BENCHMARK ARADHYA

ARADHYA DEVELOPERS

MYSORE

Approved

17th Mar 2022

Completed

30th Jun 2022

Registration No.

PRM/KA/RERA/1268/378/PR/170322/004771

Acknowledgement No.

ACK/KA/RERA/1268/378/PR/130122/005590

Project Type

Plotted Development

District

Mysore

Taluka

MYSORE

State

Karnataka

Project Details

Number of Survey No./CMC No./CTS No./PID No.1
Is there any Litigations on Land/Property/Khatha?NO

Promoter Details

Type of FirmPartnership Firm
Promoter NameARADHYA DEVELOPERS
Main ObjectivesBUILDERS
Registration NumberMYSF223202122
PANAAPPV2783C
GSTINNA
Promoter Address1053, 4 Th Stage ,T.K.Layout,,Kuvempunagar, Mysore ,MYSORE ,Mysore-570023
DistrictMysore
TalukMYSORE
PIN Code570023
Name of Authorized SignatoryChetan Vishwanath
Number of Partners2
Is there any RERA Registrations in other State / UT ?NO
Is there any Projects Launched In The Past 5 Years in Karnataka ?NO
Present Address1053, 4 Th Stage ,T.K.Layout ,Kuvempunagar Mysore 570023 , Mysore , Karnataka - 570023
Permanent Address1053, 4 Th Stage ,T.K.Layout ,Kuvempunagar Mysore 570023 , Mysore , Karnataka - 570023
Official Address1053, 4 Th Stage ,T.K.Layout ,Kuvempunagar Mysore 570023 , Mysore , Karnataka - 570023
Sl No.
Sl No._1

Modification Plan Details

Type of InventoryOPEN PLOTS with dimension 9*15
No of Inventory5
Carpet Area (Sq Mtr)675 Sq Mtr
Area of exclusive balcony/verandah (Sq Mtr)0 Sq Mtr
Area of exclusive open terrace if any (Sq Mtr)0 Sq Mtr

Residential Plot Details

Sl No.Plot No.Plot TypePlot SizePlot AreaPhaseStageNorth DimensionSouth DimensionEast DimensionWest DimensionNorth Schedule DimensionSouth Schedule DimensionEast Schedule DimensionWest Schedule Dimension
11Site201.29201.2911PRIVATE LAND18.0M ROADPRIVATE LAND9.0M ROADPRIVATE LAND18.0M ROADPRIVATE LAND9.0M ROAD
22Site2111.7892111.78911SYNO.367/19.0M ROADSITENO.3 TO 718.0M ROADSYNO.367/19.0M ROADSITENO.3 TO 718.0M ROAD
33Site143.63143.6311SYNO.367/1SITENO.49.0M ROADSITENO.2SYNO.367/1SITENO.49.0M ROADSITENO.2
44Site13513511SITENO.3SITENO.59.0M ROADSITENO.2SITENO.3SITENO.59.0M ROADSITENO.2
55Site13513511SITENO.4SITENO.69.0M ROADSITENO.2SITENO.4SITENO.69.0M ROADSITENO.2
66Site13513511SITENO.5SITENO.79.0M ROADSITENO.2SITENO.5SITENO.79.0M ROADSITENO.2
77Site162.15162.1511SITENO.69.0M ROAD9.0M ROADSITENO.2SITENO.69.0M ROAD9.0M ROADSITENO.2
88Site112.26112.2611SYNO.367/1SITENO.9SYNO.3659.0M ROADSYNO.367/1SITENO.9SYNO.3659.0M ROAD
99Site10810811SITENO.8SITENO.10SYNO.3659.0M ROADSITENO.8SITENO.10SYNO.3659.0M ROAD
1010Site10810811SITENO.9SITENO.11SYNO.3659.0M ROADSITENO.9SITENO.11SYNO.3659.0M ROAD
1111Site10810811SITENO.10SITENO.12SYNO.3659.0M ROADSITENO.10SITENO.12SYNO.3659.0M ROAD
1212Site10810811SITENO.11SITENO.13SYNO.3659.0M ROADSITENO.11SITENO.13SYNO.3659.0M ROAD
1313Site10810811SITENO.12SITENO.14SYNO.3659.0M ROADSITENO.12SITENO.14SYNO.3659.0M ROAD
1414Site10810811SITENO.13SITENO.15SYNO.3659.0M ROADSITENO.13SITENO.15SYNO.3659.0M ROAD
1515Site105.3105.311SITENO.14SYNO.368/2SYNO.3659.0M ROADSITENO.14SYNO.368/2SYNO.3659.0M ROAD

Project Development Schedule

Sl NoProject WorkIs Applicable ?Estimated From DateEstimated To Date
1Ground Clearance/Formation Of PlotsYes11-01-202101-03-2022
2Formation Of Road, FootpathYes11-01-202101-03-2022
3Construction Of Water Supply InfrastuctureYes11-01-202101-03-2022
4Construction Of Sewage System InfrastuctureYes11-01-202101-03-2022
5Power Supply Work(Transformer & Substation)Yes11-01-202101-03-2022
6Construction Of Storm Water DrainageYes11-01-202101-03-2022
7Solid Waste Management and DisposalNo
8Tree Plantation And LandScape WorkYes11-01-202101-03-2022
9Street LightingYes11-01-202101-03-2022
10Sewage Treatment Plant (STP)Yes11-01-202101-03-2022
11Other Miscellaneous WorkYes11-01-202101-03-2022

Amenities & Utilities Availability

SlNo.WorkIs Applicable ?
1ElectricityYes
2Smart home automationNo
3CCTV surveillanceNo
4Club HouseNo
5Community HallNo
6Outdoor Sports facilityNo
7Indoor sports facilityNo
8Swimming PoolsNo
9GymNo
10ParksYes
11Power BackupNo
12Piped GasNo
13Water and SanitationYes
14Air conditioningNo

Post Registration Details

Total number of Plots15
No. of Public and Semi Pubic Sites1
Area of Public and Semi Pubic Sites(in Sq.m)4204
No. of Parks and Open Spaces2
Area of Parks and Open Spaces(in Sq.m)1217
Area of Road/Transportation(in Sq.m)2986

Completion Details

Project Start Date30-12-2021
Project End Date30-06-2022
If any extension of time has been grantedNO
Cost of land3000000
Cost of construction7500000
Total cost10500000
Total amount collected From buyers0
Whether any loan has been raisedNO
Total amount spent on Project for completion of the project77192352
Total No of sites of Project15
Total No of sites sold0
Total No of sites unsold15
Whether there is any changes in inventory detailsYES

Appeals & Complaints

Complaints on PromoterNo Complaints Found.
Complaints on ProjectNo Complaints Found.

Top Properties in Mangalore

Pexo Icon

Ask Pulse Ai anything about real estate

Unlock the Latest in Real Estate

News, Infographics, Blogs & More! Delivered to your inbox.

Proptech Pulse Logo

Data that drives action.
Insight that inspires action.
Technology that empowers action.“

Made with Love

Statue

© PropTech Pulse 2026, All rights reserved.

Terms of Use and Privacy Policy