Westline Signature

Westline Builders Pvt Ltd

NH66, Nanthoor, Opp Sandesha Music Academy

Approved

21st Oct 2017

Pending

30th Sept 2027

Registration No.

PRM/KA/RERA/1257/334/PR/171021/000845

Acknowledgement No.

PR/KN/170801/000845

Project Type

Residential/Group Housing

Approving Authority

Mangaluru Urban Development Authority

District

Dakshina Kannada

Taluka

Mangalore

State

Karnataka

Project Details

Project NameWestline Signature
Project DescriptionOngoing Residential Project
Project TypeResidential/Group Housing
Project StatusOngoing
Project Start Date12-04-2017
Proposed Project Completion Date30-09-2025
Further Extension Date30-09-2027
Total Area Of Land (Sq Mtr)4250
Total Coverd Area (Sq Mtr)572
Total Open Area (Sq Mtr)3678
Estimated Cost of Construction (INR)530000000
Cost of Land (INR)84000000
Total Project Cost (INR)614000000
Project AddressNH66, Nanthoor, Opp Sandesha Music Academy
DistrictBengaluru Urban
TalukMangalore
Approving AuthorityMangaluru Urban Development Authority
No of Garage for Sale0
Area of Garage for Sale (Sq Mtr)0
No of Parking for Sale9
Area of Parking for Sale (Sq Mtr)120
Extent of development carried till date26 %
Extent of development pending26 %
Total amount of money collected from allottee97478555
Total amount of money used for development of project97286785
Total amount of balance maney lying with promoter191770
Is Any Subsequent Modification in PlanYes
Is Delay in the ProjectNo
No of Month Delay0
Type of Inventory3 BHK
No of Inventory29
Carpet Area (Sq Mtr)3261SqMtr
Area of exclusive balcony/verandah (Sq Mtr)934SqMtr
Area of exclusive open terrace if any (Sq Mtr)0SqMtr
Road SystemLocal Authority
Water SupplyLocal Authority
Sewege and Drainage SystemLocal Authority
Electricity Supply Transformer And Sub StationLocal Authority
Solid Waste Management And DisposalLocal Authority
Bank NameSTATE BANK OF INDIA
BranchCOMMERCIAL BRANCH MANGALORE
ifscCodeSBIN0004118
Account No.(70% Account)40144325620
StateKarnataka
NameMfar Constructions Pvt Ltd
AddressN0 8 & 8A, AVS Compound, 80 Feet Road,Koramangala
Pin Code560034
Year Of Establishment1996
Number of Project Completed10
Reg. Of COA No.CA/99/25434
Local Authority Licence NumberSTR/S/193
Number Of Project Completed109

Promoter Details

Promoter TypeCompany
NameYasir Rahman
PAN NumberAABCW5349J
AddressBehind Ahsanul Masjid, Bikkarnakatte Mangalore
DistrictDakshina Kannada
State/UTKarnataka
PIN Code575002
Company Registration No.U45205KA2014PTC075160
TypeDirector
Pin Code575008
Project NameWestline Skydale
Project DescriptionResidential Project, 35 Flats, Near Ahsanul Masjid, Bikkarnakatte
Current StatusOngoing
Type of LandResidential
Expected Completion Date01-08-2017

Modification Plan Details

Modification Applied On27-09-2025
Modification Approved On26-03-2026
Type of Inventory3 BHK
No of Inventory29
Carpet Area (Sq Mtr)3261 Sq Mtr
Area of exclusive balcony/verandah (Sq Mtr)934 Sq Mtr
Area of exclusive open terrace if any (Sq Mtr)0 Sq Mtr
Details of Modification of plan sanction / layout brief descriptionShortage of labour and lack of sand problems also include the additional floors and changes in the inventroy details and built up area, it has become necessary to modify the plan
Modified plan applied date03/07/2024
Modified plan approved date30/12/2024
Extend of the work carried out till date of registered project ( % )67.0
Extend of the work pending of registered project ( % )33.0
Total amount collected in respect of registered project ( INR )593379822
Total amount spent for the project ( INR )1043109341
Total balance amount lying with the promoter ( INR )0
NOCSEIAA
SlNo.

Extension Details

Extension Applied On19-08-2024
Extension Approved On09-10-2024
Extension Registration NumberEX/PRM/KA/RERA/1257/334/PR/241009/000845
Proposed Project End Date at the time of registration30-09-2024
Project End Date provided under Section 630-09-2025
whether 2/3rd concern from the allottees has taken?NO
Whether any compensation is provided for the Buyer?NO
Document Nameproject photo
1Shortage of Labour

Project Development Schedule

Sl NoProject WorkIs Applicable ?Estimated From DateEstimated To Date
1Earth work and other leveling preparation workYes27-03-201715-04-2026
2Foundation footing workYes15-04-201712-06-2026
3Retaining wall (All types)Yes05-10-202006-12-2026
4Plinth level BeamNo
5Sub-structure flooring (Parking Floor, more than one floor below general ground level)Yes13-06-201704-03-2026

Amenities & Utilities Availability

SlNo.WorkIs Applicable ?
1Water SupplyYes
2Internal Roads & FootpathsNo
3Sewage and Drainage SystemYes
4Parks & Tree plantingNo
5Street LightingYes
6Provision for community buildings and for treatment and disposal of sewage and sullage waterYes
7Solid waste management and disposalYes
8Water conservationNo
9Energy managementYes
10Fire protection and fire safety requirementsNo
11Education/Health/Other public amenitiesYes

Post Registration Details

WebSite Link 1www.westlinebuilders.com
Agent Registration No 1None
FAR Sanctioned27863.4
Number of Towers1
01
13
24
33
44
53
64
73
84
93
104
113
124
133
144
153
164
173
184
193
204
213
224
233
244
253
264
273
284
293
304
310
324
330
344
350
364
370
384
390
404
410
424
430
444
450
461
471
481
490
500
Total No of Units137

Appeals & Complaints

Appeals / FNHNO APPEALS / FNH
Complaints on PromoterNo Complaints Found.
Complaints on ProjectNo Complaints Found.

Top Properties in Bangalore

Pexo Icon

Ask Pulse Ai anything about real estate

Unlock the Latest in Real Estate

News, Infographics, Blogs & More! Delivered to your inbox.

Proptech Pulse Logo

Data that drives action.
Insight that inspires action.
Technology that empowers action.“

Made with Love

Statue

© PropTech Pulse 2026, All rights reserved.

Terms of Use and Privacy Policy