NAYAK CONSTRUCTIONS & DEVELOPERS
Udupi
Approved
16th Apr 2025
Pending
31st Dec 2030
Registration No.
PRM/KA/RERA/1273/318/PR/160425/007673
Acknowledgement No.
ACK/KA/RERA/1273/318/PR/110425/009123
Project Type
Residential/Group Housing
District
Udupi
Taluka
Udupi
State
Karnataka
| Number of Survey No./CMC No./CTS No./PID No. | 1 |
| Is there any Litigations on Land/Property/Khatha? | NO |
| Type of Firm | Partnership Firm |
| Promoter Name | NAYAK CONSTRUCTIONS & DEVELOPERS |
| Main Objectives | DEVELOPMENT OF RESIDENTIAL PROJECT |
| Registration Number | UDP-F150-2016-17 |
| PAN | ABNPN8726G |
| GSTIN | 29AANFN3983G1ZO |
| Promoter Address | #301, ND SANKALPA, 101/8, ISHWARNAGARA,MANIPAL, UDUPI-576104 ,Udupi ,Udupi-576104 |
| District | Udupi |
| Taluk | Udupi |
| PIN Code | 576104 |
| Name of Authorized Signatory | B. JAGADEESH NAYAK |
| Number of Partners | 4 |
| Is there any RERA Registrations in other State / UT ? | NO |
| Is there any Projects Launched In The Past 5 Years in Karnataka ? | YES |
| Project Name | ND SAURABHA |
| Project Description | STILT+GROUND+3 FLOORS |
| Type of Project | Residential |
| Current Status | Completed |
| Is there any case pending ? | NO |
| Is Payment Pertaining to Project Land Pending ? | NO |
| Project Address | PROPOSED CONSTRUCTION OF RESIDENTIAL APARTMENT BUILDING WITH COMPOUND WALL IN, S.NO-101/29 AT HERGA VILLAGE, UDUPI |
| State/UT | Karnataka |
| Pin Code | 576101 |
| Present Address | #1/59 BAIDERBETTY HERGA VILLAGE UDUPI-576101 , Udupi , Karnataka - 576101 |
| Permanent Address | #1/59 BAIDERBETTY HERGA VILLAGE UDUPI-576101 , Udupi , Karnataka - 576101 |
| Official Address | #301, ND SANKALPA, 101/8, ISHWARNAGARA, MANIPAL, UDUPI-576104 , Udupi , Karnataka - 576104 |
| Sl No. | |
| Sl No._1 | |
| Sl No._2 |
| Type of Inventory | 2 BHK |
| No of Inventory | 24 |
| Carpet Area (Sq Mtr) | 1903 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 510 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 10-04-2025 | 15-05-2025 |
| 2 | Foundation footing work | Yes | 16-05-2025 | 15-07-2025 |
| 3 | Upto Plinth Level | Yes | 01-06-2025 | 30-07-2025 |
| 4 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 01-07-2025 | 31-12-2026 |
| 5 | Retaining wall (All types) | Yes | 01-07-2025 | 31-12-2025 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Sewage and Drainage System | Yes |
| 3 | Water conservation/rain water harvesting/recharge of ground water | Yes |
| 4 | Energy management | No |
| 5 | Fire protection and fire safety requirements | No |
| 6 | Solid waste management and disposal | No |
| 7 | Emergency Evacuation services | No |
| FAR Sanctioned | 1.98 |
| Number of Towers | 1 |
| 0 | 0 |
| 1 | 0 |
| 2 | 6 |
| 3 | 6 |
| 4 | 6 |
| 5 | 6 |
| 6 | 6 |
| 7 | 6 |
| Total No of Units | 36 |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |