CITADEL DEVELOPERS
PADAVINANAGADY, AIRPORT ROAD, MANGALORE
Approved
26th Mar 2019
Completed
30th Jul 2024
Registration No.
PRM/KA/RERA/1257/334/PR/190326/002493
Acknowledgement No.
ACK/KA/RERA/1257/334/PR/181128/002856
Project Type
Mixed Development
Approving Authority
Local Planing Authority
District
Dakshina Kannada
Taluka
Mangalore
State
Karnataka
| Project Name | SUKRITHI |
| Project Description | SUKRITHI CONSISTS OF THREE BASEMENTS, GROUND + 11 UPPER FLOORS IN THE RESIDENTIAL UNIT AND BASEMENT, GROUND + 3 UPPER FLOORS IN THE COMMERCIAL UNIT |
| Project Type | Mixed Development |
| Project Status | New Project Launch |
| Project Start Date | 15-01-2019 |
| Proposed Project Completion Date | 30-07-2024 |
| Total Area Of Land (Sq Mtr) | 4978 |
| Total Coverd Area (Sq Mtr) | 1581 |
| Total Open Area (Sq Mtr) | 3397 |
| Estimated Cost of Construction (INR) | 400000000 |
| Cost of Land (INR) | 120000000 |
| Total Project Cost (INR) | 520000000 |
| Project Address | PADAVINANAGADY, AIRPORT ROAD, MANGALORE |
| District | Dakshina Kannada |
| Taluk | Mangalore |
| Approving Authority | Local Planing Authority |
| No of Garage for Sale | 130 |
| Area of Garage for Sale (Sq Mtr) | 1625 |
| No of Parking for Sale | 7 |
| Area of Parking for Sale (Sq Mtr) | 87 |
| Type of Inventory | COMMERCIAL |
| No of Inventory | 19 |
| Carpet Area (Sq Mtr) | 1365SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0SqMtr |
| Road System | Local Authority |
| Water Supply | Local Authority |
| Sewege and Drainage System | Local Authority |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Local Authority |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Local Authority |
| Bank Name | STATE BANK OF INDIA |
| Branch | GHS ROAD MANGALORE |
| ifscCode | SBIN0040149 |
| Account No.(70% Account) | 39192306393 |
| State | Karnataka |
| Promoter Type | Partnership Firm |
| Name | SANDEEP |
| PAN Number | AADFC7473N |
| Address | NEHRU AVENUE CROSS ROAD, LALBAGH, MANGALORE |
| District | Dakshina Kannada |
| State/UT | Karnataka |
| PIN Code | 575004 |
| Company Registration No. | 287 96 97 |
| Project Name | MAGNUM |
| Project Description | MAGNUM consists of one basement, ground + 11 upper floors with total 11 units, Magnum comprises of 4BHK apartments |
| Current Status | Ongoing |
| Type of Land | Residential |
| Expected Completion Date | 31-03-2019 |
| Pin Code | 575003 |
| Type of Inventory | COMMERCIAL |
| No of Inventory | 19 |
| Carpet Area (Sq Mtr) | 1365 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 01-04-2019 | 30-09-2019 |
| 2 | Foundation footing work | Yes | 01-05-2019 | 30-10-2019 |
| 3 | Retaining wall (All types) | Yes | 30-06-2019 | 30-10-2019 |
| 4 | Plinth level Beam | Yes | 31-05-2019 | 29-11-2019 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 01-01-2023 | 31-05-2023 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | No |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | No |
| 5 | Street Lighting | No |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | No |
| 7 | Solid waste management and disposal | No |
| 8 | Water conservation | Yes |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | Yes |
| WebSite Link 1 | www.citadeldevelopers.com |
| Agent Registration No 1 | N.A |
| FAR Sanctioned | 2.677 |
| Number of Towers | 2 |
| 0 | 4 |
| 1 | 6 |
| 2 | 7 |
| 3 | 1 |
| 4 | 1 |
| 5 | 9 |
| 6 | 9 |
| 7 | 9 |
| 8 | 9 |
| 9 | 9 |
| 10 | 9 |
| 11 | 9 |
| Total No of Units | 121 |
| Project Start Date | 15-01-2019 |
| Project End Date | 30-07-2024 |
| If any extension of time has been granted | NO |
| Cost of land | 120000000 |
| Cost of construction | 400000000 |
| Total project cost | 520000000 |
| Total amount collected from buyers | 481827580 |
| Whether any loan has been raised | YES |
| Total amount spent for completion of the project | 499816317 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 121 |
| Total number of Flats/Apartments sold | 70 |
| Total number of Flats/Apartments Unsold | 51 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 20-07-2024 |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |