R R LANDMARKS PVT LTD
OPP OXFORD COLLEGE, KUSUGAL ROAD, , KESHWAPUR, HUBLI
Approved
27th Aug 2020
Completed
31st Dec 2023
Registration No.
PRM/KA/RERA/1259/479/PR/200827/003560
Acknowledgement No.
ACK/KA/RERA/1259/479/PR/200217/003906
Project Type
Residential/Group Housing
Approving Authority
Hubbali-Dharwad Urban Development Authority
District
Dharwad
Taluka
Hubballi
State
Karnataka
| Project Name | SHARAN RESIDENCY |
| Project Description | A RESIDENTIAL PROJECT IN KUSUGAL ROAD, HUBLI WHICH SELF CONTAINS FOR COMFORTABLE LIVING AND THE PREMIUM FLATS IN DIFFERENT REQUIREMENTS AND BUDGETS. |
| Project Type | Residential/Group Housing |
| Project Status | Ongoing |
| Project Start Date | 31-12-2018 |
| Proposed Project Completion Date | 31-12-2023 |
| Total Area Of Land (Sq Mtr) | 2547 |
| Total Coverd Area (Sq Mtr) | 3159 |
| Total Open Area (Sq Mtr) | 413 |
| Estimated Cost of Construction (INR) | 39900000 |
| Cost of Land (INR) | 13200000 |
| Total Project Cost (INR) | 53100000 |
| Project Address | OPP OXFORD COLLEGE, KUSUGAL ROAD, , KESHWAPUR, HUBLI |
| District | Dharwad |
| Taluk | Hubballi |
| Approving Authority | Hubbali-Dharwad Urban Development Authority |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 48 |
| Area of Parking for Sale (Sq Mtr) | 746 |
| Extent of development carried till date | 40 % |
| Extent of development pending | 60 % |
| Total amount of money collected from allottee | 0 |
| Total amount of money used for development of project | 13500000 |
| Total amount of balance maney lying with promoter | 5000000 |
| Is Any Subsequent Modification in Plan | No |
| Is Delay in the Project | No |
| No of Month Delay | 0 |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Local Authority |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Local Authority |
| Fire Fighting facility | Local Authority |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Local Authority |
| Bank Name | Bank of Baroda |
| Branch | CBD BELAPUR |
| ifscCode | BARBOBELAPU |
| Account No.(70% Account) | 27660200001285 |
| State | Karnataka |
| Name | UDAY N KALKUNDRIKAR |
| Address | KRISHNA VIHAR, F-1 1808, KELKAR BAUG, ,OFF KIRLOSKAR ROAD, BELGAUM |
| Pin Code | 590001 |
| Year Of Establishment | 1987 |
| Number of Project Completed | 35 |
| Reg. Of COA No. | HDW/BL/10192/18-19 |
| Local Authority Licence Number | HDW/BL/10192/18-19 |
| Promoter Type | Company |
| Name | HEMANNA PAMPANNA PAWALI |
| PAN Number | AAFCR0170A |
| Address | BELLE VISTA, CHS FLAT NO. C 302, PLOT NO. 46,47,48. NEAR D Y PATIL COLLEGE, .SECTOR 15, CBD, NAVI MUMBAI, BELAPUR, KONDAN BHAVAN, THANE |
| District | Dharwad |
| State/UT | Karnataka |
| PIN Code | 580023 |
| Company Registration No. | U45200PN2010PTC136255 |
| Type | Director |
| Pin Code | 400614 |
| Sl No. |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 15-02-2019 | 20-02-2019 |
| 2 | Foundation footing work | No | ||
| 3 | Retaining wall (All types) | No | ||
| 4 | Plinth level Beam | No | ||
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | No |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | Yes |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | Yes |
| 5 | Street Lighting | No |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | No |
| 7 | Solid waste management and disposal | No |
| 8 | Water conservation | No |
| 9 | Energy management | No |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | No |
| WebSite Link 1 | www.rrconstructions.co.in |
| FAR Sanctioned | 1.009 |
| Number of Towers | 2 |
| 0 | 0 |
| 1 | 6 |
| 2 | 6 |
| 3 | 6 |
| 4 | 6 |
| Total No of Units | 48 |
| Project Start Date | 31-12-2018 |
| Project End Date | 31-12-2023 |
| If any extension of time has been granted | NO |
| Cost of land | 13200000 |
| Cost of construction | 39900000 |
| Total project cost | 53100000 |
| Total amount collected from buyers | 0 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 39900000 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 48 |
| Total number of Flats/Apartments sold | 0 |
| Total number of Flats/Apartments Unsold | 48 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 19-05-2022 |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |