |
| 8 | Water conservation | No |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | No |
| FAR Sanctioned | 20856.0 |
| Number of Towers | 3 |
| 0 | 6 |
| 1 | 6 |
| 2 | 6 |
| 3 | 6 |
| 4 | 6 |
| 5 | 6 |
| 6 | 6 |
| 7 | 6 |
| 8 | 6 |
| 9 | 6 |
| 10 | 2 |
| 11 | 0 |
| Total No of Units | 183 |
| Project Start Date | 28-02-2020 |
| Project End Date | 30-09-2025 |
| If any extension of time has been granted | YES |
| Extended From Date | 30-09-2024 |
| Extended End Date | 30-09-2025 |
| Cost of land | 527076000 |
| Cost of construction | 685825450 |
| Total project cost | 1212901450 |
| Total amount collected from buyers | 881404882 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 811406945 |
| Balance amount with the promoter | 69997937 |
| Total number of Flats/Apartments of the Project | 183 |
| Total number of Flats/Apartments sold | 105 |
| Total number of Flats/Apartments Unsold | 78 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 01-08-2025 |
| Appeals / FNH | NO APPEALS / FNH |