SHETTY-PATIL DEVELOPERS LLP
CTS NO 105+106 A/B/C, Oppsite Gali Durgamma Temple, Hosur Circle Hubli
Approved
29th Mar 2018
Completed
30th Dec 2022
Registration No.
PRM/KA/RERA/1259/410/PR/180329/001132
Acknowledgement No.
PR/KN/170810/001132
Project Type
Mixed Development
Approving Authority
Hubbali-Dharwad Urban Development Authority
District
Dharwad
Taluka
Dharwad
State
Karnataka
| Project Name | ONE HUBLI PHASE-1 |
| Project Description | Largest mixed use development in Hubli with around 2.5 million sq. ft. built up area consisting of Shopping Mall, Luxury Apartments with Private Pool, Dining & Entertainment and Hotels. |
| Project Type | Mixed Development |
| Project Status | Ongoing |
| Project Start Date | 30-03-2017 |
| Proposed Project Completion Date | 30-12-2022 |
| Total Area Of Land (Sq Mtr) | 18215 |
| Total Coverd Area (Sq Mtr) | 11187 |
| Total Open Area (Sq Mtr) | 7090 |
| Estimated Cost of Construction (INR) | 915892614 |
| Cost of Land (INR) | 393467256 |
| Total Project Cost (INR) | 1309359870 |
| Project Address | CTS NO 105+106 A/B/C, Oppsite Gali Durgamma Temple, Hosur Circle Hubli |
| District | Belagavi |
| Taluk | Dharwad |
| Approving Authority | Hubbali-Dharwad Urban Development Authority |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Extent of development carried till date | 4 % |
| Extent of development pending | 4 % |
| Total amount of money collected from allottee | 19000000 |
| Total amount of money used for development of project | 18900000 |
| Total amount of balance maney lying with promoter | 100000 |
| Is Any Subsequent Modification in Plan | Yes |
| Is Delay in the Project | No |
| No of Month Delay | 0 |
| Type of Inventory | SHOPS, FLATS, HOTEL, MULTIPLEX |
| No of Inventory | 891 |
| Carpet Area (Sq Mtr) | 39769SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0SqMtr |
| Road System | Local Authority |
| Water Supply | Local Authority |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Self Development |
| Solid Waste Management And Disposal | Self Development |
| Bank Name | Industrial Development Bank of India |
| Branch | Travellers Banglow Road , Hubli |
| ifscCode | IBKL00000069 |
| Account No.(70% Account) | 0069102000023630 |
| State | Karnataka |
| Name | D L Kulkarni Associates |
| Address | 352/B Nehru Road,Tilkwadi Belgaum |
| Pin Code | 590006 |
| Year Of Establishment | 1995 |
| Number of Project Completed | 40 |
| Reg. Of COA No. | COA/32075/2003 IGBC-CS-3084 |
| Local Authority Licence Number | HDMC/60/06/612/A/2014 |
| Promoter Type | Other |
| Name | Kamalabai Patil |
| PAN Number | ADCFS4934J |
| Address | 31 Akkamahadevi Road.Vijayapura |
| District | Pune |
| State/UT | Maharashtra |
| PIN Code | 411040 |
| Company Registration No. | NOT APPLICABLE |
| Type | Others |
| Pin Code | 586101 |
| Modification Applied On | 31-08-2020 |
| Type of Inventory | SHOPS |
| No of Inventory | 925 |
| Carpet Area (Sq Mtr) | 46843 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Details of Modification of plan sanction / layout brief description | Dear RERA Karnataka, We would like to inform the authority that in One Hubli Phase 1, we have modified the earlier approved plan in terms of shops. Hence shops have been increased and the residential part of the project has been scrapped. We have uploaded all the requisite documents as per RERA. We would request the authority to kindly look into it and grant us modification at the earliest. |
| Modified plan applied date | 04/07/2020 |
| Modified plan approved date | 04/07/2020 |
| Extend of the work carried out till date of registered project ( % ) | 30.0 |
| Extend of the work pending of registered project ( % ) | 70.0 |
| Total amount collected in respect of registered project ( INR ) | 56843947 |
| Total amount spent for the project ( INR ) | 209506822 |
| Total balance amount lying with the promoter ( INR ) | 0 |
| NOC | SEIAA |
| SlNo. |
| Extension Applied On | 10-12-2021 |
| Extension Approved On | 24-08-2022 |
| Extension Registration Number | EX/PRM/KA/RERA/1259/410/PR/220824/001132 |
| Proposed Project End Date at the time of registration | 30-12-2021 |
| Project End Date provided under Section 6 | 30-12-2022 |
| whether 2/3rd concern from the allottees has taken? | NO |
| Whether any compensation is provided for the Buyer? | NO |
| Document Name | KSPCB NOC |
| 1 | Shortage of Building Materials, Concrete, Jalli etc |
| Document Name_1 | |
| Document Name_2 |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 01-09-2017 | 18-03-2018 |
| 2 | Foundation footing work | Yes | 15-09-2017 | 01-06-2018 |
| 3 | Retaining wall (All types) | Yes | 15-09-2017 | 01-06-2018 |
| 4 | Plinth level Beam | Yes | 01-12-2017 | 01-07-2018 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 15-09-2017 | 01-07-2018 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | Yes |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | Yes |
| 7 | Solid waste management and disposal | No |
| 8 | Water conservation | Yes |
| 9 | Energy management | Yes |
| 10 | Fire protection and fire safety requirements | Yes |
| 11 | Education/Health/Other public amenities | Yes |
| FAR Sanctioned | 2.5 |
| Number of Towers | 1 |
| 0 | 221 |
| 1 | 222 |
| 2 | 189 |
| 3 | 189 |
| 4 | 10 |
| 5 | 10 |
| 6 | 10 |
| 7 | 10 |
| 8 | 10 |
| 9 | 10 |
| 10 | 10 |
| Total No of Units | 891 |
| Project Start Date | 30-03-2017 |
| Project End Date | 30-12-2022 |
| If any extension of time has been granted | YES |
| Extended From Date | 30-12-2021 |
| Extended End Date | 30-12-2022 |
| Cost of land | 393467256 |
| Cost of construction | 915892614 |
| Total project cost | 1309359870 |
| Total amount collected from buyers | 332801921 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 731083266 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 819 |
| Total number of Flats/Apartments sold | 110 |
| Total number of Flats/Apartments Unsold | 709 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 08-08-2023 |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |