SORAKE ESTATES
Anegundi , Bejai new road
Approved
20th Jan 2018
Completed
30th Jun 2019
Registration No.
PRM/KA/RERA/1257/334/PR/180120/002258
Acknowledgement No.
PR/KN/171025/002258
Project Type
Mixed Development
Approving Authority
Mangaluru Urban Development Authority
District
Dakshina Kannada
Taluka
Mangalore
State
Karnataka
| Project Name | SORAKE IRIS |
| Project Description | Residential cum commercial project with 14 flats. |
| Project Type | Mixed Development |
| Project Status | Completed |
| Project Start Date | 08-06-2016 |
| Proposed Project Completion Date | 30-06-2019 |
| Total Area Of Land (Sq Mtr) | 647 |
| Total Coverd Area (Sq Mtr) | 276 |
| Total Open Area (Sq Mtr) | 371 |
| Estimated Cost of Construction (INR) | 37000000 |
| Cost of Land (INR) | 12800000 |
| Total Project Cost (INR) | 49800000 |
| Project Address | Anegundi , Bejai new road |
| District | Dakshina Kannada |
| Taluk | Mangalore |
| Approving Authority | Mangaluru Urban Development Authority |
| No of Garage for Sale | 16 |
| Area of Garage for Sale (Sq Mtr) | 333 |
| No of Parking for Sale | 2 |
| Area of Parking for Sale (Sq Mtr) | 25 |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Self Development |
| Solid Waste Management And Disposal | Local Authority |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Self Development |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Self Development |
| Bank Name | Standard Chartered Bank |
| Branch | Bharath co op Bank Hampankatta |
| ifscCode | BCBM0000026 |
| Account No.(70% Account) | 002512100007024 |
| State | Karnataka |
| Promoter Type | Partnership Firm |
| Name | Dr Rajneesh Sorake |
| PAN Number | ABYFS0549K |
| Address | Shivbagh , Kadri Mangaluru |
| District | Dakshina Kannada |
| State/UT | Karnataka |
| PIN Code | 575005 |
| Company Registration No. | Not applicable |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 15-06-2016 | 15-07-2016 |
| 2 | Foundation footing work | Yes | 15-07-2016 | 15-08-2016 |
| 3 | Retaining wall (All types) | No | ||
| 4 | Plinth level Beam | Yes | 15-08-2016 | 15-09-2016 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 15-09-2016 | 15-10-2016 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | No |
| 2 | Internal Roads & Footpaths | No |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | No |
| 5 | Street Lighting | No |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | No |
| 7 | Solid waste management and disposal | No |
| 8 | Water conservation | No |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities |
| WebSite Link 1 | www.sorakebuilders.com |
| Agent Registration No 1 | nil |
| FAR Sanctioned | 1.0 |
| Number of Towers | 1 |
| 0 | 2 |
| 1 | 3 |
| 2 | 3 |
| 3 | 3 |
| 4 | 3 |
| Total No of Units | 14 |
| Project Start Date | 08-06-2016 |
| Project End Date | 30-06-2019 |
| If any extension of time has been granted | NO |
| Cost of land | 12800000 |
| Cost of construction | 37000000 |
| Total project cost | 49800000 |
| Total amount collected from buyers | 41521529 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 36800212 |
| Balance amount with the promoter | 4221317 |
| Total number of Flats/Apartments of the Project | 14 |
| Total number of Flats/Apartments sold | 14 |
| Total number of Flats/Apartments Unsold | 0 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 16-08-2019 |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |