Devidayal Shetty
SY NO.233/1A2A14, , Padavu Village , Mangalore taluk
Approved
4th Aug 2021
Completed
30th Jun 2023
Registration No.
PRM/KA/RERA/1257/334/PR/210804/004236
Acknowledgement No.
ACK/KA/RERA/1257/334/PR/210502/004964
Project Type
Mixed Development
Approving Authority
Mangaluru Urban Development Authority
District
Dakshina Kannada
Taluka
Mangalore
State
Karnataka
| Project Name | Sri Devidayal La Grace |
| Project Description | Project consists of 17 apartments and 3 commercial shops. it has one basement, ground floor and four upper floors. |
| Project Type | Mixed Development |
| Project Status | New Project Launch |
| Project Start Date | 02-06-2021 |
| Proposed Project Completion Date | 30-06-2023 |
| Total Area Of Land (Sq Mtr) | 607 |
| Total Coverd Area (Sq Mtr) | 289 |
| Total Open Area (Sq Mtr) | 318 |
| Estimated Cost of Construction (INR) | 37230000 |
| Cost of Land (INR) | 18000000 |
| Total Project Cost (INR) | 55230000 |
| Project Address | SY NO.233/1A2A14, , Padavu Village , Mangalore taluk |
| District | Dakshina Kannada |
| Taluk | Mangalore |
| Approving Authority | Mangaluru Urban Development Authority |
| No of Garage for Sale | 19 |
| Area of Garage for Sale (Sq Mtr) | 238 |
| No of Parking for Sale | 4 |
| Area of Parking for Sale (Sq Mtr) | 50 |
| Road System | Local Authority |
| Water Supply | Local Authority |
| Sewege and Drainage System | Local Authority |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Self Development |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Self Development |
| Bank Name | Karnataka Bank Ltd. |
| Branch | Urva Market |
| ifscCode | KARB0000487 |
| Account No.(70% Account) | 4872000100041501 |
| State | Karnataka |
| Name | K Anil Hegde |
| Address | 303, Sterling Chambers, Kalakunj road,Kodialbail Mangalore |
| Pin Code | 575003 |
| Year Of Establishment | 1998 |
| Number of Project Completed | 500 |
| Reg. Of COA No. | 286/116/330/2018-23 |
| Local Authority Licence Number | MNG/BL/10124/20-21 |
| Promoter Type | Proprietorship Firm |
| Name | Devidayal Shetty |
| PAN Number | BPPPS6832D |
| Address | Sri Devidayal " ARA ", Bandottu road, 1st Cross, Maryhill Mangalore |
| District | Dakshina Kannada |
| State/UT | Karnataka |
| PIN Code | 575006 |
| Company Registration No. | 29BPPPS6832D1ZC |
| Project Name | Sri Devidayal ARA |
| Project Description | This project consists of 6 apartments and 2 commercial shops. The Building consists of one Basement, ground and three upper floors. |
| Current Status | Completed |
| Type of Land | Residential |
| Expected Completion Date | 30-04-2023 |
| Pin Code | 575008 |
| Sl No. |
| Extension Applied On | 23-04-2023 |
| Extension Approved On | 02-08-2023 |
| Extension Registration Number | EX/PRM/KA/RERA/1257/334/PR/230802/004236 |
| Proposed Project End Date at the time of registration | 30-04-2023 |
| Project End Date provided under Section 6 | 30-06-2023 |
| whether 2/3rd concern from the allottees has taken? | NO |
| Whether any compensation is provided for the Buyer? | NO |
| Document Name | Ec last one month upto 16/04/23 |
| 1 | others |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 09-08-2021 | 29-11-2021 |
| 2 | Foundation footing work | Yes | 30-09-2021 | 28-12-2021 |
| 3 | Retaining wall (All types) | Yes | 03-11-2021 | 30-12-2021 |
| 4 | Plinth level Beam | Yes | 26-10-2021 | 24-12-2021 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | No | ||
| 6 | Basement Floor for car park | Yes | 29-12-2021 | 29-01-2022 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | No |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | No |
| 5 | Street Lighting | No |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | No |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | Yes |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | Yes |
| Agent Registration No 1 | NA |
| FAR Sanctioned | 2.1 |
| Number of Towers | 1 |
| 0 | 4 |
| 1 | 4 |
| 2 | 4 |
| 3 | 4 |
| 4 | 4 |
| Total No of Units | 20 |
| Project Start Date | 02-06-2021 |
| Project End Date | 30-06-2023 |
| If any extension of time has been granted | YES |
| Extended From Date | 30-04-2023 |
| Extended End Date | 30-06-2023 |
| Cost of land | 18000000 |
| Cost of construction | 37230000 |
| Total project cost | 55230000 |
| Total amount collected from buyers | 40456251 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 37503754 |
| Balance amount with the promoter | 2952497 |
| Total number of Flats/Apartments of the Project | 20 |
| Total number of Flats/Apartments sold | 11 |
| Total number of Flats/Apartments Unsold | 9 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 07-06-2023 |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |