MS M D DEVELOPERS
Kundapura
Approved
15th Jun 2022
Pending
31st Dec 2029
Registration No.
PRM/KA/RERA/1273/320/PR/150622/004986
Acknowledgement No.
ACK/KA/RERA/1273/320/PR/210222/005699
Project Type
Mixed Development
District
Udupi
Taluka
Kundapura
State
Karnataka
| Number of Survey No./CMC No./CTS No./PID No. | 8 |
| Is there any Litigations on Land/Property/Khatha? | NO |
| Type of Firm | Partnership Firm |
| Promoter Name | MS M D DEVELOPERS |
| Main Objectives | DEVELOPEMENT OF RESIDENTIAL PROJECT |
| Registration Number | UDPF195200910 |
| PAN | AGKPP7304A |
| GSTIN | 29AARFM8653Q1ZZ |
| Promoter Address | NANDI COMPOUND, VEERESHWARA TEMPLE ROAD, GANGOLI,,KUNDAPURA TALUK, UDUPI ,Kundapura ,Udupi-576216 |
| District | Udupi |
| Taluk | Kundapura |
| PIN Code | 576216 |
| Name of Authorized Signatory | MAHABALA K POOJARI |
| Number of Partners | 4 |
| Is there any RERA Registrations in other State / UT ? | NO |
| Is there any Projects Launched In The Past 5 Years in Karnataka ? | YES |
| Project Name | M D RESIDENCY |
| Project Description | GROUND FLOOR+9 FLOOR RESIDENTIAL AND COMMERCIAL BUILDING |
| Type of Project | Mixed Development |
| Current Status | Completed |
| Is there any case pending ? | YES |
| Is Payment Pertaining to Project Land Pending ? | NO |
| Project Address | Hemmadi village, Kundapura taluk, Udupi District |
| State/UT | Karnataka |
| Pin Code | 576230 |
| Present Address | S/O KRISHNA POOJARI, HEMMADY MANE, NANDI COMPOUND, GANGOLI, UDUPI , Udupi , Karnataka - 576216 |
| Permanent Address | S/O KRISHNA POOJARI, HEMMADY MANE, NANDI COMPOUND, GANGOLI, UDUPI , Udupi , Karnataka - 576216 |
| Official Address | M D Residency, No.12, 1st Floor, , Tallur Post, Tallur-Kollur Road, Kundapura Taluk , Udupi , Karnataka - 576230 |
| Sl No. | |
| Sl No._1 | |
| Sl No._2 |
| Type of Inventory | 3 BHK |
| No of Inventory | 7 |
| Carpet Area (Sq Mtr) | 884 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 50 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 19-02-2022 | 30-08-2022 |
| 2 | Foundation footing work | Yes | 01-09-2022 | 30-03-2023 |
| 3 | Upto Plinth Level | Yes | 01-04-2023 | 30-10-2023 |
| 4 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 01-11-2023 | 31-12-2029 |
| 5 | Retaining wall (All types) | Yes | 01-11-2023 | 31-12-2029 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Sewage and Drainage System | No |
| 3 | Water conservation/rain water harvesting/recharge of ground water | Yes |
| 4 | Energy management | Yes |
| 5 | Fire protection and fire safety requirements | Yes |
| 6 | Solid waste management and disposal | No |
| 7 | Emergency Evacuation services | Yes |
| FAR Sanctioned | 2.5 |
| Number of Towers | 1 |
| 0 | 0 |
| 1 | 4 |
| 2 | 18 |
| 3 | 17 |
| 4 | 10 |
| 5 | 9 |
| 6 | 8 |
| 7 | 9 |
| 8 | 8 |
| 9 | 8 |
| 10 | 8 |
| Total No of Units | 99 |
| Complaints on Project | No Complaints Found. |