THE AMPELON 2
TEFILAH INFRASTRUCTURE PVT LTD
Sy No 140 and Sy No 139/2, Kakalachinta Village, Mandikallu Hobili, Chikkaballapura Taluk
Approved
25th Oct 2019
Completed
31st Mar 2024
Registration No.
PRM/KA/RERA/1254/460/PR/191025/002973
Acknowledgement No.
ACK/KA/RERA/1254/460/PR/191003/003588
Project Type
Plotted Development
Approving Authority
Chikkaballapur Urban Development Authority
District
Chikkaballapura
Taluka
Chikkaballapur
State
Karnataka
Project Details
| Project Name | THE AMPELON 2 |
| Project Description | Sy No 139/2 and 140, Situated at Chikkaballapur, Total No of site 18. |
| Project Type | Plotted Development |
| Project Status | Completed |
| Project Start Date | 10-10-2019 |
| Proposed Project Completion Date | 30-07-2023 |
| Further Extension Date | 31-03-2024 |
| Total Area Of Land (Sq Mtr) | 23573 |
| Total Coverd Area (Sq Mtr) | 11703 |
| Total Open Area (Sq Mtr) | 11870 |
| Estimated Cost of Construction (INR) | 24000000 |
| Cost of Land (INR) | 66000000 |
| Total Project Cost (INR) | 90000000 |
| Project Address | Sy No 140 and Sy No 139/2, Kakalachinta Village, Mandikallu Hobili, Chikkaballapura Taluk |
| District | Bengaluru Urban |
| Taluk | Chikkaballapur |
| Approving Authority | Chikkaballapur Urban Development Authority |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Type of Inventory | Plotted Development |
| No of Inventory | 18 |
| Carpet Area (Sq Mtr) | 0SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0SqMtr |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Self Development |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Self Development |
| Bank Name | STATE BANK OF INDIA |
| Branch | IN CUBE, ST MARK'S ROAD |
| ifscCode | SBIN0011349 |
| Account No.(70% Account) | 33282024582 |
| State | Karnataka |
| Name | Nikki Thomas |
| Address | No 167 D, HSR Layout, 2nd Sector,31st Main Road, 19th Cross, Near NIFT College |
| Pin Code | 560102 |
| Year Of Establishment | 1988 |
| Number Of Project Completed | 75 |
Promoter Details
| Promoter Type | Company |
| Name | SIDDARTHA GUPTA |
| PAN Number | AAD******* |
| Address | 23/5, REST HOUSE CRESCENT ROAD , OFF CHURCH STREET |
| District | Bengaluru Urban |
| State/UT | Karnataka |
| PIN Code | 560001 |
| Company Registration No. | U45200KA2011PTC056902 |
Modification Plan Details
| Type of Inventory | Plotted Development |
| No of Inventory | 18 |
| Carpet Area (Sq Mtr) | 0 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
Extension Details
| Extension Applied On | 09-09-2023 |
| Extension Approved On | 27-10-2023 |
| Extension Registration Number | EX/PRM/KA/RERA/1254/460/PR/231027/002973 |
| Proposed Project End Date at the time of registration | 30-07-2022 |
| Project End Date provided under Section 6 | 30-07-2023 |
| whether 2/3rd concern from the allottees has taken? | NO |
| Whether any compensation is provided for the Buyer? | NO |
| Document Name | Form_B |
| 1 | Delay in getting loan |
Residential Plot Details
| Sl No. | Plot No. | Plot Type | Plot Size | Plot Area | Phase | Stage | North Dimension | South Dimension | East Dimension | West Dimension | North Schedule Dimension | South Schedule Dimension | East Schedule Dimension | West Schedule Dimension |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | B1 | Residential | (13.26 + 24.36) + 55.32 | 2920 | 1 | ongoing | Survey # 196 | Survey # 150 | Civic Amenities & Site # B2, B3, B4 | Survey # 141 | Survey # 196 | Survey # 150 | Civic Amenities & Site # B2, B3, B4 | Survey # 141 |
| 2 | B2 | Residential | 22.9 + 22.95 | 413 | 1 | ongoing | Civic Amenities | Site # B3 | Road | Site # B1 | Civic Amenities | Site # B3 | Road | Site # B1 |
| 3 | B3 | Residential | 22.84 + 22.9 | 412 | 1 | ongoing | Site # B2 | Site # B4 | Road | Site # B1 | Site # B2 | Site # B4 | Road | Site # B1 |
| 4 | B4 | Residential | 22.81 + 22.84 | 425 | 1 | ongoing | Site # B3 | Survey # 160 | Road | Site # B1 | Site # B3 | Survey # 160 | Road | Site # B1 |
| 5 | B5 | Residential | 27.89 + 33.33 | 584 | 1 | ongoing | Park | Site # B6 | Survey # 140 & Park | Road | Park | Site # B6 | Survey # 140 & Park | Road |
| 6 | B6 | Residential | 28.17 + 27.89 | 637 | 1 | ongoing | Site # B5 | Survey # 151 | Civic Amenities & Site # B2, B3, B4 | Survey # 142 | Site # B5 | Survey # 151 | Civic Amenities & Site # B2, B3, B4 | Survey # 142 |
| 7 | B7 | Residential | 33.79 + 28.17 | 614 | 1 | ongoing | Site # B6 | Site # B7 | Road | Site # B2 | Site # B6 | Site # B7 | Road | Site # B2 |
| 8 | B8 | Residential | 29.82 + 25.52 | 457 | 1 | ongoing | Site # B9 | Site # B8 | Road | Site # B3 | Site # B9 | Site # B8 | Road | Site # B3 |
| 9 | B9 | Residential | 25.52 + 26.87 | 493 | 1 | ongoing | Site # B10 | Survey # 152 | Road | Site # B5 | Site # B10 | Survey # 152 | Road | Site # B5 |
| 10 | B10 | Residential | 26.87 + 31.56 | 565 | 1 | ongoing | Survey # 139 & Park | Site # B10 | Survey # 141 & Park | Road | Survey # 139 & Park | Site # B10 | Survey # 141 & Park | Road |
| 11 | B11 | Residential | 25.35 + 27.92 | 533 | 1 | ongoing | Survey # 139 & Park | Survey # 153 | Civic Amenities & Site # B2, B3, B4 | Survey # 143 | Survey # 139 & Park | Survey # 153 | Civic Amenities & Site # B2, B3, B4 | Survey # 143 |
| 12 | B12 | Residential | 25.24 + 25.35 | 461 | 1 | ongoing | Site # B11 | Site # B12 | Road | Site # B6 | Site # B11 | Site # B12 | Road | Site # B6 |
| 13 | B13 | Residential | 32.52 + 25.24 | 515 | 1 | ongoing | Site # B12 | Site # B15 | Road | Site # B7 | Site # B12 | Site # B15 | Road | Site # B7 |
| 14 | B14 | Residential | 33.66 + 29.2 | 614 | 1 | ongoing | Site # B15 | Survey # 15 | Road | Site # B8 | Site # B15 | Survey # 15 | Road | Site # B8 |
| 15 | B15 | Residential | 29.2 + 28.5 | 500 | 1 | ongoing | Site # B16 | Site # B16 | Survey # 132 & Park | Road | Site # B16 | Site # B16 | Survey # 132 & Park | Road |
| 16 | B16 | Residential | 28.5 + 30.92 | 516 | 1 | ongoing | Survey No. 139 & Park | Survey # 152 | Road | Site # B5 | Survey No. 139 & Park | Survey # 152 | Road | Site # B5 |
| 17 | B17 | Residential | 23.68 + 24.73 | 522 | 1 | ongoing | Survey # 139 & Park | Site # B10 | Survey # 141 & Park | Road | Survey # 139 & Park | Site # B10 | Survey # 141 & Park | Road |
| 18 | B18 | Residential | 29.86 + 23.68 | 513 | 1 | ongoing | Site # 17 | Site # B6 | Survey # 140 & Park | Road | Site # 17 | Site # B6 | Survey # 140 & Park | Road |
Project Development Schedule
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Ground Clearance/Formation Of Plots | Yes | 10-10-2019 | 20-03-2020 |
| 2 | Formation Of Road, Footpath | Yes | 22-03-2020 | 06-10-2020 |
| 3 | Construction Of WaterSupply Infrastucture | Yes | 26-03-2020 | 11-11-2020 |
| 4 | Construction Of Sewage System Infrastucture | Yes | 01-11-2020 | 14-03-2021 |
| 5 | Power Supply Work(Tansformer And Substation) | Yes | 05-02-2021 | 10-12-2021 |
| 6 | Construction Of Storm Water Drainage | Yes | 10-02-2021 | 15-12-2021 |
| 7 | Solid Waste Management and Disposal | No | ||
| 8 | Tree Plantation And LandScape Work | Yes | 20-12-2021 | 05-12-2022 |
| 9 | Street Lighting | Yes | 13-12-2022 | 10-01-2023 |
| 10 | Other Miscellaneous Work | Yes | 10-01-2023 | 30-07-2023 |
Amenities & Utilities Availability
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Electricity | Yes |
| 2 | Smart home automation | No |
| 3 | CCTV surveillance | No |
| 4 | Club House | No |
| 5 | Community Hall | No |
| 6 | Outdoor Sports facility | No |
| 7 | Indoor sports facility | No |
| 8 | Swimming Pools | No |
| 9 | Gym | No |
| 10 | Parks | Yes |
| 11 | Power Backup | No |
| 12 | Gas | No |
| 13 | Water and Sanitation | Yes |
| 14 | Air conditioning and incarnation | No |
Post Registration Details
| WebSite Link 1 | www.tefilahinfra.com |
| Total number of Plots | 18 |
| No. of Public and Semi Pubic Sites | 1 |
| Area of Public and Semi Pubic Sites(in Sq.m) | 1184 |
| No. of Parks and Open Spaces | 1 |
| Area of Parks and Open Spaces(in Sq.m) | 2854 |
| Area of Road/Transportation(in Sq.m) | 7832 |
Appeals & Complaints
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in