HORIZON ENCLAVE

THE ESTATE

MYSORE

Approved

2nd Mar 2022

Completed

8th Jul 2019

Registration No.

PRM/KA/RERA/1268/378/PR/020322/004741

Acknowledgement No.

ACK/KA/RERA/1268/378/PR/120122/005579

Project Type

Plotted Development

District

Mysore

Taluka

MYSORE

State

Karnataka

Project Details

Number of Survey No./CMC No./CTS No./PID No.1
Is there any Litigations on Land/Property/Khatha?NO

Promoter Details

Type of FirmProprietorship Firm
Promoter NameTHE ESTATE
Main ObjectivesREAL ESTATE
Trade NameTHE ESTATE
Registration NumberUDYAMKR220005515
PANAFKPS0922C
GSTINNA
Promoter AddressNo.1143/A, CH1/A, Geetha Road,Chamarajapuram, Mysore ,MYSORE ,Mysore-570005
DistrictMysore
TalukMYSORE
PIN Code570005
Name of Authorized SignatoryM MAHESH SHENOY
Is there any RERA Registrations in other State / UT ?NO
Is there any Projects Launched In The Past 5 Years in Karnataka ?NO
Present AddressNo.1143/A, CH1/A, Geetha Road, Chamarajapuram, Mysore , Mysore , Karnataka - 570005
Permanent AddressNo.1143/A, CH1/A, Geetha Road, Chamarajapuram, Mysore , Mysore , Karnataka - 570005
Official AddressNo.1143/A, CH1/A, Geetha Road, Chamarajapuram, Mysore , Mysore , Karnataka - 570005
Sl No.
Sl No._1

Modification Plan Details

Type of InventoryOpen Plots with Dimension 12*ODD
No of Inventory8
Carpet Area (Sq Mtr)2622 Sq Mtr
Area of exclusive balcony/verandah (Sq Mtr)0 Sq Mtr
Area of exclusive open terrace if any (Sq Mtr)0 Sq Mtr

Residential Plot Details

Sl No.Plot No.Plot TypePlot SizePlot AreaPhaseStageNorth DimensionSouth DimensionEast DimensionWest DimensionNorth Schedule DimensionSouth Schedule DimensionEast Schedule DimensionWest Schedule Dimension
11SITE140.4140.41115.615.699A KharabROADSite No 2Pvt Property
22SITE236.34236.341115.615.610.1520.15A KharabROADROADSite No 1
33SITE102.6102.61112.34.81212Site No 4ROADSite No 19 & 20ROAD
44SITE10810811991212Site No 5Site No 3Site No 18 & 19ROAD
55SITE10810811991212Site No 6Site No 4Site No 17 & 18ROAD
66SITE10810811991212Site No 7Site No 5Site No 16 &17ROAD
77SITE10810811991212Site No 8SiteNo 6Site No 15 &16ROAD
88SITE10810811991212Site No 9Site No 7Site No 15 & 14ROAD
99SITE10810811991212Site No 10Site No 8Site No 13 & 14ROAD
1010SITE192192119.7522.251212Pvt PropertySite No 9Site No.11,12,13ROAD
1111SITE35.3435.3411991212Pvt PropertySite No 12ROADSite No 10
1212SITE81.981.911991212Site No 11Site No 13ROADSite No 10
1313SITE10810811991212Site No 12Site No 14ROADSite No 9,10
1414SITE10810811991212Site No 13Site No 15ROADSite No 9,8
1515SITE10810811991212Site No 14Site No 16ROADSite No 8,7
1616SITE1081081199122Site No 15Site No 17ROADSite No 7,6
1717SITE10810811991212Site No 16Site No 18ROADSite No 5,6
1818SITE10810811991212Site No 17Site No 19ROADSite No 4,5
1919SITE10810811991212Site No 18Site No 20ROADSite No 3,4
2020SITE108108118.1515.651212Site No 19ROADROADSite No 3
2121SITE142.8142.81112.319.81212Site No 22ROADSite No 38 & 37ROAD
2222SITE192.6192.611991212Site No 23Site No 21Site No 37 & 36ROAD
2323SITE10810811991221Site No 24Site No 22Site No 36,35ROAD
2424SITE10810811991212Site No 25Site No 23Site No 35ROAD
2525SITE10810811991212Site No 26Site No 24Site No 34,35ROAD
2626SITE10810811991212Site No 27Site No 25Site No 33,34ROAD
2727SITE10810811991212Site No 28Site No 26Site No 33,32ROAD
2828SITE10810811991212Sy No 29Site No 27Site No 32ROAD
2929SITE10810811991212Sy No 30Site No 28Site No 32,31ROAD
3030SITE108108118.511.751212Pvt PropertySite No 29Site No 31ROAD
3131SITE121.5121.511991212SY NOSY NOSY NOSY NO
3232SITE26626611991212SY NOSY NOSY NOSY NO
3333SITE26626611991212SY NOSY NOSY NOSY NO
3434SITE26626611991212SY NOSY NOSY NOSY NO
3535SITE26626611991212SY NOSY NOSY NOSY NO
3636SITE26626611991212SY NOSY NOSY NOSY NO
3737SITE26626611991212SY NOSY NOSY NOSY NO
3838SITE26626611991212SY NOSY NOSY NOSY NO

Project Development Schedule

Sl NoProject WorkIs Applicable ?Estimated From DateEstimated To Date
1Ground Clearance/Formation Of PlotsYes05-07-201815-07-2018
2Formation Of Road, FootpathYes16-07-201825-07-2018
3Construction Of Water Supply InfrastuctureYes12-10-201810-11-2018
4Construction Of Sewage System InfrastuctureYes11-11-201818-03-2019
5Power Supply Work(Transformer & Substation)Yes05-01-201920-04-2019
6Construction Of Storm Water DrainageYes12-10-201810-11-2018
7Solid Waste Management and DisposalYes11-11-201818-03-2019
8Tree Plantation And LandScape WorkYes20-06-201908-07-2019
9Street LightingYes11-11-201818-03-2019
10Sewage Treatment Plant (STP)Yes10-02-201925-02-2019
11Other Miscellaneous WorkNo

Amenities & Utilities Availability

SlNo.WorkIs Applicable ?
1ElectricityYes
2Smart home automationNo
3CCTV surveillanceNo
4Club HouseNo
5Community HallNo
6Outdoor Sports facilityNo
7Indoor sports facilityNo
8Swimming PoolsNo
9GymNo
10ParksYes
11Power BackupNo
12Piped GasNo
13Water and SanitationNo
14Air conditioningNo

Post Registration Details

Total number of Plots38
No. of Public and Semi Pubic Sites1
Area of Public and Semi Pubic Sites(in Sq.m)622
No. of Parks and Open Spaces1
Area of Parks and Open Spaces(in Sq.m)1246
Area of Road/Transportation(in Sq.m)4531

Completion Details

Project Start Date14-12-2016
Project End Date08-07-2019
If any extension of time has been grantedNO
Cost of land27183000
Cost of construction6950000
Total cost341333000
Total amount collected From buyers0
Whether any loan has been raisedNO
Total amount spent on Project for completion of the project37515286
Total No of sites of Project38
Total No of sites sold0
Total No of sites unsold38
Whether there is any changes in inventory detailsNO

Appeals & Complaints

Complaints on PromoterNo Complaints Found.
Complaints on ProjectNo Complaints Found.

Top Properties in Mysore

Pexo Icon

Ask Pulse Ai anything about real estate

Unlock the Latest in Real Estate

News, Infographics, Blogs & More! Delivered to your inbox.

Proptech Pulse Logo

Data that drives action.
Insight that inspires action.
Technology that empowers action.“

Made with Love

Statue

© PropTech Pulse 2026, All rights reserved.

Terms of Use and Privacy Policy