SULTHAN BUILDERS
PATLA,R.S.NO.28/2(P),PERMANNUR VILLAGE, ULLALA MUNCIPALITY,MANGALORE
Approved
31st May 2019
Completed
31st May 2021
Registration No.
PRM/KA/RERA/1257/333/PR/190531/002586
Acknowledgement No.
ACK/KA/RERA/1257/333/PR/180619/002358
Project Type
Residential/Group Housing
Approving Authority
Mangaluru Urban Development Authority
District
Dakshina Kannada
Taluka
Dakshina Kannada
State
Karnataka
| Project Name | sulthan view 2 |
| Project Description | Residential, no of flats 45, 2 bhk and 3bhk |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| Project Start Date | 03-05-2018 |
| Proposed Project Completion Date | 31-05-2021 |
| Total Area Of Land (Sq Mtr) | 1376 |
| Total Coverd Area (Sq Mtr) | 608 |
| Total Open Area (Sq Mtr) | 768 |
| Estimated Cost of Construction (INR) | 48478000 |
| Cost of Land (INR) | 3571825 |
| Total Project Cost (INR) | 52049825 |
| Project Address | PATLA,R.S.NO.28/2(P),PERMANNUR VILLAGE, ULLALA MUNCIPALITY,MANGALORE |
| District | Dakshina Kannada |
| Taluk | Dakshina Kannada |
| Approving Authority | Mangaluru Urban Development Authority |
| No of Garage for Sale | 45 |
| Area of Garage for Sale (Sq Mtr) | 523 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Road System | Local Authority |
| Water Supply | Local Authority |
| Sewege and Drainage System | Local Authority |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Local Authority |
| Fire Fighting facility | Local Authority |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Local Authority |
| Bank Name | VIJAYA BANK |
| Branch | kankanady |
| ifscCode | VIJB0001420 |
| Account No.(70% Account) | 142000301000199 |
| State | Karnataka |
| Name | EKANATH SIGMA |
| Address | Ist floor, Dandakeri Babu Maistry complex, Bikarnakatte,Mangalore,manglore |
| Pin Code | 575003 |
| Year Of Establishment | 2000 |
| Number of Project Completed | 50 |
| Reg. Of COA No. | LBB-ULL-BC-25-2017-19 |
| Local Authority Licence Number | LBD NO-355-418/2013-18 |
| Promoter Type | Partnership Firm |
| Name | MOHAMMED U.B |
| PAN Number | ACRFS1626B |
| Address | KANKANADY MANGALORE , 2 ND FLOOR MANGALORE GATE BUILDING |
| District | Dakshina Kannada |
| State/UT | Karnataka |
| PIN Code | 575002 |
| Company Registration No. | NOT APPLICABLE |
| Extension Applied On | 02-12-2020 |
| Extension Approved On | 21-04-2022 |
| Extension Registration Number | EX/PRM/KA/RERA/1257/333/PR/220421/002586 |
| Proposed Project End Date at the time of registration | 30-11-2020 |
| Project End Date provided under Section 6 | 31-05-2021 |
| whether 2/3rd concern from the allottees has taken? | YES |
| Whether any compensation is provided for the Buyer? | NO |
| Document Name | FORM B |
| 1 | Shortage of Building Materials, Concrete, Jalli etc |
| Document Name_1 | |
| Document Name_2 | |
| Document Name_3 | |
| Document Name_4 |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 08-05-2018 | 08-06-2018 |
| 2 | Foundation footing work | Yes | 11-06-2018 | 10-07-2018 |
| 3 | Retaining wall (All types) | Yes | 15-07-2018 | 01-11-2018 |
| 4 | Plinth level Beam | Yes | 11-06-2018 | 19-07-2018 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 08-09-2018 | 23-11-2018 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | No |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | No |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | No |
| 7 | Solid waste management and disposal | No |
| 8 | Water conservation | Yes |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | Yes |
| WebSite Link 1 | www.rera.com |
| Agent Registration No 1 | NIL |
| FAR Sanctioned | 2.5 |
| Number of Towers | 1 |
| 0 | 9 |
| 1 | 9 |
| 2 | 9 |
| 3 | 9 |
| 4 | 9 |
| Total No of Units | 45 |
| Project Start Date | 03-05-2018 |
| Project End Date | 31-05-2021 |
| If any extension of time has been granted | YES |
| Extended From Date | 30-11-2020 |
| Extended End Date | 31-05-2021 |
| Cost of land | 3571825 |
| Cost of construction | 48478000 |
| Total project cost | 52049825 |
| Total amount collected from buyers | 28922856 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 52049825 |
| Balance amount with the promoter | 34847344 |
| Total number of Flats/Apartments of the Project | 45 |
| Total number of Flats/Apartments sold | 24 |
| Total number of Flats/Apartments Unsold | 21 |
| Whether the project has been completed within the stipulated Period? | NO |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 18-06-2021 |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |