SOLITAIRE INFRA
LAKHAMANAHALLI , BRTC ROAD
Approved
21st May 2018
Completed
30th Mar 2022
Registration No.
PRM/KA/RERA/1259/410/PR/180521/001780
Acknowledgement No.
ACK/KA/RERA/1259/410/PR/180410/002155
Project Type
Commercial
Approving Authority
Hubballi Dharwad Municipal Corporation
District
Dharwad
Taluka
Dharwad
State
Karnataka
| Project Name | DHARWAD BUSINESS CENTRE |
| Project Description | COMMERCIAL COMPLEX |
| Project Type | Commercial |
| Project Status | Completed |
| Project Start Date | 07-04-2018 |
| Proposed Project Completion Date | 30-03-2022 |
| Total Area Of Land (Sq Mtr) | 3680 |
| Total Coverd Area (Sq Mtr) | 10328 |
| Total Open Area (Sq Mtr) | 3124 |
| Estimated Cost of Construction (INR) | 169540000 |
| Cost of Land (INR) | 2700000 |
| Total Project Cost (INR) | 172240000 |
| Project Address | LAKHAMANAHALLI , BRTC ROAD |
| District | Sangli |
| Taluk | Dharwad |
| Approving Authority | Hubballi Dharwad Municipal Corporation |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Self Development |
| Solid Waste Management And Disposal | Self Development |
| Fire Fighting facility | Self Development |
| Drinking Water Facility | Self Development |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Self Development |
| Power Supply by Hescom | Self Development |
| Bank Name | INDIAN OVERSEAS BANK |
| Branch | spatapur Brnach dharwad |
| ifscCode | IOBA0001053 |
| Account No.(70% Account) | 105302000004444 |
| State | Maharashtra |
| Name | Dr. A.B Kulkarni & Associates |
| Address | MIRAJ,abkassociates@gmail.com |
| Pin Code | 416410 |
| Year Of Establishment | 2007 |
| Number of Project Completed | 300 |
| Reg. Of COA No. | CA/75/00601 |
| Local Authority Licence Number | E/356/2018 |
| Promoter Type | Partnership Firm |
| Name | VISHNU R MEHARWADE |
| PAN Number | ADEFS0538C |
| Address | F 3 Sri Niketan , Dollors Colony Gokul Road Hubli |
| District | Dharwad |
| State/UT | Karnataka |
| PIN Code | 580004 |
| Company Registration No. | 29ADEFS0538C1Z9 |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 03-05-2018 | 31-01-2019 |
| 2 | Foundation footing work | Yes | 15-12-2018 | 31-01-2019 |
| 3 | Retaining wall (All types) | Yes | 20-10-2018 | 31-01-2019 |
| 4 | Plinth level Beam | Yes | 15-01-2019 | 28-02-2019 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 15-01-2019 | 28-02-2019 |
| 6 | Providing and Shotcreting the soil surface with 50mm thick 1:2:2 mix after fixing the weld mesh of size 75 * 75 * 4.2mm to excavated earth with U hooks of size 200 x 200 mm up to required depth in all kinds | Yes | 01-08-2018 | 31-01-2019 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | No |
| 3 | Sewage and Drainage System | No |
| 4 | Parks & Tree planting | No |
| 5 | Street Lighting | No |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | No |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | No |
| WebSite Link 1 | www.solitaireinfra.com |
| FAR Sanctioned | 2.38 |
| Number of Towers | 2 |
| 0 | 0 |
| 1 | 6 |
| 2 | 7 |
| 3 | 7 |
| 4 | 6 |
| 5 | 6 |
| 6 | 21 |
| Total No of Units | 230 |
| Project Start Date | 07-04-2018 |
| Project End Date | 30-03-2022 |
| If any extension of time has been granted | NO |
| Cost of land | 2700000 |
| Cost of construction | 169540000 |
| Total project cost | 172240000 |
| Total amount collected from buyers | 148396145.00 |
| Whether any loan has been raised | YES |
| Total amount spent for completion of the project | 227288138 |
| Balance amount with the promoter | 78862649.00 |
| Total number of Flats/Apartments of the Project | 230 |
| Total number of Flats/Apartments sold | 101 |
| Total number of Flats/Apartments Unsold | 129 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 19-05-2022 |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |