QVC REALTY DEVELOPERS PVT. LTD.
Chikkaballapur
Approved
28th Oct 2022
Pending
31st Mar 2027
Registration No.
PRM/KA/RERA/1254/460/PR/281022/005360
Acknowledgement No.
ACK/KA/RERA/1254/460/PR/220722/006166
Project Type
Plotted Development
District
Chikkaballapura
Taluka
Chikkaballapur
State
Karnataka
| Number of Survey No./CMC No./CTS No./PID No. | 2 |
| Is there any Litigations on Land/Property/Khatha? | NO |
| Type of Firm | Company |
| Promoter Name | QVC REALTY DEVELOPERS PVT. LTD. |
| Main Objectives | To carry on the business of Property developers including Planners, Promoters, Developers of townships and Layouts and builders of Houses, Villas, Bungalows, Cottages, Residential Apartments and Flats of all types. |
| Registration Number | U70109KA2018PTC111514 |
| PAN | AAUPG9363Q |
| GSTIN | 29AAACQ5284H1Z4 |
| Promoter Website | QVCREALTY.COM |
| Promoter Address | 619, Aceron Tervezo, First Floor, 6th B Main, 17th ACross, Indiranagar 2nd Stage, Bangalore 560038,619, Aceron Tervezo, First Floor, 6th B Main, 17th ACross, Indiranagar 2nd Stage, Bangalore 560038 ,Bengaluru North ,Bengaluru Urban-560038 |
| District | Chikkaballapura |
| Taluk | Bengaluru North |
| PIN Code | 560038 |
| Name of Authorized Signatory | PRAKASH GURBAXANI |
| Name of CEO/MD | PRAKASH GURBAXANI |
| Designation | MANAGING DIRECTOR |
| Director Identification (DIN) Number | 00255401 |
| Number of Directors | 2 |
| Is there any RERA Registrations in other State / UT ? | NO |
| Is there any Projects Launched In The Past 5 Years in Karnataka ? | YES |
| Project Name | MANTRI HILLS |
| Project Description | Plotted development in Anghatta Village, Nandi Hills, Chikkaballapura Dist. |
| Type of Project | Plotted Development |
| Current Status | Completed |
| Is there any case pending ? | NO |
| Is Payment Pertaining to Project Land Pending ? | NO |
| Project Address | Anghatta Village, Nandi Hobli, Chikkaballapura District, Bengaluru. |
| State/UT | Karnataka |
| Pin Code | 562103 |
| Present Address | 249, Phase 1, Adarsh Palm Meadows, Whitefield Road, Ramagondanahalli, Bengaluru - 560 066 , Bengaluru Urban , Karnataka - 560066 |
| Permanent Address | 249, Phase 1, Adarsh Palm Meadows, Whitefield Road, Ramagondanahalli, Bengaluru - 560 066 , Bengaluru Urban , Karnataka - 560066 |
| Official Address | 619, Aceron Tervezo, 6th B Main, 17th A Cross, Indira Nagar 2nd Stage, Bengaluru - 560 038 , Bengaluru Urban , Karnataka - 560038 |
| Sl No. | |
| Sl No._1 | |
| Sl No._2 | |
| Sl No._3 |
| Type of Inventory | 12.19 X ODD |
| No of Inventory | 3 |
| Carpet Area (Sq Mtr) | 0 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Sl No. | Plot No. | Plot Type | Plot Size | Plot Area | Phase | Stage | North Dimension | South Dimension | East Dimension | West Dimension | North Schedule Dimension | South Schedule Dimension | East Schedule Dimension | West Schedule Dimension |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 1 | Plot - 1 | 15.24m X Odd | 363.600 | N.A. | In Progress | 24.56 | 23.16 | 15.3 | 15.24 | Civic Amenities | Plot - 02 | Project Boundary Wall | 12M Wide Road |
| 2 | 2 | Plot - 2 | 15.24m X Odd | 341.18 | N.A. | In Progress | 23.16 | 21.62 | 15.32 | 15.24 | Plot - 01 | Plot - 03 | Project Boundary Wall | 12M Wide Road |
| 3 | 3 | Plot - 3 | 15.24m X Odd | 316.9 | N.A. | In Progress | 21.62 | 19.94 | 15.33 | 15.24 | Plot - 02 | Plot - 04 | Project Boundary Wall | 12M Wide Road |
| 4 | 4 | Plot - 4 | Odd | 264.62 | N.A. | In Progress | 19.94 | 18.36 | 14.7 | 13.01 | Plot - 03 | Project Boundary Wall | Project Boundary Wall | 12M Wide Road |
| 5 | 5 | Plot - 5 | Odd | 197.63 | N.A. | In Progress | 18.29 | 18.08 | 12.16 | 9.57 | Plot - 06 | Project Boundary Wall | 12M Wide Road | Plot - 16 |
| 6 | 6 | Plot - 6 | 12.19m X 18.29m | 222.955 | N.A. | In Progress | 18.29 | 18.29 | 12.19 | 12.19 | Plot - 07 | Plot - 05 | 12M Wide Road | Plot - 15 |
| 7 | 7 | Plot - 7 | 12.19m X 18.29m | 222.955 | N.A. | In Progress | 18.29 | 18.29 | 12.19 | 12.19 | Plot - 08 | Plot - 06 | 12M Wide Road | Plot - 14 |
| 8 | 8 | Plot - 8 | 12.19m X 18.29m | 222.955 | N.A. | In Progress | 18.29 | 18.29 | 12.19 | 12.19 | Plot - 09 | Plot - 07 | 12M Wide Road | Plot - 13 |
| 9 | 9 | Plot - 9 | 12.19m X 18.29m | 222.955 | N.A. | In Progress | 18.29 | 18.29 | 12.19 | 12.19 | Plot - 10 | Plot - 08 | 12M Wide Road | Plot - 12 |
| 10 | 10 | Plot - 10 | 12.19m X 18.29m | 222.955 | N.A. | In Progress | 18.29 | 18.29 | 12.19 | 12.19 | 12M Wide Road | Plot - 09 | 12M Wide Road | Plot - 11 |
| 11 | 11 | Plot - 11 | 12.19m X 18.29m | 222.955 | N.A. | In Progress | 18.29 | 18.29 | 12.19 | 12.19 | 12M Wide Road | Plot - 12 | Plot - 10 | 12M Wide Road |
| 12 | 12 | Plot - 12 | 12.19m X 18.29m | 222.955 | N.A. | In Progress | 18.29 | 18.29 | 12.19 | 12.19 | Plot - 11 | Plot - 13 | Plot - 09 | 12M Wide Road |
| 13 | 13 | Plot - 13 | 12.19m X 18.29m | 222.955 | N.A. | In Progress | 18.29 | 18.29 | 12.19 | 12.19 | Plot - 12 | Plot - 14 | Plot - 08 | 12M Wide Road |
| 14 | 14 | Plot - 14 | 12.19m X 18.29m | 222.955 | N.A. | In Progress | 18.29 | 18.29 | 12.19 | 12.19 | Plot - 13 | Plot - 15 | Plot - 07 | 12M Wide Road |
| 15 | 15 | Plot - 15 | 9.14m X 18.29m | 167.17 | N.A. | In Progress | 18.29 | 18.29 | 9.14 | 9.14 | Plot - 14 | Plot - 16 | Plot - 06 | 12M Wide Road |
| 16 | 16 | Plot - 16 | Odd | 206.69 | N.A. | In Progress | 18.29 | 18.48 | 12.62 | 9.98 | Plot - 15 | Project Boundary Wall | Plot - 05&06 | 12M Wide Road |
| 17 | 17 | Plot - 17 | Odd | 352.64 | N.A. | In Progress | 22.36 | 22.59 | 17.35 | 14.16 | Plot - 18 | Project Boundary Wall | 12M Wide Road | 3.00m Pathway and park thereafter |
| 18 | 18 | Plot - 18 | 12.19m X Odd | 272.56 | N.A. | In Progress | 22.36 | 22.36 | 12.19 | 12.19 | Plot - 19 | Plot - 17 | 12M Wide Road | 3.00m Pathway and park thereafter |
| 19 | 19 | Plot - 19 | 12.19m X Odd | 272.56 | N.A. | In Progress | 22.36 | 22.36 | 12.19 | 12.19 | Plot - 20 | Plot - 18 | 12M Wide Road | 3.00m Pathway and park thereafter |
| 20 | 20 | Plot - 20 | 12.19m X Odd | 272.56 | N.A. | In Progress | 22.36 | 22.36 | 12.19 | 12.19 | Plot - 21 | Plot - 19 | 12M Wide Road | 3.00m Pathway and park thereafter |
| 21 | 21 | Plot - 21 | 12.19m X 18.29m | 222.955 | N.A. | In Progress | 18.29 | 18.29 | 12.19 | 12.19 | 3.00m Pathway and park thereafter | Plot - 20 | 12M Wide Road | 3.00m Pathway and park thereafter |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Ground Clearance/Formation Of Plots | Yes | 15-05-2022 | 31-03-2023 |
| 2 | Formation Of Road, Footpath | Yes | 15-05-2023 | 31-03-2024 |
| 3 | Construction Of Water Supply Infrastucture | Yes | 15-07-2022 | 31-03-2024 |
| 4 | Construction Of Sewage System Infrastucture | Yes | 15-07-2022 | 31-03-2024 |
| 5 | Power Supply Work(Transformer & Substation) | Yes | 15-08-2022 | 31-03-2024 |
| 6 | Construction Of Storm Water Drainage | Yes | 15-10-2022 | 31-03-2024 |
| 7 | Solid Waste Management and Disposal | Yes | 15-10-2022 | 31-03-2025 |
| 8 | Tree Plantation And LandScape Work | Yes | 15-12-2022 | 31-03-2026 |
| 9 | Street Lighting | Yes | 15-12-2022 | 31-03-2027 |
| 10 | Sewage Treatment Plant (STP) | Yes | 15-07-2022 | 31-03-2027 |
| 11 | Other Miscellaneous Work | Yes | 15-12-2022 | 31-03-2027 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Electricity | Yes |
| 2 | Smart home automation | No |
| 3 | CCTV surveillance | No |
| 4 | Club House | No |
| 5 | Community Hall | No |
| 6 | Outdoor Sports facility | No |
| 7 | Indoor sports facility | No |
| 8 | Swimming Pools | No |
| 9 | Gym | No |
| 10 | Parks | Yes |
| 11 | Power Backup | No |
| 12 | Piped Gas | No |
| 13 | Water and Sanitation | No |
| 14 | Air conditioning | No |
| WebSite Link 1 | https://www.qvcrealty.com |
| Agent Registration No 1 | Nil |
| Total number of Plots | 21 |
| No. of Public and Semi Pubic Sites | 1 |
| Area of Public and Semi Pubic Sites(in Sq.m) | 493 |
| No. of Parks and Open Spaces | 1 |
| Area of Parks and Open Spaces(in Sq.m) | 963 |
| Area of Road/Transportation(in Sq.m) | 2897 |
| Project Start Date | 15-05-2022 |
| Project End Date | 31-03-2027 |
| If any extension of time has been granted | NO |
| Cost of land | 208800000 |
| Cost of construction | 40000000 |
| Total cost | 248800000 |
| Total amount collected From buyers | 0 |
| Whether any loan has been raised | NO |
| Total amount spent on Project for completion of the project | 48868341 |
| Total No of sites of Project | 21 |
| Total No of sites sold | 0 |
| Total No of sites unsold | 21 |
| Whether there is any changes in inventory details | NO |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |