ARNAVA HOMES

ARANAVA BUILDERS AND DEVELOPERS

NEAR NITK, MUKKA SURATHKAL

Approved

31st Oct 2018

Completed

20th Jul 2021

Registration No.

PRM/KA/RERA/1257/333/PR/181031/002106

Acknowledgement No.

ACK/KA/RERA/1257/333/PR/180728/002499

Project Type

Residential/Group Housing

Approving Authority

Mangaluru Urban Development Authority

District

Dakshina Kannada

Taluka

Dakshina Kannada

State

Karnataka

Project Details

Project NameARNAVA HOMES
Project DescriptionLAND SYNO. 241/1A(P),59/3A(P1,P2) AND 59\5B(P) OF SURTHAKAL VILLAGE,MANGALORE
Project TypeResidential/Group Housing
Project StatusNew Project Launch
Project Start Date20-03-2018
Proposed Project Completion Date20-07-2021
Total Area Of Land (Sq Mtr)2630
Total Coverd Area (Sq Mtr)757
Total Open Area (Sq Mtr)1603
Estimated Cost of Construction (INR)83200000
Cost of Land (INR)13000000
Total Project Cost (INR)96200000
Project AddressNEAR NITK, MUKKA SURATHKAL
DistrictDakshina Kannada
TalukDakshina Kannada
Approving AuthorityMangaluru Urban Development Authority
No of Garage for Sale66
Area of Garage for Sale (Sq Mtr)2275
No of Parking for Sale0
Area of Parking for Sale (Sq Mtr)0
Road SystemLocal Authority
Water SupplyLocal Authority
Sewege and Drainage SystemSelf Development
Electricity Supply Transformer And Sub StationLocal Authority
Solid Waste Management And DisposalSelf Development
Fire Fighting facilitySelf Development
Drinking Water FacilitySelf Development
Emergency Evacuation ServicesLocal Authority
Use of Renewable EnergyLocal Authority
Bank NameCanara Bank
BranchSURATHKAL
ifscCodeCNRB0000634
Account No.(70% Account)0634201000805
StateKarnataka

Promoter Details

Promoter TypePartnership Firm
NameKIRAN KUMAR SHETTY
PAN NumberABHFA2027R
Addressseetha bai compound ,kana,surathkal-575014 , seetha bai compound ,kana,surathkal-575014
DistrictDakshina Kannada
State/UTKarnataka
PIN Code575014
Company Registration No.294201718

Extension Details

Extension Applied On26-02-2020
Extension Approved On21-10-2020
Extension Registration NumberEX/PRM/KA/RERA/1257/333/PR/201021/002106
Proposed Project End Date at the time of registration20-10-2019
Project End Date provided under Section 620-10-2020
whether 2/3rd concern from the allottees has taken?YES
Whether any compensation is provided for the Buyer?NO
Document NameBank Statement - 715
1Shortage of Building Materials, Concrete, Jalli etc
Document Name_1

Project Development Schedule

Sl NoProject WorkIs Applicable ?Estimated From DateEstimated To Date
1Earth work and other leveling preparation workYes21-03-201820-04-2018
2Foundation footing workYes21-04-201821-05-2018
3Retaining wall (All types)No
4Plinth level BeamYes26-05-201810-06-2018
5Sub-structure flooring (Parking Floor, more than one floor below general ground level)No

Amenities & Utilities Availability

SlNo.WorkIs Applicable ?
1Water SupplyYes
2Internal Roads & FootpathsYes
3Sewage and Drainage SystemYes
4Parks & Tree plantingNo
5Street LightingYes
6Provision for community buildings and for treatment and disposal of sewage and sullage waterYes
7Solid waste management and disposalNo
8Water conservationNo
9Energy managementYes
10Fire protection and fire safety requirementsNo
11Education/Health/Other public amenitiesYes

Post Registration Details

FAR Sanctioned1.9
Number of Towers1
00
16
28
38
48
58
68
78
88
Total No of Units62

Completion Details

Project Start Date20-03-2018
Project End Date20-07-2021
If any extension of time has been grantedYES
Extended From Date20-10-2019
Extended End Date20-10-2020
Cost of land13000000
Cost of construction83200000
Total project cost96200000
Total amount collected from buyers25299260
Whether any loan has been raisedNO
Total amount spent for completion of the project96385780
Balance amount with the promoter0
Total number of Flats/Apartments of the Project62
Total number of Flats/Apartments sold32
Total number of Flats/Apartments Unsold30
Whether the project has been completed within the stipulated Period?YES
Whether there is any Change in inventory list or specification?NO
As built drawing approved by the planning AuthorityYES
Occupancy certificate received?YES
Occupancy certificate received date18-02-2021

Appeals & Complaints

Appeals / FNHNO APPEALS / FNH
Complaints on PromoterNo Complaints Found.
Complaints on ProjectNo Complaints Found.

Top Properties in Udupi

Pexo Icon

Ask Pulse Ai anything about real estate

Unlock the Latest in Real Estate

News, Infographics, Blogs & More! Delivered to your inbox.

Proptech Pulse Logo

Data that drives action.
Insight that inspires action.
Technology that empowers action.“

Made with Love

Statue

© PropTech Pulse 2026, All rights reserved.

Terms of Use and Privacy Policy