PRESTIGE ESTATES CONSTRUCTIONS LIMITED
SY NO 31-3, 31-4,31-5A, 31-1C2, 31-1D2, 31-1E2-, 31-1F2, 31-1G2, 31-1H1, 31-1H2, 31-1/1,31-1/3,32-1, KHADRI VILLAGESY NO 39-1,39-3, 39/3,39/8B,39-10,41-1A1, KODIALBAIL VILLAGE BEJAI MUSEUM ROAD, MANGALORE
Approved
21st Oct 2017
Completed
30th Jul 2023
Registration No.
PRM/KA/RERA/1257/334/PR/171021/000437
Acknowledgement No.
PR/KN/170730/000437
Project Type
Residential/Group Housing
Approving Authority
Mangaluru Urban Development Authority
District
Dakshina Kannada
Taluka
Mangalore
State
Karnataka
| Project Name | PRESTIGE VALLEY CREST PHASE 2 |
| Project Description | RESIDENTIAL APARTMENT. THE DEVELOPMENT IS BEEN TAKEN UP INTO 2 PHASE . THE TOTAL LAND EXTENT AND THE COVERAGE IS CONSIDERED IN THIS APPLICATION IS ON THE BASE OF THE ENTIRE DEVELOPMENT |
| Project Type | Residential/Group Housing |
| Project Status | Ongoing |
| Project Start Date | 10-06-2018 |
| Proposed Project Completion Date | 30-07-2023 |
| Total Area Of Land (Sq Mtr) | 19357 |
| Total Coverd Area (Sq Mtr) | 5944 |
| Total Open Area (Sq Mtr) | 13413 |
| Estimated Cost of Construction (INR) | 956935750 |
| Cost of Land (INR) | 295190350 |
| Total Project Cost (INR) | 1252126100 |
| Project Address | SY NO 31-3, 31-4,31-5A, 31-1C2, 31-1D2, 31-1E2-, 31-1F2, 31-1G2, 31-1H1, 31-1H2, 31-1/1,31-1/3,32-1, KHADRI VILLAGESY NO 39-1,39-3, 39/3,39/8B,39-10,41-1A1, KODIALBAIL VILLAGE BEJAI MUSEUM ROAD, MANGALORE |
| District | Bengaluru Urban |
| Taluk | Mangalore |
| Approving Authority | Mangaluru Urban Development Authority |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Extent of development carried till date | 5 % |
| Extent of development pending | 95 % |
| Total amount of money collected from allottee | 11414215 |
| Total amount of money used for development of project | 44100291 |
| Total amount of balance maney lying with promoter | 0 |
| Is Any Subsequent Modification in Plan | No |
| Is Delay in the Project | No |
| No of Month Delay | 0 |
| Type of Inventory | APARTMENTQ |
| No of Inventory | 250 |
| Carpet Area (Sq Mtr) | 20561SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 1014SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 32SqMtr |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Self Development |
| Solid Waste Management And Disposal | Self Development |
| Bank Name | KOTAK MAHINDRA BANK |
| Branch | LAVELLE ROAD, BANGALORE |
| ifscCode | KKBK0000422 |
| Account No.(70% Account) | 2611833251 |
| State | Karnataka |
| Name | K2K INFRASTRUCTURE INDIA |
| Address | 83, 4th Floor, Prestige Copper Arch, Infantry Road,BANGALORE |
| Pin Code | 560001 |
| Year Of Establishment | 2007 |
| Number of Project Completed | 50 |
| Reg. Of COA No. | CA/2010/47015 |
| Local Authority Licence Number | BCC/BL-3.6/SE:150:2013-14 |
| Number Of Project Completed | 29 |
| Promoter Type | Company |
| Name | KEZYA DE BRAGANZA |
| PAN Number | AABCP8096K |
| Address | NO 86, ATTAVAR,VILLAGE, NO 18, MILAGRES WARD , MANGALORE |
| District | Dakshina Kannada |
| State/UT | Karnataka |
| PIN Code | 560001 |
| Company Registration No. | U07010KA1997PLC022322 |
| Type | Others |
| Pin Code | 575001 |
| Project Name | PRESTIGE WESTHOLMES |
| Project Description | RESIDENTIAL APARTMENTS |
| Current Status | Completed |
| Type of Land | Residential |
| Type of Inventory | APARTMENTQ |
| No of Inventory | 250 |
| Carpet Area (Sq Mtr) | 20561 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 1014 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 32 Sq Mtr |
| Extension Applied On | 28-04-2022 |
| Extension Approved On | 12-09-2022 |
| Extension Registration Number | EX/PRM/KA/RERA/1257/334/PR/220912/000437 |
| Proposed Project End Date at the time of registration | 30-07-2022 |
| Project End Date provided under Section 6 | 30-07-2023 |
| whether 2/3rd concern from the allottees has taken? | NO |
| Whether any compensation is provided for the Buyer? | NO |
| Document Name | Delay Analysis |
| 1 | others |
| Document Name_1 | |
| Document Name_2 |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 21-01-2016 | 30-04-2019 |
| 2 | Foundation footing work | Yes | 10-10-2016 | 03-03-2018 |
| 3 | Retaining wall (All types) | Yes | 25-06-2016 | 30-03-2019 |
| 4 | Plinth level Beam | Yes | 03-11-2018 | 30-04-2019 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 15-12-2016 | 15-06-2019 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | No |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | No |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | Yes |
| 11 | Education/Health/Other public amenities | No |
| WebSite Link 1 | https://www.prestigeconstructions.com/ |
| Agent Registration No 1 | PRM/KA/RERA/1251/310/AG/170927/000164 |
| FAR Sanctioned | 28446.8 |
| Number of Towers | 1 |
| 0 | 0 |
| 1 | 0 |
| 2 | 0 |
| 3 | 0 |
| 4 | 0 |
| 5 | 10 |
| 6 | 10 |
| 7 | 10 |
| 8 | 10 |
| 9 | 10 |
| 10 | 10 |
| 11 | 10 |
| 12 | 10 |
| 13 | 10 |
| 14 | 10 |
| 15 | 10 |
| 16 | 10 |
| 17 | 10 |
| 18 | 10 |
| 19 | 10 |
| 20 | 10 |
| 21 | 10 |
| 22 | 10 |
| 23 | 10 |
| 24 | 10 |
| 25 | 10 |
| 26 | 10 |
| 27 | 10 |
| 28 | 10 |
| 29 | 10 |
| Total No of Units | 250 |
| Project Start Date | 10-06-2018 |
| Project End Date | 30-07-2023 |
| If any extension of time has been granted | YES |
| Extended From Date | 30-07-2022 |
| Extended End Date | 30-07-2023 |
| Cost of land | 295190350 |
| Cost of construction | 956935750 |
| Total project cost | 1252126100 |
| Total amount collected from buyers | 348078365 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 348078365 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 250 |
| Total number of Flats/Apartments sold | 83 |
| Total number of Flats/Apartments Unsold | 167 |
| Whether the project has been completed within the stipulated Period? | NO |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | NO |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 10-02-2023 |
| Appeals / FNH | NO APPEALS / FNH |