LAND LINKS ANANTHA NAGAR LAYOUT

J KRISHNA PALEMAR

Mangalore

Approved

2nd Aug 2023

Completed

1st Jun 2024

Registration No.

PRM/KA/RERA/1257/334/PR/020823/006107

Acknowledgement No.

ACK/KA/RERA/1257/334/PR/160623/007206

Project Type

Plotted Development

District

Dakshina Kannada

Taluka

Mangalore

State

Karnataka

Project Details

Number of Survey No./CMC No./CTS No./PID No.11
Is there any Litigations on Land/Property/Khatha?NO

Promoter Details

Type of FirmProprietorship
Promoter NameJ KRISHNA PALEMAR
Main ObjectivesTO PROVIDE GOOD LAYOUTS
Trade NameJ KRISHNA PALEMAR
Registration NumberNA
PANACZPP0444N
GSTIN29ACZPP0444NIZO
Promoter Address5-7-708/9(1) CITY POINT BUILDING ,KODIALBAIL, MANGALORE ,Mangalore ,Dakshina Kannada-575003
DistrictDakshina Kannada
TalukMangalore
PIN Code575003
Name of Authorized SignatoryJ KRISHNA PALEMAR
Is there any RERA Registrations in other State / UT ?NO
Is there any Projects Launched In The Past 5 Years in Karnataka ?NO
Present Address8TH CROSS KODIALGUTHU EAST ROAD BEJAI POST, MANGALORE , Dakshina Kannada , Karnataka - 575003
Permanent Address8TH CROSS KODIALGUTHU EAST ROAD BEJAI POST, MANGALORE , Dakshina Kannada , Karnataka - 575003
Official AddressLAND LINKS ,CITY POINT,KODIALBAIL MANGALORE , Dakshina Kannada , Karnataka - 575003
Sl No.
Sl No._1

Modification Plan Details

Type of InventoryPLOTS
No of Inventory1
Carpet Area (Sq Mtr)849 Sq Mtr
Area of exclusive balcony/verandah (Sq Mtr)0 Sq Mtr
Area of exclusive open terrace if any (Sq Mtr)0 Sq Mtr

Residential Plot Details

Sl No.Plot No.Plot TypePlot SizePlot AreaPhaseStageNorth DimensionSouth DimensionEast DimensionWest DimensionNorth Schedule DimensionSouth Schedule DimensionEast Schedule DimensionWest Schedule Dimension
11RESIDENTIALOdd343.98NAUNDER PROGRESS15.3618.1620.7520.946m wide road6m wide roadplot no.212m wide road
22RESIDENTIAL12.00x20.75242.80NAUNDER PROGRESS121220.7520.756m wide road6m wide roadsurvey.no109-4(P)plot no.1
33RESIDENTIALOdd222.57NAUNDER PROGRESS12.1913.3817.7417.866m wide road6m wide roadplot no.412m wide road
44RESIDENTIALOdd222.57NAUNDER PROGRESS12.1813.3817.717.746m wide road6m wide roadsurvey.no109-5(P)plot no.3
55RESIDENTIALOdd410.75NAUNDER PROGRESS22.0524.4417.717.876m wide road6m wide roadsurvey.no109-5(P)12m wide road
66RESIDENTIALOdd279.23NAUNDER PROGRESS13.4716.0318.9219.099m wide road6m wide roadplot no.712m wide road
77RESIDENTIAL12.80x18.92242.80NAUNDER PROGRESS12.812.818.9218.929m wide road6m wide roadsurvey.no109-5(P)plot no.6.
88RESIDENTIAL16.52x18.92313.63NAUNDER PROGRESS16.5216.5218.9218.929m wide roadsurvey no. 109-5(P)plot no.9survey no. 109-5(P)
99RESIDENTIALOdd849.83NAUNDER PROGRESS33.0834.9125.1925.129m wide roadsurvey no. 109-5(P)survey no. 64plot no.8.
1010RESIDENTIALOdd414.80NAUNDER PROGRESS17.7716.6627.7522.56Survey no.146/1B19m wide roadPlot no. 11 &13 and6m wide road9m wide road
1111RESIDENTIALOdd171.99NAUNDER PROGRESS15.8215.0411.7310.776m wide road9m wide roadplot no.12plot no.10
1212RESIDENTIALOdd202.34NAUNDER PROGRESS16.6816.6512.7611.736m wide road9m wide road9m wide roadplot no.11
1313RESIDENTIALOdd242.80NAUNDER PROGRESS19.1618.5815.3410.98Survey no.146/1B16m wide roadplot no.14plot no.10
1414RESIDENTIALOdd202.34NAUNDER PROGRESS12.5312.218.1615.34Survey no.146/1B16m wide roadplot no.15plot no.13
1515RESIDENTIALOdd202.34NAUNDER PROGRESS9.0413.2118.2218.16Survey no.146/1B19m wide roadplot no.16plot no.14
1616RESIDENTIAL12.20x18.22222.57NAUNDER PROGRESS12.212.218.2218.22Survey no.146/1B19m wide roadplot no.17plot no.15
1717RESIDENTIAL12.20x18.22222.57NAUNDER PROGRESS12.212.218.2218.22Survey no.146/1B19m wide roadplot no.18plot no.16
1818RESIDENTIAL12.20x18.22222.57NAUNDER PROGRESS12.212.218.2218.22Survey no.146/1B19m wide roadplot no.19plot no.17
1919RESIDENTIAL12.20x18.22222.57NAUNDER PROGRESS12.212.218.2218.22Survey no.146/1B19m wide roadplot no.20plot no.18
2020RESIDENTIAL11.10x18.22202.34NAUNDER PROGRESS11.111.118.2218.22Survey no.146/1B19m wide roadplot no.21plot no.19
2121RESIDENTIAL11.10x18.22202.34NAUNDER PROGRESS11.111.118.2518.22Survey no.146/1B19m wide roadplot no.22plot no.20
2222RESIDENTIAL11.10x18.25208.41NAUNDER PROGRESS11.411.418.2518.25Survey no.146/1B19m wide road3m wide pathwayplot no.21
2323RESIDENTIALOdd161.87NAUNDER PROGRESS12.512.811.5614.259m wide roadsurvey no.639m wide roadplot no.24
2424RESIDENTIALOdd222.57NAUNDER PROGRESS14.114.4314.2517.359m wide roadsurvey no.63&64plot no.23plot no.25
2525RESIDENTIALOdd222.57NAUNDER PROGRESS1212.2817.35209m wide roadsurvey no.64plot no.24plot no.26
2626RESIDENTIALOdd242.80NAUNDER PROGRESS11.4211.882022.519m wide roadsurvey no.64plot no.25plot no.27
2727RESIDENTIALOdd252.93NAUNDER PROGRESS10.8811.2222.5122.899m wide roadsurvey no.64plot no.26plot no.28
2828RESIDENTIALOdd222.57NAUNDER PROGRESS10.410.8622.8919.89m wide road9m wide roadplot no.27plot no.29
2929RESIDENTIALOdd202.34NAUNDER PROGRESS11.311.7919.816.449m wide road9m wide roadplot no.28plot no.30
3030RESIDENTIALOdd212.45NAUNDER PROGRESS13.517.6416.4411.919m wide road9m wide roadplot no.299m wide road

Project Development Schedule

Sl NoProject WorkIs Applicable ?Estimated From DateEstimated To Date
1Ground Clearance/Formation Of PlotsYes01-12-202206-04-2023
2Formation Of Road, FootpathYes01-12-202230-06-2023
3Construction Of Water Supply InfrastuctureYes01-01-202325-07-2023
4Construction Of Sewage System InfrastuctureYes01-01-202301-08-2023
5Power Supply Work(Transformer & Substation)Yes01-07-202310-12-2023
6Construction Of Storm Water DrainageYes13-02-202330-07-2023
7Solid Waste Management and DisposalYes23-01-202315-09-2023
8Tree Plantation And LandScape WorkYes15-02-202430-05-2024
9Street LightingYes02-04-202305-08-2023
10Sewage Treatment Plant (STP)Yes06-01-202313-01-2024
11Other Miscellaneous WorkYes01-02-202301-06-2024

Amenities & Utilities Availability

SlNo.WorkIs Applicable ?
1ElectricityYes
2Smart home automationNo
3CCTV surveillanceNo
4Club HouseNo
5Community HallNo
6Outdoor Sports facilityNo
7Indoor sports facilityNo
8Swimming PoolsNo
9GymNo
10ParksYes
11Power BackupNo
12Piped GasNo
13Water and SanitationYes
14Air conditioningNo

Post Registration Details

Total number of Plots30
No. of Public and Semi Pubic Sites0
Area of Public and Semi Pubic Sites(in Sq.m)0
No. of Parks and Open Spaces1
Area of Parks and Open Spaces(in Sq.m)1719
Area of Road/Transportation(in Sq.m)6810

Completion Details

Project Start Date01-12-2022
Project End Date01-06-2024
If any extension of time has been grantedNO
Cost of land94593950
Cost of construction25928750
Total cost120522700
Total amount collected From buyers0
Whether any loan has been raisedNO
Total amount spent on Project for completion of the project166346057
Total No of sites of Project30
Total No of sites sold0
Total No of sites unsold30
Whether there is any changes in inventory detailsNO

Appeals & Complaints

Complaints on PromoterNo Complaints Found.
Complaints on ProjectNo Complaints Found.

Top Properties in Mysore

Pexo Icon

Ask Pulse Ai anything about real estate

Unlock the Latest in Real Estate

News, Infographics, Blogs & More! Delivered to your inbox.

Proptech Pulse Logo

Data that drives action.
Insight that inspires action.
Technology that empowers action.“

Made with Love

Statue

© PropTech Pulse 2026, All rights reserved.

Terms of Use and Privacy Policy