V.P BUILDERS
Udupi
Approved
29th Nov 2024
Pending
31st Dec 2029
Registration No.
PRM/KA/RERA/1273/318/PR/291124/007260
Acknowledgement No.
ACK/KA/RERA/1273/318/PR/081124/008651
Project Type
Residential/Group Housing
District
Udupi
Taluka
Udupi
State
Karnataka
| Number of Survey No./CMC No./CTS No./PID No. | 1 |
| Is there any Litigations on Land/Property/Khatha? | NO |
| Type of Firm | Proprietorship |
| Promoter Name | V.P BUILDERS |
| Main Objectives | DEVELOPMENT OF RESIDENTIAL PROJECT |
| Trade Name | V.P BUILDERS |
| Registration Number | NA |
| PAN | AJJPA6711G |
| GSTIN | 29AJJPA6711G1ZD |
| Promoter Address | GROUND FLOOR, 1-4-33 E, VISHAL APARTMENTS,GUNDIBAIL, KUNJIBETTU, UDUPI -576102 ,Udupi ,Udupi-576102 |
| District | Udupi |
| Taluk | Udupi |
| PIN Code | 576102 |
| Name of Authorized Signatory | K PRASAD ACHARYA |
| Is there any RERA Registrations in other State / UT ? | NO |
| Is there any Projects Launched In The Past 5 Years in Karnataka ? | YES |
| Project Name | SRI VENKATESHA |
| Project Description | RESIDENTIAL AND COMMERCIAL APARTMENT |
| Type of Project | Mixed Development |
| Current Status | Completed |
| Is there any case pending ? | NO |
| Is Payment Pertaining to Project Land Pending ? | NO |
| Project Address | S NO 102-19 102-26 MOODANIDAMBUR VILLAGE SHIRIBEEDU WARD , BEHIND KEDIYUR HOTEL , UDUPI |
| State/UT | Karnataka |
| Pin Code | 576101 |
| Present Address | NISARGA AMBAGILU SHIVALLI VILLAGE UDUPI , Udupi , Karnataka - 576102 |
| Permanent Address | NISARGA AMBAGILU SHIVALLI VILLAGE UDUPI , Udupi , Karnataka - 576102 |
| Official Address | GROUND FLOOR, 1-4-33 E, VISHAL APARTMENTS, GUNDIBAIL, KUNJIBETTU, UDUPI -576102 , Udupi , Karnataka - 576102 |
| Sl No. | |
| Sl No._1 |
| Type of Inventory | 3 BHK |
| No of Inventory | 18 |
| Carpet Area (Sq Mtr) | 2046 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 572 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Earth work and other leveling preparation work | Yes | 15-11-2024 | 31-12-2024 |
| 2 | Foundation footing work | Yes | 01-01-2025 | 20-02-2025 |
| 3 | Upto Plinth Level | Yes | 15-01-2025 | 28-02-2025 |
| 4 | Sub-structure flooring (Parking Floor, more than one floor below general ground level) | Yes | 01-03-2025 | 31-12-2025 |
| 5 | Retaining wall (All types) | Yes | 01-04-2025 | 31-12-2025 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Water Supply | Yes |
| 2 | Sewage and Drainage System | Yes |
| 3 | Water conservation/rain water harvesting/recharge of ground water | Yes |
| 4 | Energy management | No |
| 5 | Fire protection and fire safety requirements | No |
| 6 | Solid waste management and disposal | Yes |
| 7 | Emergency Evacuation services | No |
| FAR Sanctioned | 1.9 |
| Number of Towers | 1 |
| 0 | 0 |
| 1 | 8 |
| 2 | 8 |
| 3 | 8 |
| 4 | 8 |
| 5 | 8 |
| Total No of Units | 40 |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |