SANKALP TIARA

SANKALP CONSTRUCTIONS PRIVATE LIMITED

NO 106 8TH MAIN , JAYALAKSHMIPURAM DEVRAJAMOHALA

Approved

13th Aug 2021

Completed

31st Jul 2025

Registration No.

PRM/KA/RERA/1268/378/PR/210813/004272

Acknowledgement No.

ACK/KA/RERA/1268/378/PR/210712/005072

Project Type

Residential/Group Housing

Approving Authority

Mysuru Urban Development Authority

District

Mysore

Taluka

MYSORE

State

Karnataka

Project Details

Project NameSANKALP TIARA
Project DescriptionRESIDENTIAL PROJECT
Project TypeResidential/Group Housing
Project StatusNew Project Launch
Project Start Date10-07-2021
Proposed Project Completion Date31-07-2025
Total Area Of Land (Sq Mtr)812
Total Coverd Area (Sq Mtr)350
Total Open Area (Sq Mtr)462
Estimated Cost of Construction (INR)47148000
Cost of Land (INR)1000000
Total Project Cost (INR)48148000
Project AddressNO 106 8TH MAIN , JAYALAKSHMIPURAM DEVRAJAMOHALA
DistrictCoimbatore
TalukMYSORE
Approving AuthorityMysuru Urban Development Authority
No of Garage for Sale0
Area of Garage for Sale (Sq Mtr)0
No of Parking for Sale0
Area of Parking for Sale (Sq Mtr)0
Type of InventoryRESIDENTIAL FLATS
No of Inventory8
Carpet Area (Sq Mtr)1073SqMtr
Area of exclusive balcony/verandah (Sq Mtr)178SqMtr
Area of exclusive open terrace if any (Sq Mtr)0SqMtr
Road SystemSelf Development
Water SupplyLocal Authority
Sewege and Drainage SystemLocal Authority
Electricity Supply Transformer And Sub StationSelf Development
Solid Waste Management And DisposalLocal Authority
Fire Fighting facilityLocal Authority
Drinking Water FacilityLocal Authority
Emergency Evacuation ServicesLocal Authority
Use of Renewable EnergyLocal Authority
Bank NameSTATE BANK OF INDIA
BranchKUVEMPUNAGAR BRANCH
ifscCodeSBIN0040441
Account No.(70% Account)42074332854
StateTamil Nadu
NameSAMRAJ CONSTURCIONS
Address60 A 7th Street Tatabad,Coimbatore
Pin Code641012
Year Of Establishment1998
Number Of Project Completed22

Promoter Details

Promoter TypeCompany
NameSANTHOSH KUMAR
PAN NumberAACCS5166N
AddressNO 1155 & 1156 VIJAYANAGAR 1ST STAGE DEVARAJA MOHALLA MYSORE
DistrictMysore
State/UTKarnataka
PIN Code570002
Company Registration No.08 10315
TypeOthers
Pin Code570017
Project NameSANKALP SKY VILLAS
Project DescriptionRESIDENTIAL PROJECT
Current StatusOngoing
Type of LandResidential
Expected Completion Date30-04-2024
Sl No.

Modification Plan Details

Type of InventoryRESIDENTIAL FLATS
No of Inventory8
Carpet Area (Sq Mtr)1073 Sq Mtr
Area of exclusive balcony/verandah (Sq Mtr)178 Sq Mtr
Area of exclusive open terrace if any (Sq Mtr)0 Sq Mtr

Project Development Schedule

Sl NoProject WorkIs Applicable ?Estimated From DateEstimated To Date
1Earth work and other leveling preparation workYes13-08-202130-11-2021
2Foundation footing workYes01-12-202128-02-2022
3Retaining wall (All types)Yes01-03-202230-04-2022
4Plinth level BeamYes01-05-202230-06-2022
5Sub-structure flooring (Parking Floor, more than one floor below general ground level)Yes01-07-202231-08-2022

Amenities & Utilities Availability

SlNo.WorkIs Applicable ?
1Water SupplyYes
2Internal Roads & FootpathsNo
3Sewage and Drainage SystemYes
4Parks & Tree plantingYes
5Street LightingYes
6Provision for community buildings and for treatment and disposal of sewage and sullage waterYes
7Solid waste management and disposalYes
8Water conservationYes
9Energy managementYes
10Fire protection and fire safety requirementsNo
11Education/Health/Other public amenitiesNo
12Electricity supply transformer and substationYes

Post Registration Details

FAR Sanctioned1.75
Number of Towers1
00
12
22
32
42
Total No of Units8

Completion Details

Project Start Date10-07-2021
Project End Date31-07-2025
If any extension of time has been grantedNO
Cost of land1000000
Cost of construction47148000
Total project cost48148000
Total amount collected from buyers34017363
Whether any loan has been raisedYES
Total amount spent for completion of the project44265570
Balance amount with the promoter0
Total number of Flats/Apartments of the Project8
Total number of Flats/Apartments sold3
Total number of Flats/Apartments Unsold5
Whether the project has been completed within the stipulated Period?YES
Whether there is any Change in inventory list or specification?NO
As built drawing approved by the planning AuthorityYES
Occupancy certificate received?YES
Occupancy certificate received date11-07-2023

Appeals & Complaints

Appeals / FNHNO APPEALS / FNH
Complaints on PromoterNo Complaints Found.
Complaints on ProjectNo Complaints Found.

Top Properties in Udupi

Pexo Icon

Ask Pulse Ai anything about real estate

Unlock the Latest in Real Estate

News, Infographics, Blogs & More! Delivered to your inbox.

Proptech Pulse Logo

Data that drives action.
Insight that inspires action.
Technology that empowers action.“

Made with Love

Statue

© PropTech Pulse 2026, All rights reserved.

Terms of Use and Privacy Policy