Project Details
| Project Name | Srirampura layout project |
| Project Description | development of layout in 26 guntas of land at srirampura sy.no 78/3B2 |
| Project Type | Plotted Development |
| Project Status | New Project Launch |
| Project Start Date | 15-02-2019 |
| Proposed Project Completion Date | 30-09-2029 |
| Total Area Of Land (Sq Mtr) | 2607 |
| Total Coverd Area (Sq Mtr) | 0 |
| Total Open Area (Sq Mtr) | 2607 |
| Estimated Cost of Construction (INR) | 2500000 |
| Cost of Land (INR) | 2500000 |
| Total Project Cost (INR) | 5000000 |
| Project Address | Sy.no 78/3B2, next to pinnacle pearl, near srirampura telephone exchange |
| District | Hassan |
| Taluk | MYSORE |
| Approving Authority | Mysuru Urban Development Authority |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 0 |
| Area of Parking for Sale (Sq Mtr) | 0 |
| Road System | Self Development |
| Water Supply | Self Development |
| Sewege and Drainage System | Self Development |
| Electricity Supply Transformer And Sub Station | Self Development |
| Solid Waste Management And Disposal | Local Authority |
| Fire Fighting facility | Local Authority |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Local Authority |
| Bank Name | STATE BANK OF INDIA |
| Branch | Hassan city |
| ifscCode | SBIN0011259 |
| Account No.(70% Account) | 20330421934 |
| State | Karnataka |
Promoter Details
| Firm Type | Individual |
| Name | Uma Bs |
| Father's Name | shamanna |
| PAN Number | AAO******* |
| Address | #1076 SUKRUTHA ,10th Cross KR Puram |
| State/UT | Karnataka |
| PIN Code | 573201 |
Residential Plot Details
| Sl No. | Plot No. | Plot Type | Plot Size | Plot Area | Phase | Stage | North Dimension | South Dimension | East Dimension | West Dimension | North Schedule Dimension | South Schedule Dimension | East Schedule Dimension | West Schedule Dimension |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 1 | na | 9 12 | 108 | on going | process | 9 | 9 | 12 | 12 | private layout | road | private layout | s no 2 |
| 2 | 2 | na | 9 12 | 108 | on going | process | 9 | 9 | 12 | 12 | private layout | road | s no 1 | s no 3 |
| 3 | 3 | na | 9 12 | 108 | on going | process | 9 | 9 | 12 | 12 | private layout | road | s no 2 | s no 4 |
| 4 | 4 | na | 9 12 | 108 | on going | process | 9 | 9 | 12 | 12 | private layout | road | s no 3 | s no 5 |
| 5 | 5 | na | 9 12 | 108 | on going | process | 9 | 9 | 12 | 12 | private layout | road | s no 4 | private layout |
| 6 | 6 | na | 9 12 | 108 | on going | process | 12 | 12 | 9 | 9 | road | site no 6 | road | private layout |
| 7 | 7 | na | 9 12 | 108 | on going | process | 12 | 12 | 9 | 9 | site no 6 | siteno 7 | road | private layout |
| 8 | 8 | na | 9 12 | 108 | on going | process | 12 | 12 | 9 | 9 | siteno 7 | site no 8 | road | private layout |
| 9 | 9 | na | 9 12 | 108 | on going | process | 12 | 12 | 9 | 9 | site no 8 | private layout | road | private layout |
| 10 | 10 | na | 15 18 | 108 | on going | process | 15 | 15 | 18 | 18 | park | private layout | private layout | road |
Project Development Schedule
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Ground Clearance/Formation Of Plots | Yes | 21-05-2019 | 22-01-2021 |
| 2 | Formation Of Road, Footpath | No | ||
| 3 | Construction Of WaterSupply Infrastucture | No | ||
| 4 | Construction Of Sewage System Infrastucture | No | ||
| 5 | Power Supply Work(Tansformer And Substation) | No | ||
| 6 | Construction Of Storm Water Drainage | No | ||
| 7 | Solid Waste Management and Disposal | No | ||
| 8 | Tree Plantation And LandScape Work | No | ||
| 9 | Street Lighting | No | ||
| 10 | Other Miscellaneous Work | No |
Amenities & Utilities Availability
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Electricity | Yes |
| 2 | Smart home automation | No |
| 3 | CCTV surveillance | No |
| 4 | Club House | No |
| 5 | Community Hall | No |
| 6 | Outdoor Sports facility | No |
| 7 | Indoor sports facility | No |
| 8 | Swimming Pools | No |
| 9 | Gym | No |
| 10 | Parks | Yes |
| 11 | Power Backup | No |
| 12 | Gas | No |
| 13 | Water and Sanitation | No |
| 14 | Air conditioning and incarnation | No |
Post Registration Details
| Total number of Plots | 10 |
| No. of Public and Semi Pubic Sites | 0 |
| Area of Public and Semi Pubic Sites(in Sq.m) | 0 |
| No. of Parks and Open Spaces | 1 |
| Area of Parks and Open Spaces(in Sq.m) | 457 |
| Area of Road/Transportation(in Sq.m) | 693 |
Completion Details
| Project Start Date | 15-02-2019 |
| Project End Date | 30-09-2029 |
| If any extension of time has been granted | NO |
| Cost of land | 2500000 |
| Cost of construction | 2500000 |
| Total cost | 5000000 |
| Total amount collected From buyers | 0 |
| Whether any loan has been raised | NO |
| Total amount spent on Project for completion of the project | 2150000 |
| Total No of sites of Project | 10 |
| Total No of sites sold | 5 |
| Total No of sites unsold | 5 |
| Whether there is any changes in inventory details | NO |
Appeals & Complaints
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in