Registration No.
PRM/KA/RERA/1257/334/PR/180222/002275
Acknowledgement No.
PR/KN/171026/002275
Project Type
Mixed Development
District
Dakshina Kannada
Taluka
Mangalore
State
Karnataka
| Project Name | Zulfas Masterpiece B Block |
| Project Description | B+G+4 mixed occupancy |
| Project Type | Mixed Development |
| Project Status | Completed |
| Project Start Date | 03-10-2017 |
| Proposed Project Completion Date | 31-01-2020 |
| Total Area Of Land (Sq Mtr) | 811 |
| Total Coverd Area (Sq Mtr) | 475 |
| Total Open Area (Sq Mtr) | 336 |
| Estimated Cost of Construction (INR) | 50000000 |
| Cost of Land (INR) | 17000000 |
| Total Project Cost (INR) | 67000000 |
| Project Address | Monkey Stand Road, Marnamikatta |
| District | Dakshina Kannada |
| Taluk | Mangalore |
| No of Garage for Sale | 25 |
| Area of Garage for Sale (Sq Mtr) | 701 |
| No of Parking for Sale | 5 |
| Area of Parking for Sale (Sq Mtr) | 62 |
| Road System | Local Authority |
| Water Supply | Local Authority |
| Sewege and Drainage System | Local Authority |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Local Authority |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Local Authority |
| Bank Name | STATE BANK OF INDIA |
| Branch | SME Branch |
| ifscCode | SBIN0004118 |
| Account No.(70% Account) | 37348065696 |
| State | Karnataka |
| Name | K. ANIL HEGDE |
| Address | #304, STERLING CHAMBERS,KODIALBAIL, MANGALURU |
| Pin Code | 575003 |
| Year Of Establishment | 1998 |
| Number of Project Completed | 500 |
| Reg. Of COA No. | 328-238-211-113/2013-18 |
| Local Authority Licence Number | 2012-COM31858 |
| Firm Type | Individual |
| Name | Muhammad Abid Misbah |
| Father's Name | Mohammed Husain Misbah |
| PAN Number | AOHPM3134J |
| Address | Near Modern Bed House, Marnamikatta, Mangalore |
| State/UT | Karnataka |
| PIN Code | 575001 |
| Project Name | Zulfas Masterpiece A Block |
| Project Description | B+G+9 mixed occupancy |
| Current Status | Completed |
| Type of Land | Mixed Development |
| District | Dakshina Kannada |
| Pin Code | 575001 |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 15-09-2017 | 31-10-2017 |
| 2 | Foundation footing work | Yes | 01-11-2017 | 31-01-2018 |
| 3 | Retaining wall (All types) | Yes | 01-01-2018 | 31-03-2018 |
| 4 | Plinth level Beam | Yes | 02-02-2018 | 14-04-2018 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | No |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | No |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | No |
| 5 | Street Lighting | No |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | No |
| 7 | Solid waste management and disposal | No |
| 8 | Water conservation | Yes |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities |
| WebSite Link 1 | www.zulfas.com |
| FAR Sanctioned | 3.02 |
| Number of Towers | 1 |
| 0 | 0 |
| 1 | 6 |
| 2 | 6 |
| 3 | 6 |
| 4 | 6 |
| Total No of Units | 24 |
| Project Start Date | 03-10-2017 |
| Project End Date | 31-01-2020 |
| If any extension of time has been granted | NO |
| Cost of land | 17000000 |
| Cost of construction | 50000000 |
| Total project cost | 67000000 |
| Total amount collected from buyers | 31055435 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 61272332 |
| Balance amount with the promoter | 8609713 |
| Total number of Flats/Apartments of the Project | 24 |
| Total number of Flats/Apartments sold | 14 |
| Total number of Flats/Apartments Unsold | 10 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 08-11-2019 |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |