PARADISE CITADEL PROJECTS PRIVATE LIMITED
KADRI B VILLAGE, MANGALORE
Approved
11th Aug 2020
Completed
30th Jun 2023
Registration No.
PRM/KA/RERA/1257/334/PR/200811/003512
Acknowledgement No.
ACK/KA/RERA/1257/334/PR/200623/004097
Project Type
Commercial
Approving Authority
Mangaluru Urban Development Authority
District
Dakshina Kannada
Taluka
Mangalore
State
Karnataka
| Project Name | MIND SPACE |
| Project Description | COMMERCIAL BUILDING |
| Project Type | Commercial |
| Project Status | New Project Launch |
| Project Start Date | 15-06-2020 |
| Proposed Project Completion Date | 30-06-2023 |
| Total Area Of Land (Sq Mtr) | 1659 |
| Total Coverd Area (Sq Mtr) | 1340 |
| Total Open Area (Sq Mtr) | 318 |
| Estimated Cost of Construction (INR) | 75000000 |
| Cost of Land (INR) | 27650000 |
| Total Project Cost (INR) | 102650000 |
| Project Address | KADRI B VILLAGE, MANGALORE |
| District | Dakshina Kannada |
| Taluk | Mangalore |
| Approving Authority | Mangaluru Urban Development Authority |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Road System | Local Authority |
| Water Supply | Self Development |
| Sewege and Drainage System | Local Authority |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Local Authority |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Local Authority |
| Bank Name | STATE BANK OF INDIA |
| Branch | GHS ROAD |
| ifscCode | SBIN0040149 |
| Account No.(70% Account) | 39395286467 |
| State | Karnataka |
| Promoter Type | Company |
| Name | AJITH KUMAR |
| PAN Number | AAKCP8666N |
| Address | ANUGRAHA, TILERY ROAD, .MULIHITHLU, MANGALORE |
| District | Dakshina Kannada |
| State/UT | Karnataka |
| PIN Code | 575004 |
| Company Registration No. | U45500KA2019TC129520 |
| Type | Director |
| Pin Code | 575001 |
| Sl No. |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 15-06-2020 | 15-07-2020 |
| 2 | Foundation footing work | Yes | 01-07-2020 | 31-12-2020 |
| 3 | Retaining wall (All types) | Yes | 01-08-2020 | 30-01-2021 |
| 4 | Plinth level Beam | Yes | 20-07-2020 | 15-01-2021 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 01-01-2023 | 30-04-2023 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | No |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | No |
| 5 | Street Lighting | No |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | No |
| 7 | Solid waste management and disposal | No |
| 8 | Water conservation | No |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | No |
| FAR Sanctioned | 2.61 |
| Number of Towers | 1 |
| 0 | 9 |
| 1 | 9 |
| 2 | 15 |
| 3 | 15 |
| 4 | 15 |
| 5 | 15 |
| Total No of Units | 78 |
| Project Start Date | 15-06-2020 |
| Project End Date | 30-06-2023 |
| If any extension of time has been granted | NO |
| Cost of land | 27650000 |
| Cost of construction | 75000000 |
| Total project cost | 102650000 |
| Total amount collected from buyers | 229002016 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 133028316 |
| Balance amount with the promoter | 26865239 |
| Total number of Flats/Apartments of the Project | 78 |
| Total number of Flats/Apartments sold | 59 |
| Total number of Flats/Apartments Unsold | 19 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 27-03-2023 |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |