Project Details

Number of Survey No./CMC No./CTS No./PID No.2
Is there any Litigations on Land/Property/Khatha?NO

Promoter Details

Type of FirmProprietorship
Promoter NameM B S Infrastructure
Main ObjectivesBuying lands and developing them into plots and selling them to the general public
Legal NameSyed Afsar
Trade NameM B S Infrastructure
Registration Number29ENQPS4822F1ZE
PANENQPS4822F
GSTIN29ENQPS4822F1ZE
Promoter WebsiteNA
Promoter AddressOpposite Jumma Masjid Complex, Ground Floor, BH Road, Kyathsandra Post, ,Tumkur ,Tumakuru ,Tumakuru-572104
DistrictTumakuru
TalukTumakuru
PIN Code572104
Name of Authorized SignatorySyed Afsar
Is there any RERA Registrations in other State / UT ?NO
Is there any Projects Launched In The Past 5 Years in Karnataka ?NO
Present AddressOpposite Jumma Masjid Complex, Ground Floor, BH Road, Kyathsandra Post, Tumkur , Tumakuru , Karnataka - 572104
Permanent AddressSame as above , Tumakuru , Karnataka - 572104
Official AddressSame as above , Tumakuru , Karnataka - 572104
Sl No.

Modification Plan Details

Type of InventoryPlots
No of Inventory21
Carpet Area (Sq Mtr)5615 Sq Mtr
Area of exclusive balcony/verandah (Sq Mtr)0 Sq Mtr
Area of exclusive open terrace if any (Sq Mtr)0 Sq Mtr

Residential Plot Details

Sl No.Plot No.Plot TypePlot SizePlot AreaPhaseStageNorth DimensionSouth DimensionEast DimensionWest DimensionNorth Schedule DimensionSouth Schedule DimensionEast Schedule DimensionWest Schedule Dimension
11EF11.13X15.24169.62EastNA11.1311.1315.2415.24Park AreaSite 2RoadSite 6
22EF9.14X15.24139.29EastNA9.149.1415.2415.24Site 1Site 3RoadSite 5
33EF9.45X15.24139.29EastNA9.459.4515.2415.24Site 2Sy No 113RoadSite 4
44WF9.14X15.24144.02WestNA9.459.4515.2415.24Site 5Sy No 113Site 3Road
55WF9.14X15.24139.29WestNA9.149.1415.2415.24Site 6Site 4Site 2Road
66WF11.13X15.24169.62WestNA11.1311.1315.2415.24Park AreaSite 5Site 1Road
77EF ODD11.13X15.24169.62EastNA11.1311.1315.2415.24Park AreaSite 8RoadSite12
88EF ODD9.14X15.24139.29EastNA9.149.1415.2415.24Site 7Site 9RoadSite 11
99EF ODD8.70X15.24132.58EastNA8.78.715.2415.24Site 8Sy No 113RoadSite 10
1010WF ODD9.70X15.24147.83WestNA9.79.715.2415.24Site 11Sy No 113Site 9Road
1111WF ODD9.14X15.24139.29WestNA9.149.1415.2415.24Site 12Site 10Site 8Road
1212WF ODD11.13X15.24169.62WestNA11.1311.1315.2415.24Park AreaSite 11Site 7Road
1313EF ODD11.13X15.24169.62EastNA11.1311.1315.2415.24Park AreaSite 14RoadSite 18
1414EF ODD9.14X15.24139.29EastNA9.149.1415.2415.24Site 13Site 15RoadSite 17
1515EF ODD9.54X15.24145.38EastNA9.549.5415.2415.24Site 14Sy No 113RoadSite 16
1616WF ODD10.40X15.24158.5WestNA10.410.415.2415.24Site 16Sy No 113Site 15Road
1717WF ODD9.14X15.24139.29WestNA9.149.1415.2415.24Site 18Site 16Site 14Road
1818WF ODD11.13X15.24169.62WestNA11.1311.1315.2415.24Park AreaSite 17Site 13Road
1919CS NE ODD10.40X11.60120.64North EastNA11.611.610.410.4RoadSy No 113RoadSite 20
2020NF ODD9.14X11.60106.02NorthNA11.611.69.149.14RoadSy No 113Site 19Site 21
2121NF ODD9.14X10.6096.88NorthNA10.610.69.149.14RoadSy No 113Site 20CA

Project Development Schedule

Sl NoProject WorkIs Applicable ?Estimated From DateEstimated To Date
1Ground Clearance/Formation Of PlotsYes05-12-202330-04-2024
2Formation Of Road, FootpathYes16-05-202430-07-2024
3Construction Of Water Supply InfrastuctureYes02-08-202431-10-2024
4Construction Of Sewage System InfrastuctureYes02-11-202431-01-2025
5Power Supply Work(Transformer & Substation)Yes05-02-202530-04-2025
6Construction Of Storm Water DrainageNo
7Solid Waste Management and DisposalNo
8Tree Plantation And LandScape WorkNo
9Street LightingYes03-05-202530-08-2025
10Sewage Treatment Plant (STP)No
11Other Miscellaneous WorkYes05-09-202530-12-2025

Amenities & Utilities Availability

SlNo.WorkIs Applicable ?
1ElectricityYes
2Smart home automationNo
3CCTV surveillanceNo
4Club HouseNo
5Community HallNo
6Outdoor Sports facilityNo
7Indoor sports facilityNo
8Swimming PoolsNo
9GymNo
10ParksYes
11Power BackupNo
12Piped GasNo
13Water and SanitationYes
14Air conditioningNo

Post Registration Details

Total number of Plots21
No. of Public and Semi Pubic Sites0
Area of Public and Semi Pubic Sites(in Sq.m)0
No. of Parks and Open Spaces1
Area of Parks and Open Spaces(in Sq.m)563
Area of Road/Transportation(in Sq.m)1738

Completion Details

Project Start Date05-12-2023
Project End Date31-03-2026
If any extension of time has been grantedNO
Cost of land4797257
Cost of construction11484954
Total cost16282211
Total amount collected From buyers0
Whether any loan has been raisedNO
Total amount spent on Project for completion of the project16286971
Total No of sites of Project21
Total No of sites sold0
Total No of sites unsold21
Whether there is any changes in inventory detailsNO

Appeals & Complaints

Complaints on PromoterNo Complaints Found.
Complaints on ProjectNo Complaints Found.

Top Properties in Mangalore

Pexo Icon

Ask Pulse Ai anything about real estate

Unlock the Latest in Real Estate

News, Infographics, Blogs & More! Delivered to your inbox.

Proptech Pulse Logo

Data that drives action.
Insight that inspires action.
Technology that empowers action.“

Made with Love

Statue

© PropTech Pulse 2026, All rights reserved.

Terms of Use and Privacy Policy