Project Details
| Project Name | NFORCE LEZORIN |
| Project Description | basement car park,ground floor commercial and car park,1st floor commercial, 2nd to 4th floor residential |
| Project Type | Mixed Development |
| Project Status | Completed |
| Project Start Date | 02-10-2019 |
| Proposed Project Completion Date | 01-06-2022 |
| Total Area Of Land (Sq Mtr) | 711 |
| Total Coverd Area (Sq Mtr) | 349 |
| Total Open Area (Sq Mtr) | 362 |
| Estimated Cost of Construction (INR) | 47388847 |
| Cost of Land (INR) | 19924380 |
| Total Project Cost (INR) | 67313227 |
| Project Address | nforce lezorin, opposite nandigudda bus stand, nanndigudda road, mangalore 575002 |
| District | Dakshina Kannada |
| Taluk | Mangalore |
| Approving Authority | Local Planing Authority |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 9 |
| Area of Parking for Sale (Sq Mtr) | 115 |
| Road System | Local Authority |
| Water Supply | Local Authority |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Local Authority |
| Fire Fighting facility | Local Authority |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Local Authority |
| Bank Name | CORPORATION BANK |
| Branch | JEPPU |
| ifscCode | CORP0000732 |
| Account No.(70% Account) | 510341000695464 |
| State | Karnataka |
| Name | GUARDIAN CONSTRUCTIONS |
| Address | D.No.2-13-1148/16, Shanthala Building,New Bejai Road, |
| Pin Code | 575004 |
| Year Of Establishment | 2006 |
| Number of Project Completed | 25 |
| Reg. Of COA No. | 369-65-406/2018-23 |
| Local Authority Licence Number | 56-200-77-22-296/2018-19 (BE) |
| Number Of Project Completed | 19 |
Promoter Details
| Firm Type | Individual |
| Name | IVAN MARK SEQUEIRA |
| Father's Name | LATE VICTOR SEQUEIRA |
| PAN Number | AEL******* |
| Address | NFORCE PAULINE, OPP ROSHNI NILAYA SCHOOL, FR MULLER ROAD, KANKANADY MANGALORE |
| State/UT | Karnataka |
| PIN Code | 575002 |
| Project Name | NFORCE PAULINE |
| Project Description | 1&2,BASEMENT, GROUND,FLOOR WITH COMMERCIAL SPACE & 1-4 FLOOR WITH 12 RESIDENTIAL UNITS-2 BHK- 8 UNITS & 3BHK -4 UNITS,LOBBY,LIFT,RETUCLATED GAS CONNECTION,ONE BOREWELL,CITY CORPORATION WATER SUPPLY,SUMPTANK WITH AUTO LEVEL CONTROLLER STAND BY GENERATOR |
| Current Status | Ongoing |
| Type of Land | Mixed Development |
| Expected Completion Date | 31-08-2017 |
| District | Dakshina Kannada |
| Pin Code | 575002 |
Project Development Schedule
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 18-01-2020 | 05-02-2020 |
| 2 | Foundation footing work | Yes | 02-02-2020 | 11-02-2020 |
| 3 | Retaining wall (All types) | Yes | 15-02-2020 | 29-02-2020 |
| 4 | Plinth level Beam | Yes | 10-02-2020 | 22-02-2020 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | No |
Amenities & Utilities Availability
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | No |
| 3 | Sewage and Drainage System | No |
| 4 | Parks & Tree planting | No |
| 5 | Street Lighting | No |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | No |
| 7 | Solid waste management and disposal | No |
| 8 | Water conservation | No |
| 9 | Energy management | No |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | No |
Post Registration Details
| FAR Sanctioned | 2.63 |
| Number of Towers | 1 |
| 0 | 8 |
| 1 | 10 |
| 2 | 4 |
| 3 | 4 |
| 4 | 4 |
| Total No of Units | 30 |
Completion Details
| Project Start Date | 02-10-2019 |
| Project End Date | 01-06-2022 |
| If any extension of time has been granted | NO |
| Cost of land | 19924380 |
| Cost of construction | 47388847 |
| Total project cost | 67313227 |
| Total amount collected from buyers | 47978614 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 47429293 |
| Balance amount with the promoter | 549321 |
| Total number of Flats/Apartments of the Project | 30 |
| Total number of Flats/Apartments sold | 15 |
| Total number of Flats/Apartments Unsold | 15 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 06-04-2022 |
Appeals & Complaints
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in
Top Properties in Mysore


Ask Pulse Ai anything about real estate