JENNIFER MENEZES
BEJAI NEW ROAD, BEJAI
Approved
2nd Nov 2017
Completed
31st May 2019
Registration No.
PRM/KA/RERA/1257/334/PR/171102/001917
Acknowledgement No.
PR/KN/170831/001917
Project Type
Residential/Group Housing
Approving Authority
Mangaluru Urban Development Authority
District
Dakshina Kannada
Taluka
Mangalore
State
Karnataka
| Project Name | DIVINE HOMES 'SAVERA' |
| Project Description | RESIDENTIAL APARTMENTS |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| Project Start Date | 01-12-2016 |
| Proposed Project Completion Date | 31-05-2019 |
| Total Area Of Land (Sq Mtr) | 640 |
| Total Coverd Area (Sq Mtr) | 305 |
| Total Open Area (Sq Mtr) | 329 |
| Estimated Cost of Construction (INR) | 38500000 |
| Cost of Land (INR) | 0 |
| Total Project Cost (INR) | 38500000 |
| Project Address | BEJAI NEW ROAD, BEJAI |
| District | Dakshina Kannada |
| Taluk | Mangalore |
| Approving Authority | Mangaluru Urban Development Authority |
| No of Garage for Sale | 16 |
| Area of Garage for Sale (Sq Mtr) | 244 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Type of Inventory | 1,2 ,3 |
| No of Inventory | 4 |
| Carpet Area (Sq Mtr) | 955SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 270SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0SqMtr |
| Road System | Local Authority |
| Water Supply | Local Authority |
| Sewege and Drainage System | Local Authority |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Local Authority |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Self Development |
| RESIDENTIAL APARTMENT | Self Development |
| Bank Name | Canara Bank |
| Branch | FOUNDERS BRANCH |
| ifscCode | CNRB0000611 |
| Account No.(70% Account) | 0611201001246 |
| State | Karnataka |
| Name | Mahabala M |
| Address | Emporium,Kankanady, Mangalore |
| Pin Code | 575002 |
| Year Of Establishment | 1991 |
| Number of Project Completed | 500 |
| Reg. Of COA No. | LBD-95-269/142-2013-18 |
| Local Authority Licence Number | 2012-com31858 |
| Number Of Project Completed | 91 |
| Firm Type | Individual |
| Name | JENNIFER MENEZES |
| Father's Name | MAXIE CRASTO |
| PAN Number | ATFPM7091K |
| Address | 2-13-1152,FLORAINE,BEJAI NEW ROAD, MANGALORE |
| State/UT | Karnataka |
| PIN Code | 575004 |
| Type of Inventory | 1,2 ,3 |
| No of Inventory | 4 |
| Carpet Area (Sq Mtr) | 955 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 270 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Extension Applied On | 18-12-2018 |
| Extension Approved On | 22-12-2020 |
| Extension Registration Number | EX/PRM/KA/RERA/1257/334/PR/201222/001917 |
| Proposed Project End Date at the time of registration | 31-12-2018 |
| Project End Date provided under Section 6 | 31-05-2019 |
| whether 2/3rd concern from the allottees has taken? | NO |
| Whether any compensation is provided for the Buyer? | NO |
| Document Name | COMPLETION CERTIFICATE |
| 1 | Activities undertaken by BMRDA, BBPM, BESCOM etc. leading to delay in construction |
| Document Name_1 | |
| Document Name_2 |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 02-02-2017 | 04-03-2017 |
| 2 | Foundation footing work | Yes | 04-03-2017 | 10-07-2017 |
| 3 | Retaining wall (All types) | Yes | 15-12-2018 | 31-01-2019 |
| 4 | Plinth level Beam | Yes | 05-10-2017 | 03-04-2018 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | No |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | No |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | No |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | No |
| 7 | Solid waste management and disposal | No |
| 8 | Water conservation | Yes |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | Yes |
| FAR Sanctioned | 20723.0 |
| Number of Towers | 1 |
| 0 | 0 |
| 1 | 4 |
| 2 | 4 |
| 3 | 4 |
| 4 | 4 |
| Total No of Units | 16 |
| Project Start Date | 01-12-2016 |
| Project End Date | 31-05-2019 |
| If any extension of time has been granted | YES |
| Extended From Date | 31-12-2018 |
| Extended End Date | 31-05-2019 |
| Cost of land | 0 |
| Cost of construction | 38500000 |
| Total project cost | 38500000 |
| Total amount collected from buyers | 19380806 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 34707526 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 16 |
| Total number of Flats/Apartments sold | 8 |
| Total number of Flats/Apartments Unsold | 8 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 14-09-2019 |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |


Ask Pulse Ai anything about real estate