NEW HOMES REALITY
R.S NO.567/2A, PLOT NO.1, BESIDE IBMR COLLEGE,, AKSHAY COLONY, HUBLI
Approved
16th May 2018
Completed
30th Dec 2021
Registration No.
PRM/KA/RERA/1259/410/PR/180516/001709
Acknowledgement No.
PR/KN/180120/002676
Project Type
Residential/Group Housing
Approving Authority
Hubbali-Dharwad Urban Development Authority
District
Dharwad
Taluka
Dharwad
State
Karnataka
| Project Name | SAILAND PARK |
| Project Description | SITUATED AT R.S NO.567/2A, PLOT NO.1, AKSHAY COLONY, HUBBALLI-580031 |
| Project Type | Residential/Group Housing |
| Project Status | Completed |
| Project Start Date | 26-01-2018 |
| Proposed Project Completion Date | 30-12-2021 |
| Total Area Of Land (Sq Mtr) | 1584 |
| Total Coverd Area (Sq Mtr) | 1042 |
| Total Open Area (Sq Mtr) | 570 |
| Estimated Cost of Construction (INR) | 65876577 |
| Cost of Land (INR) | 15996500 |
| Total Project Cost (INR) | 81873077 |
| Project Address | R.S NO.567/2A, PLOT NO.1, BESIDE IBMR COLLEGE,, AKSHAY COLONY, HUBLI |
| District | Dharwad |
| Taluk | Dharwad |
| Approving Authority | Hubbali-Dharwad Urban Development Authority |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Road System | Local Authority |
| Water Supply | Local Authority |
| Sewege and Drainage System | Local Authority |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Local Authority |
| Fire Fighting facility | Local Authority |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Local Authority |
| Bank Name | CORPORATION BANK |
| Branch | VIDYANAGAR |
| ifscCode | CORP0000528 |
| Account No.(70% Account) | 510101006371902 |
| State | Karnataka |
| Name | D.L.KULKARNI & ASSOCIATES |
| Address | #352/B , NEHRU ROAD, TILAKWADI,,BELAGAVI |
| Pin Code | 590006 |
| Year Of Establishment | 2008 |
| Number of Project Completed | 100+ |
| Reg. Of COA No. | C.A./2015/70108 |
| Local Authority Licence Number | HDMC/60/05/219/2015 |
| Promoter Type | Partnership Firm |
| Name | S. M. SHIVYOGIMATH |
| PAN Number | AAMFN9976G |
| Address | 52/101, SEAWOOD ESTATE, NRI COMPLEX,.NEAR D.P.S SCHOOL, SECTOR 54/56/58 NERUL |
| District | Dharwad |
| State/UT | Karnataka |
| PIN Code | 580031 |
| Company Registration No. | NOT APPLICABLE |
| Type | Others |
| Pin Code | 400706 |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 02-01-2018 | 27-02-2018 |
| 2 | Foundation footing work | Yes | 27-02-2018 | 21-04-2018 |
| 3 | Retaining wall (All types) | Yes | 19-03-2018 | 28-05-2018 |
| 4 | Plinth level Beam | Yes | 21-03-2018 | 24-04-2018 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 01-01-2021 | 30-06-2021 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | No |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | No |
| 5 | Street Lighting | No |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | No |
| 7 | Solid waste management and disposal | Yes |
| 8 | Water conservation | Yes |
| 9 | Energy management | No |
| 10 | Fire protection and fire safety requirements | Yes |
| 11 | Education/Health/Other public amenities | No |
| 12 | Electricity supply transformer and substation | Yes |
| FAR Sanctioned | 2.25 |
| Number of Towers | 1 |
| 0 | 8 |
| 1 | 8 |
| 2 | 8 |
| 3 | 8 |
| 4 | 8 |
| Total No of Units | 40 |
| Project Start Date | 26-01-2018 |
| Project End Date | 30-12-2021 |
| If any extension of time has been granted | NO |
| Cost of land | 15996500 |
| Cost of construction | 65876577 |
| Total project cost | 81873077 |
| Total amount collected from buyers | 73934721 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 73934721 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 40 |
| Total number of Flats/Apartments sold | 21 |
| Total number of Flats/Apartments Unsold | 19 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 07-06-2021 |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |