HERBAL VILLAGE
D SRIHARI
SY NO 237/2 JAYAPURA VILLAGE, JAYAPURA HOBI
Approved
2nd Jan 2019
Completed
30th Sept 2021
Registration No.
PRM/KA/RERA/1268/378/PR/190102/002273
Acknowledgement No.
ACK/KA/RERA/1268/378/PR/181122/002832
Project Type
Plotted Development
Approving Authority
Local Planing Authority
District
Mysore
Taluka
MYSORE
State
Karnataka
Project Details
| Project Name | HERBAL VILLAGE |
| Project Description | PLOTTED DEVELOPMENT ON 2 ACRES 17 GUNTAS OF CONVERTED LAND |
| Project Type | Plotted Development |
| Project Status | Completed |
| Project Start Date | 21-11-2018 |
| Proposed Project Completion Date | 30-09-2021 |
| Total Area Of Land (Sq Mtr) | 9814 |
| Total Coverd Area (Sq Mtr) | 0 |
| Total Open Area (Sq Mtr) | 9814 |
| Estimated Cost of Construction (INR) | 4500000 |
| Cost of Land (INR) | 3691470 |
| Total Project Cost (INR) | 8191470 |
| Project Address | SY NO 237/2 JAYAPURA VILLAGE, JAYAPURA HOBI |
| District | Mysore |
| Taluk | MYSORE |
| Approving Authority | Local Planing Authority |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Type of Inventory | 41 |
| No of Inventory | 41 |
| Carpet Area (Sq Mtr) | 0SqMtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0SqMtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0SqMtr |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Local Authority |
| Fire Fighting facility | Local Authority |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Local Authority |
| Bank Name | BANK OF INDIA |
| Branch | KUVEMPUNAGAR |
| ifscCode | BKID0008432 |
| Account No.(70% Account) | 843210110003870 |
| State | Karnataka |
Promoter Details
| Firm Type | Individual |
| Name | D SRIHARI |
| Father's Name | LATE S R DWARAKANATH |
| PAN Number | ABC******* |
| Address | 1720 3RD CROSS ANIKETANA ROAD,KUVEMPUNAGAR MYSORE |
| State/UT | Karnataka |
| PIN Code | 570023 |
Modification Plan Details
| Type of Inventory | 41 |
| No of Inventory | 41 |
| Carpet Area (Sq Mtr) | 0 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
Residential Plot Details
| Sl No. | Plot No. | Plot Type | Plot Size | Plot Area | Phase | Stage | North Dimension | South Dimension | East Dimension | West Dimension | North Schedule Dimension | South Schedule Dimension | East Schedule Dimension | West Schedule Dimension |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 1 | Odd | 233.14 | 233.14 | 1 | 1 | 20.98 | 17.99 | 11.84 | 12.09 | Sy No 238 | Road | Road | Site 02 |
| 2 | 2 | 9.14*odd | 136.64 | 136.64 | 1 | 1 | 9.14 | 9.14 | 15.09 | 14.81 | Sy No 238 | Road | Site 01 | Site 03 |
| 3 | 3 | 9.14*odd | 134.13 | 134.13 | 1 | 1 | 9.14 | 9.14 | 14.81 | 14.54 | Sy No 238 | Road | Site 02 | Site 04 |
| 4 | 4 | 9.14*odd | 131.62 | 131.62 | 1 | 1 | 9.14 | 9.14 | 14.54 | 14.26 | Sy No 238 | Road | Site 03 | Site 05 |
| 5 | 5 | 9.14*odd | 129.10 | 129.10 | 1 | 1 | 9.14 | 9.14 | 14.26 | 13.99 | Sy No 238 | Road | Site 04 | Site 06 |
| 6 | 6 | 9.14*odd | 126.63 | 126.63 | 1 | 1 | 9.14 | 9.14 | 13.99 | 13.72 | Sy No 238 | Road | Site 05 | Site 07 |
| 7 | 7 | 9.14*odd | 124.12 | 124.12 | 1 | 1 | 9.14 | 9.14 | 13.72 | 13.44 | Sy No 238 | Road | Site 06 | Site 08 |
| 8 | 8 | 9.14*odd | 121.61 | 121.61 | 1 | 1 | 9.14 | 9.14 | 13.44 | 13.17 | Sy No 238 | Road | Site 07 | Site 09 |
| 9 | 9 | 9.14*odd | 119.09 | 119.09 | 1 | 1 | 9.14 | 9.14 | 13.17 | 12.89 | Sy No 238 | Road | Site 08 | Site 10 |
| 10 | 10 | 9.14*odd | 116.58 | 116.58 | 1 | 1 | 9.14 | 9.14 | 12.89 | 12.62 | Sy No 238 | Road | Site 09 | Site 11 |
| 11 | 11 | 9.14*odd | 114.07 | 114.07 | 1 | 1 | 9.14 | 9.14 | 12.62 | 12.34 | Sy No 238 | Road | Site 10 | Site 12 |
| 12 | 12 | 9.14*odd | 110.96 | 110.96 | 1 | 1 | 9.14 | 9.14 | 12.34 | 11.94 | Sy No 238 | Road | Site 11 | Site 13 |
| 13 | 13 | 9.14*odd | 108.45 | 108.45 | 1 | 1 | 9.14 | 9.14 | 11.94 | 11.79 | Sy No 238 | Road | Site 12 | Site 14 |
| 14 | 14 | 9.14*odd | 106.53 | 106.53 | 1 | 1 | 9.14 | 9.14 | 11.79 | 11.52 | Sy No 238 | Road | Site 13 | Site 15 |
| 15 | 15 | 9.14*odd | 104.01 | 104.01 | 1 | 1 | 9.14 | 9.14 | 11.52 | 11.24 | Sy No 238 | Road | Site 14 | Site 16 |
| 16 | 16 | 9.14*odd | 101.50 | 101.50 | 1 | 1 | 9.14 | 9.14 | 11.24 | 10.97 | Sy No 238 | Road | Site 15 | Site 17 |
| 17 | 17 | 9.14*odd | 99.03 | 99.03 | 1 | 1 | 9.14 | 9.14 | 10.97 | 10.70 | Sy No 238 | Road | Site 16 | Site 18 |
| 18 | 18 | 9.14*odd | 96.52 | 96.52 | 1 | 1 | 9.14 | 9.14 | 10.70 | 10.42 | Sy No 238 | Road | Site 17 | Site 19 |
| 19 | 19 | Odd | 95.71 | 95.71 | 1 | 1 | (9.16+9.14)/2 | (9.16+9.14)/2 | 10.42 | 10.50 | Sy No 238 | Road | Site 18 | Site 20 |
| 20 | 20 | Odd | 142.84 | 142.84 | 1 | 1 | 14.15 | 14.49 | 10.15 | 9.80 | Sy No 238 | Road | Site 19 | Road |
| 21 | 21 | 9.14*15.24 | 139.29 | 139.29 | 1 | 1 | 9.14 | 9.14 | 15.24 | 15.24 | Road | Sy No 237/1 | Site 22 | Road |
| 22 | 22 | 9.14*15.24 | 139.29 | 139.29 | 1 | 1 | 9.14 | 9.14 | 15.24 | 15.24 | Road | Sy No 237/1 | Site 23 | Site 21 |
| 23 | 23 | 9.14*15.24 | 139.29 | 139.29 | 1 | 1 | 9.14 | 9.14 | 15.24 | 15.24 | Road | Sy No 237/1 | Site 24 | Site 22 |
| 24 | 24 | 9.14*15.24 | 139.29 | 139.29 | 1 | 1 | 9.14 | 9.14 | 15.24 | 15.24 | Road | Sy No 237/1 | Site 25 | Site 23 |
| 25 | 25 | 9.14*15.24 | 139.29 | 139.29 | 1 | 1 | 9.14 | 9.14 | 15.24 | 15.24 | Road | Sy No 237/1 | Site 26 | Site 24 |
| 26 | 26 | 9.14*15.24 | 139.29 | 139.29 | 1 | 1 | 9.14 | 9.14 | 15.24 | 15.24 | Road | Sy No 237/1 | Site 27 | Site 25 |
| 27 | 27 | 9.14*15.24 | 139.29 | 139.29 | 1 | 1 | 9.14 | 9.14 | 15.24 | 15.24 | Road | Sy No 237/1 | Site 28 | Site 26 |
| 28 | 28 | 9.14*15.24 | 139.29 | 139.29 | 1 | 1 | 9.14 | 9.14 | 15.24 | 15.24 | Road | Sy No 237/1 | Site 29 | Site 27 |
| 29 | 29 | 9.14*15.24 | 139.29 | 139.29 | 1 | 1 | 9.14 | 9.14 | 15.24 | 15.24 | Road | Sy No 237/1 | Site 30 | Site 28 |
| 30 | 30 | 9.14*15.24 | 139.29 | 139.29 | 1 | 1 | 9.14 | 9.14 | 15.24 | 15.24 | Road | Sy No 237/1 | Site 31 | Site 29 |
| 31 | 31 | 9.14*15.24 | 139.29 | 139.29 | 1 | 1 | 9.14 | 9.14 | 15.24 | 15.24 | Road | Sy No 237/1 | Site 32 | Site 30 |
| 32 | 32 | 9.14*15.24 | 139.29 | 139.29 | 1 | 1 | 9.14 | 9.14 | 15.24 | 15.24 | Road | Sy No 237/1 | Site 33 | Site 31 |
| 33 | 33 | 9.14*15.24 | 139.29 | 139.29 | 1 | 1 | 9.14 | 9.14 | 15.24 | 15.24 | Road | Sy No 237/1 | Site 34 | Site 32 |
| 34 | 34 | 9.14*15.24 | 139.29 | 139.29 | 1 | 1 | 9.14 | 9.14 | 15.24 | 15.24 | Road | Sy No 237/1 | Site 35 | Site 33 |
| 35 | 35 | 9.14*15.24 | 139.29 | 139.29 | 1 | 1 | 9.14 | 9.14 | 15.24 | 15.24 | Road | Sy No 237/1 | Site 36 | Site 34 |
| 36 | 36 | 9.14*15.24 | 139.29 | 139.29 | 1 | 1 | 9.14 | 9.14 | 15.24 | 15.24 | Road | Sy No 237/1 | Site 37 | Site 35 |
| 37 | 37 | 9.14*15.24 | 139.29 | 139.29 | 1 | 1 | 9.14 | 9.14 | 15.24 | 15.24 | Road | Sy No 237/1 | Site 38 | Site 36 |
| 38 | 38 | 9.14*15.24 | 139.29 | 139.29 | 1 | 1 | 9.14 | 9.14 | 15.24 | 15.24 | Road | Sy No 237/1 | Site 39 | Site 37 |
| 39 | 39 | 9.14*15.24 | 139.29 | 139.29 | 1 | 1 | 9.14 | 9.14 | 15.24 | 15.24 | Road | Sy No 237/1 | Site 40 | Site 38 |
| 40 | 40 | 9.14*15.24 | 139.29 | 139.29 | 1 | 1 | 9.14 | 9.14 | 15.24 | 15.24 | Road | Sy No 237/1 | Site 41 | Site 39 |
| 41 | 41 | Odd | 139.13 | 139.13 | 1 | 1 | 11.62 | 6.07 | 16.22 | 15.24 | Road | Sy No 237/1 | Road | Site 40 |
Project Development Schedule
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Ground Clearance/Formation Of Plots | Yes | 01-12-2018 | 20-12-2018 |
| 2 | Formation Of Road, Footpath | Yes | 01-10-2019 | 31-12-2019 |
| 3 | Construction Of WaterSupply Infrastucture | Yes | 01-01-2019 | 28-02-2019 |
| 4 | Construction Of Sewage System Infrastucture | Yes | 01-01-2019 | 31-03-2019 |
| 5 | Power Supply Work(Tansformer And Substation) | Yes | 01-08-2019 | 30-09-2019 |
| 6 | Construction Of Storm Water Drainage | Yes | 01-04-2019 | 30-06-2019 |
| 7 | Solid Waste Management and Disposal | Yes | 02-06-2019 | 31-07-2019 |
| 8 | Tree Plantation And LandScape Work | Yes | 01-11-2019 | 31-12-2019 |
| 9 | Street Lighting | Yes | 01-08-2019 | 30-09-2019 |
| 10 | Other Miscellaneous Work | Yes | 01-12-2019 | 31-12-2019 |
Amenities & Utilities Availability
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Electricity | Yes |
| 2 | Smart home automation | No |
| 3 | CCTV surveillance | No |
| 4 | Club House | No |
| 5 | Community Hall | No |
| 6 | Outdoor Sports facility | No |
| 7 | Indoor sports facility | No |
| 8 | Swimming Pools | No |
| 9 | Gym | No |
| 10 | Parks | Yes |
| 11 | Power Backup | No |
| 12 | Gas | No |
| 13 | Water and Sanitation | Yes |
| 14 | Air conditioning and incarnation | No |
Post Registration Details
| Agent Registration No 1 | PRM/KA/RERA/1268/378/AG/170831/000236 |
| Total number of Plots | 41 |
| No. of Public and Semi Pubic Sites | 1 |
| Area of Public and Semi Pubic Sites(in Sq.m) | 736 |
| No. of Parks and Open Spaces | 1 |
| Area of Parks and Open Spaces(in Sq.m) | 496 |
| Area of Road/Transportation(in Sq.m) | 3016 |
Completion Details
| Project Start Date | 21-11-2018 |
| Project End Date | 30-09-2021 |
| If any extension of time has been granted | NO |
| Cost of land | 3691470 |
| Cost of construction | 4500000 |
| Total cost | 8191470 |
| Total amount collected From buyers | 24340000 |
| Whether any loan has been raised | NO |
| Total amount spent on Project for completion of the project | 11538772 |
| Total No of sites of Project | 41 |
| Total No of sites sold | 25 |
| Total No of sites unsold | 16 |
| Whether there is any changes in inventory details | NO |
Appeals & Complaints
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in