Sandesh Kumar Shetty
Bappanadu village Mangalore, Bappanadu village Mangalore
Approved
5th Sept 2018
Completed
19th Apr 2022
Registration No.
PRM/KA/RERA/1257/334/PR/180905/001995
Acknowledgement No.
ACK/KA/RERA/1257/334/PR/180727/002496
Project Type
Mixed Development
Approving Authority
Mangaluru Urban Development Authority
District
Dakshina Kannada
Taluka
Mangalore
State
Karnataka
| Project Name | Agraja Atharva |
| Project Description | Commercial cum Residential bulding it contains 2 shops and 50 flats |
| Project Type | Mixed Development |
| Project Status | Completed |
| Project Start Date | 09-07-2018 |
| Proposed Project Completion Date | 19-04-2022 |
| Total Area Of Land (Sq Mtr) | 910 |
| Total Coverd Area (Sq Mtr) | 563 |
| Total Open Area (Sq Mtr) | 308 |
| Estimated Cost of Construction (INR) | 24274689 |
| Cost of Land (INR) | 8000000 |
| Total Project Cost (INR) | 32599689 |
| Project Address | Bappanadu village Mangalore, Bappanadu village Mangalore |
| District | Dakshina Kannada |
| Taluk | Mangalore |
| Approving Authority | Mangaluru Urban Development Authority |
| No of Garage for Sale | 33 |
| Area of Garage for Sale (Sq Mtr) | 580 |
| No of Parking for Sale | 5 |
| Area of Parking for Sale (Sq Mtr) | 62 |
| Road System | Local Authority |
| Water Supply | Local Authority |
| Sewege and Drainage System | Local Authority |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Local Authority |
| Fire Fighting facility | Local Authority |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Local Authority |
| Bank Name | Canara Bank |
| Branch | KODIALBAIL |
| ifscCode | CNRB0001978 |
| Account No.(70% Account) | 1978201000119 |
| State | Karnataka |
| Firm Type | Individual |
| Name | Sandesh Kumar Shetty |
| Father's Name | Kittanna shetty |
| PAN Number | AVJPS6222L |
| Address | 2nd Floor Pam Arcade, Near Indian oil Petrol Pump, Kottara Chowki,2nd Floor Pam Arcade, Near Indian oil Petrol Pump, Kottara Chowki |
| State/UT | Karnataka |
| PIN Code | 575006 |
| Extension Applied On | 26-07-2021 |
| Extension Approved On | 31-12-2022 |
| Extension Registration Number | EX/PRM/KA/RERA/1257/334/PR/221231/001995 |
| Proposed Project End Date at the time of registration | 09-06-2021 |
| Project End Date provided under Section 6 | 19-04-2022 |
| whether 2/3rd concern from the allottees has taken? | YES |
| Whether any compensation is provided for the Buyer? | NO |
| Document Name | REASON FOR DELAY |
| 1 | others |
| Document Name_1 | |
| Document Name_2 | |
| Document Name_3 | |
| Document Name_4 | |
| Document Name_5 | |
| Document Name_6 |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 09-07-2018 | 06-08-2018 |
| 2 | Foundation footing work | Yes | 02-08-2018 | 06-10-2018 |
| 3 | Retaining wall (All types) | Yes | 07-10-2018 | 03-11-2018 |
| 4 | Plinth level Beam | Yes | 04-11-2018 | 30-11-2018 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 01-06-2020 | 30-08-2020 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | No |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | No |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | No |
| 7 | Solid waste management and disposal | No |
| 8 | Water conservation | No |
| 9 | Energy management | No |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | No |
| WebSite Link 1 | www.agrajabuilders.com |
| Agent Registration No 1 | Not applicable |
| FAR Sanctioned | 1.0 |
| Number of Towers | 1 |
| 0 | 2 |
| 1 | 10 |
| 2 | 10 |
| 3 | 10 |
| 4 | 10 |
| 5 | 10 |
| Total No of Units | 52 |
| Project Start Date | 09-07-2018 |
| Project End Date | 09-06-2021 |
| If any extension of time has been granted | NO |
| Extended From Date | 09-06-2021 |
| Extended End Date | 19-04-2022 |
| Cost of land | 8000000 |
| Cost of construction | 24274689 |
| Total project cost | 32599689 |
| Total amount collected from buyers | 55570721 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 72727699 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 52 |
| Total number of Flats/Apartments sold | 31 |
| Total number of Flats/Apartments Unsold | 21 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 19-04-2022 |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |


Ask Pulse Ai anything about real estate
News, Infographics, Blogs & More! Delivered to your inbox.