WONDERWALL -Phase II, Block-1

BRICKS AND MILESTONES PROJECTS LLP

Sy.No.22 Sompura Village, Sarjapura Hobli, Anekal Taluk, Bengalur Urban, Sy.No.22 Sompura Village, Sarjapura Hobli, Anekal Taluk, Bengalur Urban

Approved

4th Aug 2021

Completed

31st Mar 2025

Registration No.

PRM/KA/RERA/1251/308/PR/210804/004226

Acknowledgement No.

ACK/KA/RERA/1251/308/PR/210610/005013

Project Type

Residential/Group Housing

Approving Authority

BMRDA - Bangalore Metropolitan Region Development Authority

District

Bengaluru Urban

Taluka

Anekal

State

Karnataka

Project Details

Project NameWONDERWALL -Phase II, Block-1
Project DescriptionWONDERWALL Phase-II, Block-1 is a part of larger development in the Project Wonderwall. Now Wonderwall Phase-II, Block -1, is getting registered with the KRERA, consisting 58 Apartments on a land measuring 1 acre ¼ guntas.
Project TypeResidential/Group Housing
Project StatusNew Project Launch
Project Start Date22-03-2021
Proposed Project Completion Date31-03-2025
Total Area Of Land (Sq Mtr)4754
Total Coverd Area (Sq Mtr)1024
Total Open Area (Sq Mtr)3730
Estimated Cost of Construction (INR)304027200
Cost of Land (INR)11172156
Total Project Cost (INR)315199356
Project AddressSy.No.22 Sompura Village, Sarjapura Hobli, Anekal Taluk, Bengalur Urban, Sy.No.22 Sompura Village, Sarjapura Hobli, Anekal Taluk, Bengalur Urban
DistrictBengaluru Urban
TalukAnekal
Approving AuthorityBMRDA - Bangalore Metropolitan Region Development Authority
No of Garage for Sale0
Area of Garage for Sale (Sq Mtr)0
No of Parking for Sale4
Area of Parking for Sale (Sq Mtr)55
Type of Inventory3 BHK
No of Inventory33
Carpet Area (Sq Mtr)3641SqMtr
Area of exclusive balcony/verandah (Sq Mtr)0SqMtr
Area of exclusive open terrace if any (Sq Mtr)0SqMtr
Road SystemSelf Development
Water SupplyLocal Authority
Sewege and Drainage SystemSelf Development
Electricity Supply Transformer And Sub StationLocal Authority
Solid Waste Management And DisposalSelf Development
Fire Fighting facilityLocal Authority
Drinking Water FacilitySelf Development
Emergency Evacuation ServicesLocal Authority
Use of Renewable EnergyLocal Authority
Bank NameAxis Bank
BranchBeguru KT
ifscCodeUTIB0003960
Account No.(70% Account)921020019568489
StateKarnataka
NamePraveen Kumar Gurrala
AddressVijaya Arch, No.A-6, 2nd A Cross, PNS Layout, 2nd Block, HRBR Layout, Banasavadi, Bangalore ,Vijaya Arch, No.A-6, 2nd A Cross, PNS Layout, 2nd Block, HRBR Layout, Banasavadi, Bangalore
Pin Code560043
Year Of Establishment2000
Number of Project Completed100
Reg. Of COA No.BCC/BL-3.6/SE-203/2015-16
Local Authority Licence NumberBCC/BL-3.6/SE-203/2015-16

Promoter Details

Promoter TypeCompany
NameV KIRAN
PAN NumberAASFB2952L
AddressNo.1140, 4th Floor,17th Cross, 7th Sector, HSR Layout, Bengaluru – 560 102. , No.1140, 4th Floor,17th Cross, 7th Sector, HSR Layout, Bengaluru – 560 102.
DistrictBengaluru Urban
State/UTKarnataka
PIN Code560102
Company Registration No.AAD6195
Sl No.

Modification Plan Details

Type of Inventory3 BHK
No of Inventory33
Carpet Area (Sq Mtr)3641 Sq Mtr
Area of exclusive balcony/verandah (Sq Mtr)0 Sq Mtr
Area of exclusive open terrace if any (Sq Mtr)0 Sq Mtr

Project Development Schedule

Sl NoProject WorkIs Applicable ?Estimated From DateEstimated To Date
1Earth work and other leveling preparation workYes29-05-202130-08-2021
2Foundation footing workYes08-06-202112-09-2021
3Retaining wall (All types)Yes19-06-202115-09-2021
4Plinth level BeamYes06-07-202130-08-2021
5Sub-structure flooring (Parking Floor, more than one floor below general ground level)No

Amenities & Utilities Availability

SlNo.WorkIs Applicable ?
1Water SupplyYes
2Internal Roads & FootpathsYes
3Sewage and Drainage SystemYes
4Parks & Tree plantingYes
5Street LightingYes
6Provision for community buildings and for treatment and disposal of sewage and sullage waterNo
7Solid waste management and disposalYes
8Water conservationYes
9Energy managementYes
10Fire protection and fire safety requirementsNo
11Education/Health/Other public amenitiesYes

Post Registration Details

FAR Sanctioned1.82
Number of Towers1
00
10
210
38
48
58
68
78
88
Total No of Units58

Completion Details

Project Start Date22-03-2021
Project End Date31-03-2025
If any extension of time has been grantedNO
Cost of land11172156
Cost of construction304027200
Total project cost315199356
Total amount collected from buyers204016641
Whether any loan has been raisedYES
Total amount spent for completion of the project322973859
Balance amount with the promoter0
Total number of Flats/Apartments of the Project58
Total number of Flats/Apartments sold54
Total number of Flats/Apartments Unsold4
Whether the project has been completed within the stipulated Period?YES
Whether there is any Change in inventory list or specification?NO
As built drawing approved by the planning AuthorityNO
Occupancy certificate received?YES
Occupancy certificate received date16-05-2023

Appeals & Complaints

Appeals / FNHNO APPEALS / FNH
Complaints on PromoterNo Complaints Found.
Complaints on ProjectNo Complaints Found.

Top Properties in Mysore

Pexo Icon

Ask Pulse Ai anything about real estate

Unlock the Latest in Real Estate

News, Infographics, Blogs & More! Delivered to your inbox.

Proptech Pulse Logo

Data that drives action.
Insight that inspires action.
Technology that empowers action.“

Made with Love

Statue

© PropTech Pulse 2026, All rights reserved.

Terms of Use and Privacy Policy