Zionhills Avenues LLP
Bangarapet
Approved
22nd Jan 2024
Completed
31st Dec 2025
Registration No.
PRM/KA/RERA/1265/345/PR/220124/006567
Acknowledgement No.
ACK/KA/RERA/1265/345/PR/271223/007708
Project Type
Plotted Development
District
Kolar
Taluka
Bangarapet
State
Karnataka
| Number of Survey No./CMC No./CTS No./PID No. | 1 |
| Is there any Litigations on Land/Property/Khatha? | YES |
| Sl No. |
| Type of Firm | Partnership Firm |
| Promoter Name | Zionhills Avenues LLP |
| Main Objectives | Plotted Development |
| Registration Number | ABZ6160 |
| PAN | ADBPG1298G |
| GSTIN | 29AADFZ3217F1Z5 |
| Promoter Address | Villa No.307, Zionhills Golf Country, Bangarapet Road, Hanchala Post ,Bangarapet ,Kolar-563114 |
| District | Kolar |
| Taluk | Bangarapet |
| PIN Code | 563114 |
| Name of Authorized Signatory | Mr George Peter Menomparampil |
| Number of Partners | 2 |
| Is there any RERA Registrations in other State / UT ? | NO |
| Is there any Projects Launched In The Past 5 Years in Karnataka ? | NO |
| Present Address | 23183 Tower 23, Floor 18, Prestige Shantiniketan ITPL, Whitefield Road, Near Bigbazar, Bangalore North , Bengaluru Urban , Karnataka - 560048 |
| Permanent Address | 23183 Tower 23, Floor 18, Prestige Shantiniketan ITPL, Whitefield Road, Near Bigbazar, Bangalore North , Bengaluru Urban , Karnataka - 560048 |
| Official Address | Villa No.307, Zionhills Golf Country, Bangarapet Road, Hanchala Post , Kolar , Karnataka - 563114 |
| Sl No. | |
| Sl No._1 |
| Type of Inventory | Odd Sites |
| No of Inventory | 7 |
| Carpet Area (Sq Mtr) | 0 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Sl No. | Plot No. | Plot Type | Plot Size | Plot Area | Phase | Stage | North Dimension | South Dimension | East Dimension | West Dimension | North Schedule Dimension | South Schedule Dimension | East Schedule Dimension | West Schedule Dimension |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 1 | Residential Site | Odd Site | 3102.864 | Phase 1 | New Project | 15.31 | 15.24 | 203 | 204.21 | Private Property | 12m wide road | Private Property | 12m wide road |
| 2 | 2 | Residential Site | Odd Site | 568.4953 | Phase 1 | New Project | 17.46 | 21.21 | 29.65 | 29.41 | 12m Wide Road | Private Property | 12m Wide Road | Site No 03 |
| 3 | 3 | Residential Site | 19.0m*29.41m | 558.79 | Phase 1 | New Project | 19 | 19 | 29.41 | 29.41 | 12m Wide Road | Private Property | 12m Wide Road | Site No 04 |
| 4 | 4 | Residential Site | 19.0m*29.41m | 558.79 | Phase 1 | New Project | 19 | 19 | 29.41 | 29.41 | 12m Wide Road | Private Property | 12m Wide Road | Site No 05 |
| 5 | 5 | Residential Site | Odd Site | 664.9601 | Phase 1 | New Project | 22.61 | 22.61 | 29.41 | 29.41 | 12m Wide Road | Private Property | 12m Wide Road | 3m wide Pathway |
| 6 | 6 | Residential Site | Odd Site | 520.95 | Phase 1 | New Project | 32.29 | 37.66 | 17.28 | 13.5 | Site No 08 | 12m wide road | Site No.07 | 3m wide Pathway |
| 7 | 7 | Residential Site | Odd Site | 368.6515 | Phase 1 | New Project | 20.09 | 20.25 | 19.43 | 17.28 | Site No 08 | 12m wide road | 12m Wide Road | Site No 06 |
| 8 | 8 | Residential Site | 16.0m*odd | 785.76 | Phase 1 | New Project | 45.83 | 52.38 | 16 | 16 | Site No 09 | Site No 06 & 07 | 12m Wide Road | 3m wide Pathway |
| 9 | 9 | Residential Site | 16.0m*odd | 680.8 | Phase 1 | New Project | 39.28 | 45.83 | 16 | 16 | Site No 10 | Site No 08 | 12m Wide Road | 3m wide Pathway |
| 10 | 10 | Residential Site | 16.0m*odd | 576 | Phase 1 | New Project | 32.72 | 39.28 | 16 | 16 | Site No 11 | Site No 09 | 12m Wide Road | 3m wide Pathway |
| 11 | 11 | Residential Site | 16.0m*odd | 471.04 | Phase 1 | New Project | 26.17 | 32.72 | 16 | 16 | Site No 12 | Site No 10 | 12m Wide Road | 3m wide Pathway |
| 12 | 12 | Residential Site | Odd Site | 452.4 | Phase 1 | New Project | 21.12 | 26.17 | 20 | 21.03 | Site No 13 | Site No 11 | 12m Wide Road | 3m wide Pathway |
| 13 | 12A | Residential Site | 20.0*Odd | 428.6 | Phase 1 | New Project | 21.75 | 21.12 | 20 | 20 | Site No 14 | Site No 12 | 12m Wide Road | 3m wide Pathway |
| 14 | 14 | Residential Site | 20.0*Odd | 441.4 | Phase 1 | New Project | 22.39 | 21.75 | 20 | 20 | Site No 15 | Site No 13 | 12m Wide Road | 3m wide Pathway |
| 15 | 15 | Residential Site | 20.0*Odd | 454.2 | Phase 1 | New Project | 23.03 | 22.39 | 20 | 20 | Site No 16 | Site No 14 | 12m Wide Road | 3m wide Pathway |
| 16 | 16 | Residential Site | 20.0*Odd | 470 | Phase 1 | New Project | 23.67 | 23.03 | 20 | 20 | Site No 17 | Site No 15 | 12m Wide Road | 3m wide Pathway |
| 17 | 17 | Residential Site | 20.0*Odd | 479.6 | Phase 1 | New Project | 24.3 | 23.67 | 20 | 20 | Site No 18 | Site No 16 | 12m Wide Road | 3m wide Pathway |
| 18 | 18 | Residential Site | Odd Site | 423.306 | Phase 1 | New Project | 27.58 | 24.3 | 16.02 | 19.06 | Private Property | Site No 17 | 12m Wide Road | 3m wide Pathway |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Ground Clearance/Formation Of Plots | Yes | 01-01-2024 | 31-01-2024 |
| 2 | Formation Of Road, Footpath | Yes | 01-02-2024 | 30-06-2024 |
| 3 | Construction Of Water Supply Infrastucture | Yes | 01-07-2024 | 31-12-2024 |
| 4 | Construction Of Sewage System Infrastucture | Yes | 01-01-2025 | 30-06-2025 |
| 5 | Power Supply Work(Transformer & Substation) | Yes | 01-07-0005 | 31-12-2025 |
| 6 | Construction Of Storm Water Drainage | Yes | 01-07-2025 | 31-12-2025 |
| 7 | Solid Waste Management and Disposal | Yes | 01-07-2025 | 31-12-2025 |
| 8 | Tree Plantation And LandScape Work | Yes | 01-07-2025 | 31-12-2025 |
| 9 | Street Lighting | Yes | 01-07-2025 | 31-12-2025 |
| 10 | Sewage Treatment Plant (STP) | Yes | 01-07-2025 | 31-12-2025 |
| 11 | Other Miscellaneous Work | Yes | 01-07-2025 | 31-12-2025 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Electricity | Yes |
| 2 | Smart home automation | No |
| 3 | CCTV surveillance | Yes |
| 4 | Club House | No |
| 5 | Community Hall | No |
| 6 | Outdoor Sports facility | No |
| 7 | Indoor sports facility | No |
| 8 | Swimming Pools | No |
| 9 | Gym | No |
| 10 | Parks | Yes |
| 11 | Power Backup | Yes |
| 12 | Piped Gas | No |
| 13 | Water and Sanitation | Yes |
| 14 | Air conditioning | No |
| Total number of Plots | 18 |
| No. of Public and Semi Pubic Sites | 0 |
| Area of Public and Semi Pubic Sites(in Sq.m) | 0 |
| No. of Parks and Open Spaces | 1 |
| Area of Parks and Open Spaces(in Sq.m) | 6438 |
| Area of Road/Transportation(in Sq.m) | 4622 |
| Project Start Date | 01-01-2024 |
| Project End Date | 31-12-2025 |
| If any extension of time has been granted | NO |
| Cost of land | 15000000 |
| Cost of construction | 26938545 |
| Total cost | 41938545 |
| Total amount collected From buyers | 49776394 |
| Whether any loan has been raised | NO |
| Total amount spent on Project for completion of the project | 49342856 |
| Total No of sites of Project | 18 |
| Total No of sites sold | 5 |
| Total No of sites unsold | 13 |
| Whether there is any changes in inventory details | NO |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |