Alevoor Business Centre
Karthik Shetty
Guddeangadi, , Alevoor, Udupi
Approved
2nd Jun 2018
Completed
29th Dec 2021
Registration No.
PRM/KA/RERA/1273/318/PR/180602/001860
Acknowledgement No.
ACK/KA/RERA/1273/318/PR/180507/002233
Project Type
Commercial
Approving Authority
Udupi Urban Development Authority
District
Udupi
Taluka
Udupi
State
Karnataka
Project Details
| Project Name | Alevoor Business Centre |
| Project Description | A state of art commercial centre is an upcoming commercial project developed in Guddeangadi, Alevoor, with options for retail shops and office spaces designed to cater growing development in the region |
| Project Type | Commercial |
| Project Status | Completed |
| Project Start Date | 20-04-2018 |
| Proposed Project Completion Date | 29-12-2021 |
| Total Area Of Land (Sq Mtr) | 830 |
| Total Coverd Area (Sq Mtr) | 185 |
| Total Open Area (Sq Mtr) | 645 |
| Estimated Cost of Construction (INR) | 7050000 |
| Cost of Land (INR) | 1210500 |
| Total Project Cost (INR) | 8260500 |
| Project Address | Guddeangadi, , Alevoor, Udupi |
| District | Udupi |
| Taluk | Udupi |
| Approving Authority | Udupi Urban Development Authority |
| No of Garage for Sale | 0 |
| Area of Garage for Sale (Sq Mtr) | 0 |
| No of Parking for Sale | 5 |
| Area of Parking for Sale (Sq Mtr) | 69 |
| Road System | Local Authority |
| Water Supply | Local Authority |
| Sewege and Drainage System | Local Authority |
| Electricity Supply Transformer And Sub Station | Local Authority |
| Solid Waste Management And Disposal | Local Authority |
| Fire Fighting facility | Local Authority |
| Drinking Water Facility | Local Authority |
| Emergency Evacuation Services | Local Authority |
| Use of Renewable Energy | Local Authority |
| Bank Name | CORPORATION BANK |
| Branch | Alevoor |
| ifscCode | CORP0000229 |
| Account No.(70% Account) | 510101002965185 |
| State | Karnataka |
Promoter Details
| Firm Type | Individual |
| Name | Karthik Shetty |
| Father's Name | Y. Karunakar Shetty |
| PAN Number | BAQ******* |
| Address | Ashray Near Panchayath Office,Post Alevoor Udupi |
| State/UT | Karnataka |
| PIN Code | 574118 |
Project Development Schedule
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 20-04-2018 | 27-04-2018 |
| 2 | Foundation footing work | Yes | 25-04-2018 | 25-05-2018 |
| 3 | Retaining wall (All types) | No | ||
| 4 | Plinth level Beam | Yes | 24-05-2018 | 10-06-2018 |
| 5 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | No |
Amenities & Utilities Availability
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Internal Roads & Footpaths | No |
| 3 | Sewage and Drainage System | Yes |
| 4 | Parks & Tree planting | No |
| 5 | Street Lighting | No |
| 6 | Provision for community buildings and for treatment and disposal of sewage and sullage water | No |
| 7 | Solid waste management and disposal | No |
| 8 | Water conservation | No |
| 9 | Energy management | No |
| 10 | Fire protection and fire safety requirements | No |
| 11 | Education/Health/Other public amenities | No |
Post Registration Details
| FAR Sanctioned | 1.0 |
| Number of Towers | 1 |
| 0 | 6 |
| 1 | 12 |
| 2 | 12 |
| Total No of Units | 30 |
Completion Details
| Project Start Date | 20-04-2018 |
| Project End Date | 29-12-2021 |
| If any extension of time has been granted | NO |
| Cost of land | 1210500 |
| Cost of construction | 7050000 |
| Total project cost | 8260500 |
| Total amount collected from buyers | 0 |
| Whether any loan has been raised | NO |
| Total amount spent for completion of the project | 9000000 |
| Balance amount with the promoter | 0 |
| Total number of Flats/Apartments of the Project | 30 |
| Total number of Flats/Apartments sold | 0 |
| Total number of Flats/Apartments Unsold | 30 |
| Whether the project has been completed within the stipulated Period? | YES |
| Whether there is any Change in inventory list or specification? | NO |
| As built drawing approved by the planning Authority | YES |
| Occupancy certificate received? | YES |
| Occupancy certificate received date | 17-08-2018 |
Appeals & Complaints
| Appeals / FNH | NO APPEALS / FNH |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in