SHRIYA PROPERTIES
PLOT NO 1, OPPSIT TO MURDESHWAR CERAMICS, R N S ROAD HUBLI
Approved
31st Oct 2017
Completed
2nd Dec 2019
Registration No.
PRM/KA/RERA/1259/410/PR/171031/001140
Acknowledgement No.
PR/KN/170808/001140
Project Type
Mixed Development
Approving Authority
Hubballi Dharwad Municipal Corporation
District
Dharwad
Taluka
Dharwad
State
Karnataka
| Project Name | SHRIYA SOLITAIRE |
| Project Description | RESIDENTIAL CUM COMMERCIAL PROJECT |
| Project Type | Mixed Development |
| Project Status | Completed |
| Project Start Date | 17-03-2016 |
| Proposed Project Completion Date | 02-12-2019 |
| Total Area Of Land (Sq Mtr) | 707 |
| Total Coverd Area (Sq Mtr) | 565 |
| Total Open Area (Sq Mtr) | 142 |
| Estimated Cost of Construction (INR) | 61000000 |
| Cost of Land (INR) | 10000000 |
| Total Project Cost (INR) | 71000000 |
| Project Address | PLOT NO 1, OPPSIT TO MURDESHWAR CERAMICS, R N S ROAD HUBLI |
| District | Dharwad |
| Taluk | Dharwad |
| Approving Authority | Hubballi Dharwad Municipal Corporation |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 18 |
| Area of Parking for Sale (Sq Mtr) | 90 |
| Road System | Local Authority |
| Water Supply | Local Authority |
| Sewege and Drainage System | Local Authority |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Local Authority |
| Fire Fighting facility | Local Authority |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Self Development |
| Use of Renewable Energy | Self Development |
| Bank Name | Karnataka Bank Ltd. |
| Branch | NEW COTTON MARKET |
| ifscCode | KARB0000316 |
| Account No.(70% Account) | 3162000100164401 |
| State | Karnataka |
| Name | PRAKASH CHAVAN |
| Address | 13, ARJUN VIHAR,,GOKUL ROAD HUBLI |
| Pin Code | 580030 |
| Year Of Establishment | 2010 |
| Number of Project Completed | 15 |
| Local Authority Licence Number | HDMC6005558A201617 |
| Promoter Type | Partnership Firm |
| Name | SURAJ ALAVANDI |
| PAN Number | ACEFS9497D |
| Address | 13, ARJUN VIHAR , GOKUL ROAD, HUBLI. |
| District | Dharwad |
| State/UT | Karnataka |
| PIN Code | 580030 |
| Company Registration No. | DWRF114201213 |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 11-03-2016 | 12-04-2016 |
| 2 | Foundation footing work | Yes | 13-04-2016 | 10-05-2016 |
| 3 | Retaining wall (All types) | Yes | 25-04-2016 | 20-05-2016 |
| 4 | Plinth level Beam | Yes | 10-05-2016 | 20-05-2016 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 01-06-2016 | 05-06-2016 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | No |
| 2 | Internal Roads & Footpaths | No |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | No |
| 5 | Street Lighting | No |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | No |
| 7 | Solid waste management and disposal | No |
| 8 | Water conservation | No |
| 9 | Energy management | No |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities |
| FAR Sanctioned | 2.5 |
| Number of Towers | 1 |
| 0 | 7 |
| 1 | 8 |
| 2 | 6 |
| 3 | 6 |
| 4 | 6 |
| Total No of Units | 33 |
| Project Start Date | 17-03-2016 |
| Project End Date | 02-12-2019 |
| If any extension of time has been granted | NO |
| Cost of land | 10000000 |
| Cost of construction | 61000000 |
| Total project cost | 71000000 |
| Total amount collected from buyers | 74271450 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 34812500 |
| Balance amount with the promoter | 39458950 |
| Total number of Flats/Apartments of the Project | 33 |
| Total number of Flats/Apartments sold | 33 |
| Total number of Flats/Apartments Unsold | 0 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | NO |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 06-02-2019 |
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |


Ask Pulse Ai anything about real estate