BRC PLOTS

BELLAM VIJAYALAKSHMI

MYSORE

Approved

30th Oct 2024

Completed

30th Dec 2025

Registration No.

PRM/KA/RERA/1268/378/PR/301024/007186

Acknowledgement No.

ACK/KA/RERA/1268/378/PR/240723/007311

Project Type

Plotted Development

District

Mysore

Taluka

MYSORE

State

Karnataka

Project Details

Number of Survey No./CMC No./CTS No./PID No.1
Is there any Litigations on Land/Property/Khatha?NO

Promoter Details

Type of FirmOther ( INDIVIDUAL )
Promoter NameBELLAM VIJAYALAKSHMI
Main ObjectivesPLOT DEVELOPMENT
Registration NumberNOT APPLICABLE
PANABUPB5047M
GSTINNOT APPLICABLE
Promoter AddressSy. No 10/3, Varuna Hobli, Choranahalli Village,Mysore ,MYSORE ,Mysore-570010
DistrictMysore
TalukMYSORE
PIN Code570010
Name of Authorized SignatoryBELLAM VIJAYALAKSHMI
Is there any RERA Registrations in other State / UT ?NO
Is there any Projects Launched In The Past 5 Years in Karnataka ?NO
Present AddressChellamathota, Tanguturu , Prakasam , Andhra Pradesh - 523274
Permanent AddressChellamathota, Tanguturu , Prakasam , Andhra Pradesh - 523274
Official AddressSy. No 10/3, Varuna Hobli, Choranahalli Village , Mysore , Karnataka - 570010
Sl No.

Modification Plan Details

Type of InventorySite Measuring 9*15
No of Inventory13
Carpet Area (Sq Mtr)0 Sq Mtr
Area of exclusive balcony/verandah (Sq Mtr)0 Sq Mtr
Area of exclusive open terrace if any (Sq Mtr)0 Sq Mtr

Residential Plot Details

Sl No.Plot No.Plot TypePlot SizePlot AreaPhaseStageNorth DimensionSouth DimensionEast DimensionWest DimensionNorth Schedule DimensionSouth Schedule DimensionEast Schedule DimensionWest Schedule Dimension
11Residential101.321090.60Under DevelopmentNew9.969.8010.3910.12Pvt PropertyPlot No.2RoadPlot No.5
22Residential87.85945.57Under DevelopmentNew9.159.0010.129.24Plot No.4Plot No.3N2Plot No.4
33Residential190.322048.60Under DevelopmentNew9.309.0022.0019.60Plot No.2 & 4CAPvt PropertyRoad
44Residential117.541265.20Under DevelopmentNew9.009.0013.0613.06Plot No.5Plot No.3Plot No.2Road
55Residential125.571351.66Under DevelopmentNew9.809.4313.0613.06Pvt PropertyPlot No.4Plot No.4Road
66Residential138.071486.24Under DevelopmentNew9.419.0015.0015.00Pvt PropertyPlot No.7RoadPvt Property
77Residential135.001453.14Under DevelopmentNew9.009.0015.0015.00Plot No.6Plot No.8RoadPvt Property
88Residential135.001453.14Under DevelopmentNew9.009.0015.0015.00Plot No.7Plot No.9RoadPvt Property
99Residential135.001453.14Under DevelopmentNew9.009.0015.0015.00Plot No.8Plot No.10RoadPvt Property
1010Residential135.001453.14Under DevelopmentNew9.009.0015.0015.00Plot No.9Plot No.11RoadPvt Property
1111Residential135.001453.14Under DevelopmentNew9.009.0015.0015.00Plot No.10Plot No.12RoadPvt Property
1212Residential135.001453.14Under DevelopmentNew9.009.0015.0015.00Plot No.11Plot No.13RoadPvt Property
1313Residential135.001453.14Under DevelopmentNew9.009.0015.0015.00Plot No.12Plot No.14RoadPvt Property
1414Residential135.001453.14Under DevelopmentNew9.009.0015.0015.00Plot No.13Plot No.15RoadPvt Property
1515Residential135.001453.14Under DevelopmentNew9.009.0015.0015.00Plot No.14Plot No.16RoadPvt Property
1616Residential135.001453.14Under DevelopmentNew9.009.0015.0015.00Plot No.15Plot No.17RoadPvt Property
1717Residential135.001453.14Under DevelopmentNew9.009.0015.0015.00Plot No.16Plot No.18RoadPvt Property
1818Residential197.472125.62Under DevelopmentNew12.6713.6615.0015.00Plot No.17RoadRoadPvt Property

Project Development Schedule

Sl NoProject WorkIs Applicable ?Estimated From DateEstimated To Date
1Ground Clearance/Formation Of PlotsYes08-03-202331-05-2023
2Formation Of Road, FootpathYes06-04-202318-05-2023
3Construction Of Water Supply InfrastuctureYes14-04-202330-05-2023
4Construction Of Sewage System InfrastuctureYes25-05-202320-06-2023
5Power Supply Work(Transformer & Substation)Yes30-05-202329-06-2023
6Construction Of Storm Water DrainageYes11-06-202330-06-2023
7Solid Waste Management and DisposalYes06-06-202315-06-2023
8Tree Plantation And LandScape WorkYes15-06-202315-07-2023
9Street LightingYes30-05-202329-06-2023
10Sewage Treatment Plant (STP)No
11Other Miscellaneous WorkNo

Amenities & Utilities Availability

SlNo.WorkIs Applicable ?
1ElectricityYes
2Smart home automationNo
3CCTV surveillanceNo
4Club HouseNo
5Community HallNo
6Outdoor Sports facilityNo
7Indoor sports facilityNo
8Swimming PoolsNo
9GymNo

Post Registration Details

Total number of Plots18
No. of Public and Semi Pubic Sites1
Area of Public and Semi Pubic Sites(in Sq.m)482
No. of Parks and Open Spaces1
Area of Parks and Open Spaces(in Sq.m)446
Area of Road/Transportation(in Sq.m)1080

Completion Details

Project Start Date01-04-2023
Project End Date30-12-2025
If any extension of time has been grantedNO
Cost of land4342600
Cost of construction6000000
Total cost10342600
Total amount collected From buyers17884200
Whether any loan has been raisedNO
Total amount spent on Project for completion of the project10342600
Total No of sites of Project18
Total No of sites sold10
Total No of sites unsold8
Whether there is any changes in inventory detailsNO

Appeals & Complaints

Complaints on PromoterNo Complaints Found.
Complaints on ProjectNo Complaints Found.

Top Properties in Mysore

Pexo Icon

Ask Pulse Ai anything about real estate

Unlock the Latest in Real Estate

News, Infographics, Blogs & More! Delivered to your inbox.

Proptech Pulse Logo

Data that drives action.
Insight that inspires action.
Technology that empowers action.“

Made with Love

Statue

© PropTech Pulse 2026, All rights reserved.

Terms of Use and Privacy Policy